In: Accounting
Cornerstone Exercise 11.4 (Algorithmic)
Activity-Based Life-Cycle Costing
Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $550 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of the Engineering Department, Cost Accounting is providing both unit- and activity-based accounting information (made possible by a recent pilot study producing the activity-based data).
Unit-based system:
Variable conversion activity rate: $110 per direct labor hour
Material usage rate: $15 per part
ABC system:
Labor usage: $30 per direct labor hour
Material usage (direct materials): $35 per part
Machining: $85 per machine hour
Purchasing activity: $160 per purchase order
Setup activity: $4,000 per setup hour
Warranty activity: $550 per returned unit (usually requires
extensive rework)
Customer repair cost: $35 per repair hour (average)
Activity and Resource Information (annual estimates) |
||||
Design A | Design B | |||
Units produced | 20,000 | 20,000 | ||
Direct material usage | 340,000 | parts | 315,000 | parts |
Labor usage | 50,000 | hours | 120,000 | hours |
Machine hours | 50,000 | 60,000 | ||
Purchase orders | 3,000 | 2,500 | ||
Setup hours | 650 | 300 | ||
Returned units | 1,000 | 300 | ||
Repair time (customer) | 2,100 | 500 |
Required:
1. Select the lower-cost design using
unit-based costing.
- Select your answer -Design ADesign BItem 1
Are logistical and post-purchase activities considered in this
analysis?
- Select your answer -YesNoItem 2
2. Select the lower-cost design using ABC
analysis.
- Select your answer -Design ADesign BItem 3
3. What if the post-purchase cost was an environmental contaminant and amounted to $20 per unit for Design A and $40 per unit for Design B? Compute the Post-purchase cost for each design.
Post-Purchase Cost | ||
Design A | $ | |
Design B | $ |
Assume that the environmental cost is borne by society. Now
which is the better design?
- Select your answer -Design ADesign B
DESIGN A |
|||
UNIT BASIS PER PART |
ABC |
||
$ |
$ |
||
DIRECT MAT |
DIRECT MAT |
||
17 X $15 |
255 |
17 X $35 |
595 |
DIRECT ACTIVITY LABOUR |
DIRECT LABOUR |
||
2.5 HRS X 110 |
275 |
2.5 HRS X $30 |
75 |
TOTAL |
530 |
||
MACHINE HOURS |
|||
2.5 X $85 |
212.50 |
||
PURCHASE ACTIVITY |
|||
.15 X $160 |
24 |
||
SET UP |
|||
.0325 X 4000 |
130 |
||
TOTAL |
1036.50 |
||
DESIGN B |
|||||
UNIT BASIS PER PART |
ABC |
||||
$ |
$ |
||||
Design B |
DIRECT MAT |
DIRECT MAT |
|||
Units produced |
20,000 |
$15 X 15.75 |
236.25 |
$35 X 15.75 |
551.25 |
Direct material usage |
315,000 parts |
DIRECT ACTIVITY ON LABOUR |
DIRECT LABOUR |
||
Labor usage |
120,000 hours |
6 HRS X $110 |
660 |
6 HRS X $30 |
180 |
Machine hours |
60,000 |
||||
Purchase orders |
2,500 |
TOTAL |
896.25 |
MACHINE HOURS |
|
Setup hours |
300 |
3 HRS X $85 |
255 |
||
Returned units |
300 |
PURCHASE ACTIVITY |
|||
Repair time (customer) |
500 |
.125 X 160 |
20 |
||
SET UP |
|||||
.015 X 4000 |
60 |
||||
TOAL |
1066.25 |
||||
QUESTION 1
UNIT COST - DESIGN A
QUESTION 2
ABC - DESIGN A
QUESTION 3 Are logistical and post-purchase
activities considered in this analysis?
- Select your answer –No
3. What if the post-purchase cost was an environmental contaminant and amounted to $20 per unit for Design A and $40 per unit for Design B? Compute the Post-purchase cost for each design.
Post-Purchase Cost |
||
1036.50 |
1066.25 |
|
Design A |
$ 20 |
|
Design B |
$40 |
|
1056.50 |
1106.25 |
Assume that the environmental cost is borne by society. Now
which is the better design?
- Select your answer - Design B