In: Operations Management
Assume that you are the manager of a shop that assembles power
tools. You have just received an order for 59 chain saws, which are
to be shipped at the start of week 8. Pertinent information on the
saws is
Item | Lead Time (weeks) | On Hand | Components | |
Saw | 2 | 15 | A(2), B(1), C(4) | |
A | 1 | 10 | E(3), D(1) | |
B | 2 | 5 | D(2), F(3) | |
C | 2 | 65 | E(2), D(2) | |
D | 1 | 20 | ||
E | 1 | 10 | ||
F | 2 | 30 | ||
Develop the material requirements plan for component E using
lot-for-lot ordering. (Leave no cells blank - be certain to
enter "0" wherever required.)
Item: E(3) & E(2) LT = 1 wk. | Beg. Inv. | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | |||||||||
Scheduled receipts | |||||||||
Projected on hand | |||||||||
Net requirements | |||||||||
Planned order receipt | |||||||||
Planned order release | |||||||||