Question

In: Accounting

Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product,...

Activity-Based Life-Cycle Costing

Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $500 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of the Engineering Department, Cost Accounting is providing both unit- and activity-based accounting information (made possible by a recent pilot study producing the activity-based data).

Unit-based system:
Variable conversion activity rate: $110 per direct labor hour
Material usage rate: $15 per part

ABC system:
Labor usage: $25 per direct labor hour
Material usage (direct materials): $30 per part
Machining: $80 per machine hour
Purchasing activity: $150 per purchase order
Setup activity: $3,600 per setup hour
Warranty activity: $500 per returned unit (usually requires extensive rework)
Customer repair cost: $35 per repair hour (average)

Activity and Resource Information (annual estimates)

Design A Design B
Units produced 20,000 20,000
Direct material usage 320,000 parts 295,000 parts
Labor usage 55,000 hours 125,000 hours
Machine hours 55,000 65,000
Purchase orders 2,000 1,500
Setup hours 650 250
Returned units 1,100 300
Repair time (customer) 2,000 500

Required:

1. Select the lower-cost design using unit-based costing.

Are logistical and post-purchase activities considered in this analysis?

2. Select the lower-cost design using ABC analysis.

3. What if the post-purchase cost was an environmental contaminant and amounted to $10 per unit for Design A and $40 per unit for Design B? Compute the Post-purchase cost for each design.

Post-Purchase Cost
Design A $fill in the blank 4
Design B $fill in the blank 5

Assume that the environmental cost is borne by society. Now which is the better design?

Solutions

Expert Solution

SOLUTION:

1. lower-cost design using unit-based costing. Are logistical and post-purchase activities considered in this analysis?

Particulars Design A ($) Design B ($)
Material ($ 15 per part) (320,000*15) (295,000*15)
4,800,000 4,425,000
Variable conversion activity rate (55000*110) (125000*110)
($110 per direct labor hour) 6,050,000 13,750,000
Total Cost (A) 10,850,000 18,175,000
Units produced (B) 20,000 20,000
Cost per unit (A/B) 542.5 908.75

The lower cost design using unit based costing is Design A.

However the cost per unit $ 542.5 is greater than the target price $ 500 per unit

Logistical and post purchase activities are NOT considered in this analysis.

2. lower-cost design using ABC analysis.

ABC Analysis

Particulars Design A ($) Design B ($)
Material (320,000*30) (295,000*30)
($ 30 per part) 9,600,000 8,850,000
Labour (55000*25) (125000*25)
($25 per direct labor hour) 1,375,000 3,125,000
Machining (80*55000) (80*65000)
($ 80 per machine hour) 4,400,000 5,200,000
Purchasing (2000*150) (1500*150)
($150 per purchase order) 300,000 225,000
Setup (3600*650) (3600*250)
($ 3600 per setup hours) 2,340,000 900,000
Warranty Activity (500*1100) (500*300)
($ 500 per returned unit) 550,000 150,000
Customer repair Cost (35*2000) (35*500)
($35 per repair hour) 70,000 17,500
Total cost 18,635,000 18,467,500

USING ABC ANALYSIS, THE LOWER COST DESIGN IS DESIGN B.

3. POST PURCHASE COST :

Design A = 20,000 *10 per unit = $ 200,000

Design B = 20,000 *40 per unit = $ 800,000

After taking into consideration the post purchase cost the revised cost is as follows:

There will not be any impact on the cost because the post purchase cost is borne by the society.

Thus Design B is better.


Related Solutions

Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product,...
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $500 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of...
Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing...
Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $550 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system....
Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing...
Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $650 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system....
Kagle design engineers are in the process of developing a new “green” product, one that will...
Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $550 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of the Engineering Department,...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing....
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $462,400. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing....
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $462,400. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing....
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $462,400. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing....
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $462,400. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
The Product Life Cycle Part & The New Product Process 4 stages are 1. introduction 2....
The Product Life Cycle Part & The New Product Process 4 stages are 1. introduction 2. growth 3. maturity 4. decline Assess the value of the product life cycle as a tool for product succession planning and related product management activities. Give your opinion on whether or not the Product Life Cycle can help health care managers in promoting portfolio planning, strategy formulation, and forecasting. Provide one (1) example to support your rationale. Select two (2) stages of the Product...
Companies can choose from different costing methods: process/product costing and activity-based costing. Think about a company...
Companies can choose from different costing methods: process/product costing and activity-based costing. Think about a company you know and answer the following: What are the differences between the two costing methods, and how do these apply to your company? What are some ABC cost drivers the company might use? How could the costs differ if one method is chosen over the other? Which method would you recommend for your company, and why?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT