Assume that you are the manager of a shop that assembles power tools. You have just...

Assume that you are the manager of a shop that assembles power tools. You have just received an order for 59 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is

Item Lead Time (weeks) On Hand     Components
Saw 2 15         A(2), B(1), C(4)
A 1 10         E(3), D(1)
B 2 5         D(2), F(3)
C 2 65         E(2), D(2)
D 1 20      
E 1 10      
F 2 30      
a. Develop the material requirements plan for component E using lot-for-lot ordering. (Leave no cells blank - be certain to enter "0" wherever required.)
  Item: E(3) & E(2) LT = 1 wk.       Beg. Inv.        1      2      3      4      5     6     7     8
  Gross requirements
  Scheduled receipts   
  Projected on hand
  Net requirements
  Planned order receipt
  Planned order release

Solutions

Expert Solution

First calculate the material requirement for each component -

Components

Gross requirement

Stock On-hand

Net requirement = (Gross requirement – Stock in hand)

Saw

59

15

59 -15 = 44

A

Net requirement of Saw *2 = 44 * 2 =88

10

88 -10 = 78

B

Net requirement of Saw *1 = 44 * 1 = 44

5

44 -5 = 39

C

Net requirement of Saw *4 = 44 * 4 =176

65

176 -65 = 110

D

Net requirement of A *1 + Net requirement of B *2 + Net requirement of C *2 = 78 *1 + 39 * 2 + 110 *2 = 376

20

376 -20 =356

E

Net requirement of A * 3 + Net requirement of C *2 = 78 * 3 + 110 *2 = 454

10

454 -10 = 444

F

Net requirement of B *3 = 39 * 3 = 117

30

117 -30 = 87

Gross requirement of each sub-components are calculated based on net requirement of their main components multiplied by number of sub-components required for each component.

The material requirement plan for component E:

  • 78*3 = 234 number of component E required for component A at the week 5 as the lead time of component A is 1 weeks and lead time for end product Saw is also 2 weeks; [8 weeks – (1+2) weeks = 5 weeks]
  • 110 * 2 =220 number of component E required for component C at the week 4 as the lead time of component C is 2 week and lead time for end product Saw is also 2 weeks; [8 weeks – (2+2) weeks = 4 weeks]

The material requirements plan for component E using lot-for-lot ordering

Item E(3) & E(2) Period Inv          1          2          3          4          5          6          7          8
Gross requirements 0 0 0 220 234 0 0 0
OH = 10 Scheduled receipts 0 0 0 0 0 0 0 0
LT = 1 Projected On Hand 10 10 10 10 0 0 0 0 0
Q = L4L Net requirements 0 0 0 210 234 0 0 0
Planned order receipts 0 0 0 210 234 0 0 0
Planned order releases 0 0 210 234 0 0 0 0

Related Solutions

Assume that you are the manager of a shop that assembles power tools. You have just...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 50 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30 b. Develop the...
Assume that you are the manager of a shop that assembles power tools. You have just...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 50 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30 b. Develop the...
Assume that you are the manager of a shop that assembles power tools. You have just...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 59 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30    Develop the...
Assume that you are the manager of a shop that assembles power tools. You have just...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 59 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand     Components Saw 2 15         A(2), B(1), C(4) A 1 10         E(3), D(1) B 2 5         D(2), F(3) C 2 65         E(2), D(2) D 1 20       E 1 10      ...
Problem 12-9 Assume that you are the manager of a shop that assembles power tools. You...
Problem 12-9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 60 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30   ...
HR Management Tools and Teams Directions: You have just been hired as an HR manager in...
HR Management Tools and Teams Directions: You have just been hired as an HR manager in a health care setting. Select a health care organization of interest. You decide to prepare for your first day on the job by creating a document that compiles tools to manage staffing, increase work production, and improve team dynamics. Complete all four parts. Part 1: Organization Selection Selected Health Care Organization: Part 2: Staffing and Work Production As a HR manager, your serve the...
Assume you have just been appointed a project manager for building a female hostel at the...
Assume you have just been appointed a project manager for building a female hostel at the University Campus area. Prepare the procurement plan to be submitted to the management
Case Six   Power/Influence    You have just been hired as the project manager on a major project...
Case Six   Power/Influence    You have just been hired as the project manager on a major project that is critical to the company’s success.  Eight people from different functional specialties have been assigned to your project team.  About forty percent of their time will be devoted to the project.  They take their direction from you with respect to the project but are not under your direct authority as they continue to do other work and continue to report to their current manager.   Question: Describe...
Assume you have just been hired as a Finance Manager of Anjung Puteri. The company’s earnings...
Assume you have just been hired as a Finance Manager of Anjung Puteri. The company’s earnings before interest and taxes (EBIT) was RM500,000 last year and is expected to remain constant over time. Since no expansion capital will be required, Anjung Puteri plans to pay out all earnings as dividends. The management group owns fifty percent (50%) of the stock and the rest is traded in the over-the-counter market. In your finance course, you learned that most firm owners would...
Assume you have just been hired as a Finance Manager of Anjung Puteri. The company’s earnings...
Assume you have just been hired as a Finance Manager of Anjung Puteri. The company’s earnings before interest and taxes (EBIT) was RM500,000 last year and is expected to remain constant over time. Since no expansion capital will be required, Anjung Puteri plans to pay out all earnings as dividends. The management group owns fifty percent (50%) of the stock and the rest is traded in the over-the-counter market. In your finance course, you learned that most firm owners would...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT