In: Accounting
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows:
May 1 | $3,300,000 |
July 30 | 2,200,000 |
September 1 | 1,740,000 |
October 1 | 2,640,000 |
MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021.
Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar]
Date | Expenditure | Months financed (out of 7) | WA Accum Exp |
March 28** | $ 998,600 | 7 | 998,600 |
April 30** | 148,000 | 6 | 126,857 |
May 1 | 3,300,000 | ||
July 30 | 2,200,000 | ||
September 1 | 1,740,000 | ||
October 1 | 2,640,000 | ||
Total |
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows:
May 1 | $3,300,000 |
July 30 | 2,200,000 |
September 1 | 1,740,000 |
October 1 | 2,640,000 |
MMI borrowed $5,000,000 at 6% on May 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021.
Avoidable interest on the building was:
WA Accum Expend | 5,771,171 | Avoidable Interest | Actual Interest | |
construction loan | 6% | |||
note payable | 8% | |||
Total | ||||
[Hint: Lesser of Avoidable or Actual Interest is capitalized.]
The building would be recorded on the balance sheet as:
Total expenditures | 9,880,000 |
Capitalized interest | |
Total historical cost |