Question

In: Accounting

UVW began construction of a new office building on March 1, Y1. On the day construction...

  1. UVW began construction of a new office building on March 1, Y1. On the day construction began, UVW borrowed $240,000 at 7% and immediately spent it on the project. An additional payment of $60,000 was also made on the day construction began. Additional expenditures of $75,000 were made on May 1 and August 31. Construction was complete and the building was placed in service on December 31, Y1. In addition to the $240,000 borrowed to finance the project, UVW also has $2,000,000 of other debt at 5% outstanding for the entire year.

    What is the balance in the building account on the December 31, Y1 balance sheet?

    230,250

    8,750

    345,250

    20,250

    21,050

    None of the other answer choices is correct.

    470,250

    471,050

    564,000

    450,000

Solutions

Expert Solution

Capitalizable value of asset:
Date Particulars Amount
Mar-01 Construction Cost $    2,40,000.00
Mar-01 Construction Cost $       60,000.00
May-01 Construction Cost $       75,000.00
Aug-31 Construction Cost $       75,000.00
Interest (WN.-1) $       20,250.00
Capitalizable value of asset $   4,70,250.00
working notes 1:
Computation of Interest to be capitalized:
Date Amount of Loan Interest
Mar-01 $ 2,40,000.00 $ 14,000.00 ($ 240,000 * 7.00% * 10/12)
Mar-01 $     60,000.00 $ 2,500.00 ($ 60,000 * 5.00% * 10/12)
May-01 $     75,000.00 $ 2,500.00 ($ 75,000 * 5.00% * 8/12)
Aug-31 $     75,000.00 $ 1,250.00 ($ 75,000 * 5.00% * 4/12)
Interest to be capitalized $ 20,250.00
THREFORE THE ANSWER IS $470250

Related Solutions

On March 1, 2020, Reed hired a contractor to construct a new office building. The construction...
On March 1, 2020, Reed hired a contractor to construct a new office building. The construction work commenced on April 1, 2020, and it is expected to continue through July 31, 2022, the estimated completion date. Reed made progress payments to the contractor in 2020 as follows: Date Amount April 1 $ 48,000 June 1 195,000 September 1 322,000 November 1 67,000 $632,000 As stated in A5 above, Reed took a 1-year, 9%, $225,000 construction loan to help fund the...
On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 11% $ 1,800,000 Long-term note, 10% 2,400,000 Long-term note, 7% 4,800,000 Calculate the amount of interest capitalized in 2018 for the building using the specific...
On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 10% $ 1,800,000 Long-term note, 9% 2,400,000 Long-term note, 6% 4,800,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the...
On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $9,900,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 10% $ 2,475,000 Long-term note, 9% 3,300,000 Long-term note, 6% 6,600,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred...
On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred for construction: March 1 $315,000 April 1 254,000 May 1 751,500 June 1 1,152,000 July 1 391,000 The building was completed and occupied on July 1. To help pay for construction $215,000 was borrowed on March 1 on a 12%, three-year note payable. The only other debt outstanding during the year was a $2,000,000, 10% note issued two years ago. Calculate the weighted-average accumulated...
On March 1, Imhoff Co. began construction of a small building. Payments of $400,000 were made...
On March 1, Imhoff Co. began construction of a small building. Payments of $400,000 were made monthly for four months beginning March 1. The building was completed and ready for occupancy on June 1. In determining the amount of interest cost to be capitalized, the weighted-average accumulated expenditures are? How would I calculate this? You probably will answer that $400,000 * ((3/12)+(2/12)+1/12))=200,000 But Why is that weighted as 3/12, 2/12 and 1/12 if the project was outstanding just for 3...
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building...
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building was completed on June 30, 2016. Cash outlays for the $5 million project were as follows: 2015 January 1                        $1,000,000 March 1                          $600,000 June 30                           $800,000 September 30               $750,000 December 1                   $600,000 2016 March 31                        $800,000 June 30                           $450,000 (final payment) Total payments             $5,000,000 On January 1, 2015 Costco obtained a $3 million dollar construction loan with a 5% interest rate. Costco’s other long-term...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 326,000 September 1, 2021 $ 477,000 December 31, 2021 $ 477,000 March 31, 2022 $ 477,000 September 30, 2022 $ 326,000 Dreamworld had $5,900,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT