Question

In: Operations Management

Assume that you are the manager of a shop that assembles power tools. You have just...

Assume that you are the manager of a shop that assembles power tools. You have just received an order for 59 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is

Item Lead Time (weeks) On Hand     Components
Saw 2 15         A(2), B(1), C(4)
A 1 10         E(3), D(1)
B 2 5         D(2), F(3)
C 2 65         E(2), D(2)
D 1 20      
E 1 10      
F 2 30      
a. Develop the material requirements plan for component E using lot-for-lot ordering. (Leave no cells blank - be certain to enter "0" wherever required.)
  Item: E(3) & E(2) LT = 1 wk.       Beg. Inv.        1      2      3      4      5     6     7     8
  Gross requirements
  Scheduled receipts   
  Projected on hand
  Net requirements
  Planned order receipt
  Planned order release

Down below is my results. The numbers in BOLD are INCORRECT.

  Item: E(3) & E(2) LT = 1 wk.       Beg. Inv.        1      2      3      4      5     6     7     8
  Gross requirements 0 0 0 0 220 234 0 0 0
  Scheduled receipts
  Projected on hand 10 10 10 10 10 0 0 0 0
  Net requirements 0 0 0 0 210 234 0 0 0
  Planned order receipt 0 0 0 0 210 234 0 0 0
  Planned order release 0 0 0 210 234 0 0 0 0

Solutions

Expert Solution

As per bill of material;

For every unit of A we need 3 units of E; for every unit of C we need 2 unit of E.

Saw is made of 2 units of A and 4 units of C

We will first focus primarily on A and C MRP to final total gross requirement for E.

Total 59 chain saws are needed by end of week 7

We will first create MRP plan for A and C as below:

Saw has 2 weeks lead time and needed by week 8 hence gross requirement for C will be in week 6. 2 units of A is required for each Saw. Already 15 units of Saw on hand so net requirement for Saw is 59-15=44
  Item: A Lead time: 1week       Beg. Inv.        1      2      3      4      5     6     7     8
  Gross requirements (59-15)*2=88
  Scheduled receipts   
  Projected on hand 10 10 10 10 10 10 78+10-88=0
  Net requirements 88-10=78
  Planned order receipt 78
  Planned order release 78
Saw has 2 weeks lead time and needed by week 8 hence gross requirement for C will be in week 6. 4 units of C is required for each Saw
  Item: C Lead time: 2 weeks       Beg. Inv.        1      2      3      4      5     6     7     8
  Gross requirements (59-15)*4=176
  Scheduled receipts   
  Projected on hand 65 65 65 65 65 65 111+65-176=0
  Net requirements 176-65=111
  Planned order receipt 111
  Planned order release 111

For every unit of A we need 3 units of E; for every unit of C we need 2 unit of E.

Now, basis above the gross requirement for E is 3*78=234 in week 5 and 2*111=222 in week 4.

MRP for item E is below

  Item: E(3) & E(2) LT = 1 wk.       Beg. Inv.        1      2      3      4      5     6     7     8
  Gross requirements 2*111=222 3*78=234
  Scheduled receipts   
  Projected on hand 10 10 10 10 212+10-222=0 0
  Net requirements 222-10=212 234
  Planned order receipt 212 234
  Planned order release 212 234

Change BOLD figures (210) with 212 to get the correct answer.


  
Please give Thanks if you like my answer. Thank you!


Related Solutions

Assume that you are the manager of a shop that assembles power tools. You have just...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 50 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30 b. Develop the...
Assume that you are the manager of a shop that assembles power tools. You have just...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 50 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30 b. Develop the...
Assume that you are the manager of a shop that assembles power tools. You have just...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 59 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30    Develop the...
Assume that you are the manager of a shop that assembles power tools. You have just...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 59 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand     Components Saw 2 15         A(2), B(1), C(4) A 1 10         E(3), D(1) B 2 5         D(2), F(3) C 2 65         E(2), D(2) D 1 20       E 1 10      ...
Problem 12-9 Assume that you are the manager of a shop that assembles power tools. You...
Problem 12-9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 60 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30   ...
HR Management Tools and Teams Directions: You have just been hired as an HR manager in...
HR Management Tools and Teams Directions: You have just been hired as an HR manager in a health care setting. Select a health care organization of interest. You decide to prepare for your first day on the job by creating a document that compiles tools to manage staffing, increase work production, and improve team dynamics. Complete all four parts. Part 1: Organization Selection Selected Health Care Organization: Part 2: Staffing and Work Production As a HR manager, your serve the...
Assume you have just been appointed a project manager for building a female hostel at the...
Assume you have just been appointed a project manager for building a female hostel at the University Campus area. Prepare the procurement plan to be submitted to the management
Case Six   Power/Influence    You have just been hired as the project manager on a major project...
Case Six   Power/Influence    You have just been hired as the project manager on a major project that is critical to the company’s success.  Eight people from different functional specialties have been assigned to your project team.  About forty percent of their time will be devoted to the project.  They take their direction from you with respect to the project but are not under your direct authority as they continue to do other work and continue to report to their current manager.   Question: Describe...
Assume you have just been hired as a Finance Manager of Anjung Puteri. The company’s earnings...
Assume you have just been hired as a Finance Manager of Anjung Puteri. The company’s earnings before interest and taxes (EBIT) was RM500,000 last year and is expected to remain constant over time. Since no expansion capital will be required, Anjung Puteri plans to pay out all earnings as dividends. The management group owns fifty percent (50%) of the stock and the rest is traded in the over-the-counter market. In your finance course, you learned that most firm owners would...
Assume you have just been hired as a Finance Manager of Anjung Puteri. The company’s earnings...
Assume you have just been hired as a Finance Manager of Anjung Puteri. The company’s earnings before interest and taxes (EBIT) was RM500,000 last year and is expected to remain constant over time. Since no expansion capital will be required, Anjung Puteri plans to pay out all earnings as dividends. The management group owns fifty percent (50%) of the stock and the rest is traded in the over-the-counter market. In your finance course, you learned that most firm owners would...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT