Question

In: Accounting

At the beginning of 2018, Heinz Corp. started construction on a new office building. Construction expenditures...

At the beginning of 2018, Heinz Corp. started construction on a new office building. Construction expenditures during 2018 were as follows:

January 1                     $400,000

May 1                          150,000

July 1                         300,000  

December 31               100,000   

Heinz has the following debts outstanding during 2018; the bonds payable is directly related to the construction projects; none of the others are related to the construction project.

Liability

Annual Percent

Loan Amount

Notes Payable

4%

$200,000

Bonds Payable

6%

$400,000

Mortgage Payable

5%

$300,000

Solutions

Expert Solution

Actual interest expenditure incurred:
Principal Interest % Interest
expenditure
1 2 1*2
6 % Bonds payable-Specific loan for construction 400000 6% 24000
4% note-General purpose 200000 4% 8000
5% Mortgage payable-General purpose 300000 5% 15000
47000
Avoidable interest=Weighted average accumulated expenditure*interest rate
Weighted average accumulated expenditure:
Date Expense Capitalization
period
Weight Weighted
expenditure
A B C=B/12 A*C
1-Jan 400000 12 months 1.00 400000
1-May 150000 8 months 0.67 100000
1-Jul 300000 6 months 0.50 150000
31-Dec 100000 0 months 0.00 0
650000
Weighted average interest rate for general purpose notes:
Principal Interest % Interest
expenditure
4% note-General purpose 200000 4% 8000
5% Mortgage payable-General purpose 300000 5% 15000
500000 23000
Weighted average interest rate=23000/500000=4.60%
Avoidable interest:
Principal Interest % Interest
expenditure
Specific note 400000 6% 24000
General note 250000 4.60% 11500
(650000-400000)
35500
Interest to be capitalized=Lower of actual interest or avoidable interest=Lower of 47000 or 35500=35500
Hence interest to be charged to expense=Actual interest-Interest capitalized=47000-35500=11500

Related Solutions

In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in early 2010 and was completed in 2011. The following additional information is available:                                                                                                    2010                       2011        Costs incurred............................................................. $ 2,430,000            $ 2,700,000        Estimated costs to complete............................................. 2,600,000                         —        Collections during the year.............................................. 2,400,000               3,600,000          Billings for the year …………………………………………..     2,800,000                3,200,000 Used the percentage-of-completion method. Instructions Under the contract-based approach, a)     How much revenue should be reported...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available: 2019 2020 Cost Incurred $1,458,000 $1,620,000 Estimated costs to complete 1,560,000 - Billed 1,700,000 1,900,000 Collections during the year 1,440,000 2,160,000 Miller uses the percentage-of-completion method. Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019 and 2020? b) Prepare all journal entries for 2019...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available:                                                                                           2019               2020        Costs incurred...................................................... $1,458,000          $1,620,000        Estimated costs to complete.................................. 1,560,000                         —        Billed ……………………………………………….    1,700,000           1,900,000        Collections during the year.................................... 1,440,000            2,160,000 Miller uses the percentage-of-completion method. Instructions Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019...
A company made the following expenditures in connection with the construction of its new building: Architect’s...
A company made the following expenditures in connection with the construction of its new building: Architect’s fees for the new building $25,000 Cash paid for land and run-down building on the land 425,000 Removal of old building 17,500 Salvage from sale of old building materials 6,000 Construction survey to site the new building 3,500 Legal fees for title search 4,500 Excavation for basement construction 45,500 Machinery purchased for operations 250,000 Storage charges on machinery because building was not ready when...
ABC Furniture Company started construction of a office building for it’s own use at an estimated...
ABC Furniture Company started construction of a office building for it’s own use at an estimated cost of $5,000,000 on January 1, 2016. ABC expected to complete the building by December 31, 2016. ABC has the following debt obligations outstanding during the construction period. Construction Loan­ 12% interest, payable semiannually, issued December 31, 2015 $2,000,000 Short Term Loan ­ 10% interest, payable monthly, and principal payable at maturity on May 30, 2017 $1,400,000 Long­term loan – 11% interest, payable on...
The Furniture Company started construction of a combination office and warehouse building for its own use...
The Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $14,500,000 on January 1, 2020. The Furniture Company expected to complete the building by December 31, 2020. The Furniture Company has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,800,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 4,060,000 Long-term loan-11% interest, payable...
NashFurniture Company started construction of a combination office and warehouse building for its own use at...
NashFurniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,500,000 on January 1, 2020. Nash expected to complete the building by December 31, 2020. Nash has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,800,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 1,260,000 Long-term loan-11% interest, payable on January 1 of each...
On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 11% $ 1,800,000 Long-term note, 10% 2,400,000 Long-term note, 7% 4,800,000 Calculate the amount of interest capitalized in 2018 for the building using the specific...
On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 10% $ 1,800,000 Long-term note, 9% 2,400,000 Long-term note, 6% 4,800,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the...
On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $9,900,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 10% $ 2,475,000 Long-term note, 9% 3,300,000 Long-term note, 6% 6,600,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT