In: Accounting
Option 1: Building a new refinery
The construction and installation of a new refinery will cost $22 million. In addition, a processing plant will also need to be constructed at a cost $6 million. This plant will need to be supplied with grinding machines, DMS flotation machines and other equipment at a total cost of $16 million. Kidman Resources’ current fleet of Haul trucks, water carts and dump trucks will meet the needs for this project, however until recently, the fleet has been earning a rental income of $120,000 per year.
Under the agreement with Tesla inc., the lithium mined is expected to generate a revenue of $15 million per year, which will increase by 2.8% per annum adjusted for rising costs. Due to the additional complexities involved with the construction and management of this new refinery, 5 new engineers (yearly salary per engineer $160,000) will replace 5 existing engineers (yearly salary per engineer $120,000). All other remaining labour force required is expected to cost $3 million per annum for the duration of the project.
For tax reasons you will expense the cost of the processing plant
immediately. The cost for the construction and installation of the
new refinery and associated machines and equipment will be
depreciated over three years using the straight-line method. Due to
the nature of the mining project, the machines and equipment will
likely have a salvage value of $10 million at the end of three
years. Finally, the required net working capital is $2 million.
Option 2: Outsourcing the supply of ore
Alternatively, Kidman Resources can contract BHP to supply the required ore to process into lithium hydroxide. Based on the required amount of lithium hydroxide, management has quoted a total cost of $28 million. BHP has however offered this rate on the condition that Kidman Resources pays 20% of the total cost in advance in the beginning of the year, with the remaining paid in equal instalments thereafter. Kidman Resources will process the ore into lithium hydroxide using existing facilities at an expected cost of $4.4 million per year.
Calculate NPV for option 1 and 2. Tax rate= 28%, discount rate= 10%