Question

In: Accounting

Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing...

Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $650 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of the Engineering Department, Cost Accounting is providing both unit- and activity-based accounting information (made possible by a recent pilot study producing the activity-based data). Unit-based system: Variable conversion activity rate: $100 per direct labor hour Material usage rate: $25 per part ABC system: Labor usage: $15 per direct labor hour Material usage (direct materials): $20 per part Machining: $85 per machine hour Purchasing activity: $150 per purchase order Setup activity: $3,300 per setup hour Warranty activity: $600 per returned unit (usually requires extensive rework) Customer repair cost: $30 per repair hour (average) Activity and Resource Information (annual estimates) Design A Design B Units produced 20,000 20,000 Direct material usage 350,000 parts 325,000 parts Labor usage 60,000 hours 130,000 hours Machine hours 60,000 70,000 Purchase orders 2,000 1,500 Setup hours 650 250 Returned units 1,100 250 Repair time (customer) 2,200 650 Required: 1. Select the lower-cost design using unit-based costing. - Select your answer -Design ADesign B Are logistical and post-purchase activities considered in this analysis? - Select your answer -YesNo 2. Select the lower-cost design using ABC analysis. - Select your answer -Design ADesign B 3. What if the post-purchase cost was an environmental contaminant and amounted to $15 per unit for Design A and $50 per unit for Design B? Compute the Post-purchase cost for each design. Post-Purchase Cost Design A $ Design B $ Assume that the environmental cost is borne by society. Now which is the better design? - Select your answer -Design ADesign B

Solutions

Expert Solution


Related Solutions

Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing...
Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $550 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system....
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product,...
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $500 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of...
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product,...
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $500 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of...
Kagle design engineers are in the process of developing a new “green” product, one that will...
Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $550 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of the Engineering Department,...
Cornerstone Exercise 11.2 (Algorithmic) Activity-Based Supplier Costing Ventana Company is a car window repair and replacement...
Cornerstone Exercise 11.2 (Algorithmic) Activity-Based Supplier Costing Ventana Company is a car window repair and replacement company operating in the after-sales market. Ventana’s purchasing manager uses two suppliers (Jones Glass and Claro Glass) for the source of its passenger car windows. Data relating to side windows (Side) and windshields (WS) are given below. I. Activity costs Activity Adverse buying* 652,500 Supplier returns** 64,900 * Extra cost of purchasing from local car dealer because of insufficient delivery of supplier. ** Windows...
Cornerstone Exercise 5.3 (Algorithmic) Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm...
Cornerstone Exercise 5.3 (Algorithmic) Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $62,500 Number of moves 2,500 Engineering 113,750 Number of change orders 6,500 Other overhead 343,200 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job...
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced....
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic      Advanced      Total Units produced         150,000         450,000         ------ Prime costs         $10,500,000         $52,200,000         $62,700,000 Machine hours         150,000         750,000         900,000 Engineering hours         400         3,600         4,000 Receiving orders         200         600        ...
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced....
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 80,000 240,000 ------ Prime costs $6,720,000 $27,360,000 $34,080,000 Machine hours 80,000 400,000 480,000 Engineering hours 500 4,500 5,000 Receiving orders 200 600 800 Inspection hours 800 1,600 2,400 Overhead costs: Machining $7,200,000 Engineering 2,250,000 Receiving 192,000 Inspecting products 336,000...
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced....
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic      Advanced      Total Units produced         130,000         390,000         ------ Prime costs         $9,360,000         $39,780,000         $49,140,000 Machine hours         130,000         650,000         780,000 Engineering hours         400         3,600         4,000 Receiving orders         400         1,200        ...
Cornerstone Exercise 11.3 (Algorithmic) Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment...
Cornerstone Exercise 11.3 (Algorithmic) Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below. Frequently Ordering Customers Less Frequently Ordering Customers Sales orders 39,000 3,900 Order size 15 150 Average...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT