Question

In: Finance

Question: Building a new refinery The construction and installation of a new refinery will cost $22...

Question:

Building a new refinery

The construction and installation of a new refinery will cost $22 million. In addition, a processing plant will also need to be constructed at a cost $6 million. This plant will need to be supplied with grinding machines, DMS flotation machines and other equipment at a total cost of $16 million. Kidman Resources' current fleet of Haul trucks, water carts and dump trucks will meet the needs for this project, however until recently, the fleet has been earning a rental income of $120,000 per year.

Under the agreement with Tesla inc., the lithium mined is expected to generate a revenue of $15 million per year, which will increase by 2.8% per annum adjusted for rising costs. Due to the additional complexities involved with the construction and management of this new refinery, 5 new engineers (yearly salary per engineer $160,000) will replace 5 existing engineers (yearly salary per engineer $120,000). All other remaining labour force required is expected to cost $3 million per annum for the duration of the project.

For tax reasons you will expense the cost of the processing plant immediately. The cost for the construction and installation of the new refinery and associated machines and equipment will be depreciated over three years using the straight-line method. Due to the nature of the mining project, the machines and equipment will likely have a salvage value of $10 million at the end of three years. Finally, the required net working capital is $2 million.

Calculate Net Present Value given rate of return = 10% and tax rate= 30%

Solutions

Expert Solution

Formula Year (n) 0 1 2 3
New refinery cost & equipment cost Initial investment (II)         (38,000,000)
Increasing at 2.8% p.a. Revenue ('R)            15,000,000            15,420,000            15,851,760
Opportunity cost of rental income lost (O)               (120,000)               (120,000)               (120,000)
Annual salary increase from 120,000 to 160,000 for 5 engineers Salary cost increase (S)               (200,000)               (200,000)               (200,000)
Labor force cost (L)             (3,000,000)             (3,000,000)             (3,000,000)
(II/3) Depreciation (D)         (12,666,667)         (12,666,667)         (12,666,667)
Processing plant cost (P)             (6,000,000)
(R-O-S-L-D-P) EBIT             (6,000,000)               (986,667)               (566,667)               (134,907)
(30%*EBIT) Tax @30%               1,800,000                  296,000                  170,000                     40,472
(EBIT - Tax) Net income (NI)             (4,200,000)               (690,667)               (396,667)                   (94,435)
Add: depreciation (D)                               -              12,666,667            12,666,667            12,666,667
(NI+ D) Operating Cash Flow (OCF)             (4,200,000)            11,976,000            12,270,000            12,572,232
NWC will be recovered in Year 2 Increase in NWC             (2,000,000)               2,000,000
salvage value*(1-Tax rate) Salvage value (after-tax) SV)               7,000,000
(II + OCF + NWC + SV) Free Cash Flow (FCF)         (44,200,000)            11,976,000            12,270,000            21,572,232
1/(1+d)^n Discount factor @10%                        1.000                        0.909                        0.826                        0.751
(FCF*Discount factor) PV of FCF (44,200,000.00)      10,887,272.73      10,140,495.87      16,207,537.19
Sum of all PVs NPV       (6,964,694.21)

This project has a negative NPV of - 6,964,694.21


Related Solutions

Option 1: Building a new refinery The construction and installation of a new refinery will cost...
Option 1: Building a new refinery The construction and installation of a new refinery will cost $22 million. In addition, a processing plant will also need to be constructed at a cost $6 million. This plant will need to be supplied with grinding machines, DMS flotation machines and other equipment at a total cost of $16 million. Kidman Resources’ current fleet of Haul trucks, water carts and dump trucks will meet the needs for this project, however until recently, the...
Option 1: Building a new refinery The construction and installation of a new refinery will cost...
Option 1: Building a new refinery The construction and installation of a new refinery will cost $22 million. In addition, a processing plant will also need to be constructed at a cost $6 million. This plant will need to be supplied with grinding machines, DMS flotation machines and other equipment at a total cost of $16 million. Kidman Resources’ current fleet of Haul trucks, water carts and dump trucks will meet the needs for this project, however until recently, the...
You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
UVW began construction of a new office building on March 1, Y1. On the day construction...
UVW began construction of a new office building on March 1, Y1. On the day construction began, UVW borrowed $240,000 at 7% and immediately spent it on the project. An additional payment of $60,000 was also made on the day construction began. Additional expenditures of $75,000 were made on May 1 and August 31. Construction was complete and the building was placed in service on December 31, Y1. In addition to the $240,000 borrowed to finance the project, UVW also...
At the beginning of 2018, Heinz Corp. started construction on a new office building. Construction expenditures...
At the beginning of 2018, Heinz Corp. started construction on a new office building. Construction expenditures during 2018 were as follows: January 1                     $400,000 May 1                          150,000 July 1                         300,000   December 31               100,000    Heinz has the following debts outstanding during 2018; the bonds payable is directly related to the construction projects; none of the others are related to the construction project. Liability Annual Percent Loan Amount Notes Payable 4% $200,000 Bonds Payable 6% $400,000 Mortgage Payable 5% $300,000
Company purchases a new punch press at a cost of $265,000. Delivery and installation cost $46,000....
Company purchases a new punch press at a cost of $265,000. Delivery and installation cost $46,000. The machine has a useful life of 12-years, but will depreciate using MACRS over a seven year property class, 1. What is the cost basis of the machine 2. What will be the depreciation allowance each year over the seven years 3. If we sell the machine at the end of five years for $70,000, what will be the gain/loss tax assuming a 40%...
A new machine will cost $600,000 including delivery and installation. The new unit has a CCA...
A new machine will cost $600,000 including delivery and installation. The new unit has a CCA depreciation rate of 25 percent. At the end of four years, it will be sold for $100,000. The net working capital requirement required at the beginning of the first four years are $50,000, $60,000, $70,000, and $60,000. In the first year, revenue will increase by $150,000 and operating costs will decrease by $30,000. The difference between them, R−C, will grow at 3 percent. The...
3. A new machine will cost $600,000 including delivery and installation. The new unit has a...
3. A new machine will cost $600,000 including delivery and installation. The new unit has a CCA depreciation rate of 25 percent. At the end of four years, it will be sold for $100,000. The net working capital requirement required at the beginning of the rst four years are $50,000, $60,000, $70,000, and $60,000. In the rst year, revenue will increase by $150,000 and operating costs will decrease by $30,000. The dierence between them, R?C, will grow at 3 percent....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT