Question

In: Finance

On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...

On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows:

January 1, 2018

$

300,000

September 1, 2018

$

450,000

December 31, 2018

$

450,000

March 31, 2019

$

450,000

Dreamworld had the following debt obligations outstanding during both years:

Construction loan, 10%             $500,000

             Long-term note, 12%                      $2,500,000

Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest from 2018 does not compound in 2019)?

Solutions

Expert Solution

Date Amount incurred No. of months Weighted average amount
a b c=a × b/12
Beg.           1,200,000                         12                 1,200,000
Mar. 31              450,000                           8                     300,000
Accumulated expenditure                 1,500,000
Avoidable interest
Particulars Amount used for contruction Rate of interest Interest
Contruction loan                    500,000 10.0000%      50,000.00
General debt                 1,000,000 12.0000%    120,000.00
Avoidable interest    170,000.00

Capitalized interest is 170,000


Related Solutions

On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $50,000 None...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 336,000 September 1, 2018 $ 504,000 December 31, 2018 $ 504,000 March 31, 2019 $ 504,000 September 30, 2019 $ 336,000 Dreamworld had $6,800,000 in 10% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 307,000 September 1, 2018 $ 459,000 December 31, 2018 $ 459,000 March 31, 2019 $ 459,000 September 30, 2019 $ 307,000 Dreamworld had $5,300,000 in 13% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 326,000 September 1, 2021 $ 477,000 December 31, 2021 $ 477,000 March 31, 2022 $ 477,000 September 30, 2022 $ 326,000 Dreamworld had $5,900,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $300,000 September 1, 2016 $450,000 December 31, 2016 $450,000 March 31, 2017 $450,000 September 30, 2017 $300,000 Dreamworld had $5,000,000 in 12% bonds outstanding through both years. Dreamworld's capitalized interest in 2016 was: a. $72,000 b. $63,000 c. $54,000 d. $36,000
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building...
On January 1, 2015 Costco began construction of a new warehouse in Redmond, WA. The building was completed on June 30, 2016. Cash outlays for the $5 million project were as follows: 2015 January 1                        $1,000,000 March 1                          $600,000 June 30                           $800,000 September 30               $750,000 December 1                   $600,000 2016 March 31                        $800,000 June 30                           $450,000 (final payment) Total payments             $5,000,000 On January 1, 2015 Costco obtained a $3 million dollar construction loan with a 5% interest rate. Costco’s other long-term...
On January 1, 2018, Star Inc. began construction of a new warehouse for its own use....
On January 1, 2018, Star Inc. began construction of a new warehouse for its own use. The warehouse was completed in 2019. Expenditures on the project in 2018 were as follows:             January 1, 2018           $310,000             March 31, 2018           $600,000             September 1, 2018      $720,000 Star borrowed $600,000 on a construction loan at 6% interest rate on January 1, 2018. The loan was outstanding throughout the construction period. During 2018, the company had $300,000 in 4% bonds and $700,000 in 8% notes outstanding. Star’s capitalized...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT