Problem 12-9
Assume that you are the manager of a shop that assembles power
tools. You have just received an order for 60 chain saws, which are
to be shipped at the start of week 8. Pertinent information on the
saws is
Item | Lead Time (weeks) | On Hand | Components | |
Saw | 2 | 15 | A(2), B(1), C(4) | |
A | 1 | 10 | E(3), D(1) | |
B | 2 | 5 | D(2), F(3) | |
C | 2 | 65 | E(2), D(2) | |
D | 1 | 20 | ||
E | 1 | 10 | ||
F | 2 | 30 | ||
Develop the material requirements plan for component E using
lot-for-lot ordering. (Leave no cells blank - be certain to
enter "0" wherever required.)
Item: E(3) & E(2) LT = 1 wk. | Beg. Inv. | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | |||||||||
Scheduled receipts | |||||||||
Projected on hand | |||||||||
Net requirements | |||||||||
Planned order receipt | |||||||||
Planned order release | |||||||||
Information given is as under:
Product structure is shown below:
Component E is required in Component A and Component C.
To derive the MRP for Component E, the MRP of Item Saw, Component A and Component C has to be derived first.
60 units of Chain Saw is to be shipped in beginning of week 8, so it should be ready by end of week 7. Hence the gross requirement is 60 in Week 7.
Item: Saw LT = 2 wk. |
Beg. Inv. |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
Gross requirements |
0 |
0 |
0 |
0 |
0 |
0 |
60 |
0 |
|
Scheduled receipts |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Projected on hand |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
0 |
0 |
Net requirements |
0 |
0 |
0 |
0 |
0 |
0 |
45 |
0 |
|
Planned order receipt |
0 |
0 |
0 |
0 |
0 |
0 |
45 |
0 |
|
Planned order release |
0 |
0 |
0 |
0 |
45 |
0 |
0 |
0 |
|
Item: A LT = 1 wk. |
Beg. Inv. |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
Gross requirements |
0 |
0 |
0 |
0 |
90 |
0 |
0 |
0 |
|
Scheduled receipts |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Projected on hand |
10 |
10 |
10 |
10 |
10 |
0 |
0 |
0 |
0 |
Net requirements |
0 |
0 |
0 |
0 |
80 |
0 |
0 |
0 |
|
Planned order receipt |
0 |
0 |
0 |
0 |
80 |
0 |
0 |
0 |
|
Planned order release |
0 |
0 |
0 |
80 |
0 |
0 |
0 |
0 |
|
Item: C LT = 2 wk. |
Beg. Inv. |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
Gross requirements |
0 |
0 |
0 |
0 |
180 |
0 |
0 |
0 |
|
Scheduled receipts |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Projected on hand |
65 |
65 |
65 |
65 |
65 |
0 |
0 |
0 |
0 |
Net requirements |
0 |
0 |
0 |
0 |
115 |
0 |
0 |
0 |
|
Planned order receipt |
0 |
0 |
0 |
0 |
115 |
0 |
0 |
0 |
|
Planned order release |
0 |
0 |
115 |
0 |
0 |
0 |
0 |
0 |
|
Therefore the MRP of Item E is as shown below: |
|||||||||
Item: E(3) & E(2) LT = 1 wk. |
Beg. Inv. |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
Gross requirements |
0 |
0 |
230 |
240 |
0 |
0 |
0 |
0 |
|
Scheduled receipts |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Projected on hand |
10 |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
Net requirements |
0 |
0 |
220 |
240 |
0 |
0 |
0 |
0 |
|
Planned order receipt |
0 |
0 |
220 |
240 |
0 |
0 |
0 |
0 |
|
Planned order release |
0 |
220 |
240 |
0 |
0 |
0 |
0 |
0 |
Excel working is shown below: