Question

In: Accounting

Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing...

Cornerstone Exercise 11.4 (Algorithmic)
Activity-Based Life-Cycle Costing

Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $550 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of the Engineering Department, Cost Accounting is providing both unit- and activity-based accounting information (made possible by a recent pilot study producing the activity-based data).

Unit-based system:
Variable conversion activity rate: $110 per direct labor hour
Material usage rate: $15 per part

ABC system:
Labor usage: $30 per direct labor hour
Material usage (direct materials): $35 per part
Machining: $85 per machine hour
Purchasing activity: $160 per purchase order
Setup activity: $4,000 per setup hour
Warranty activity: $550 per returned unit (usually requires extensive rework)
Customer repair cost: $35 per repair hour (average)

Activity and Resource Information (annual estimates)

Design A Design B
Units produced 20,000 20,000
Direct material usage 340,000 parts 315,000 parts
Labor usage 50,000 hours 120,000 hours
Machine hours 50,000 60,000
Purchase orders 3,000 2,500
Setup hours 650 300
Returned units 1,000 300
Repair time (customer) 2,100 500

Required:

1. Select the lower-cost design using unit-based costing.
- Select your answer -Design ADesign BItem 1

Are logistical and post-purchase activities considered in this analysis?
- Select your answer -YesNoItem 2

2. Select the lower-cost design using ABC analysis.
- Select your answer -Design ADesign BItem 3

3. What if the post-purchase cost was an environmental contaminant and amounted to $20 per unit for Design A and $40 per unit for Design B? Compute the Post-purchase cost for each design.

Post-Purchase Cost
Design A $
Design B $

Assume that the environmental cost is borne by society. Now which is the better design?
- Select your answer -Design ADesign B

Solutions

Expert Solution

DESIGN A

UNIT BASIS

PER PART

ABC

$

$

DIRECT MAT

DIRECT MAT

17 X $15

255

17 X $35

595

DIRECT ACTIVITY LABOUR

DIRECT LABOUR

2.5 HRS X 110

275

2.5 HRS X $30

75

TOTAL

530

MACHINE HOURS

2.5 X $85

212.50

PURCHASE

ACTIVITY

.15 X $160

24

SET UP

.0325 X 4000

130

TOTAL

1036.50

DESIGN B

UNIT BASIS

PER PART

ABC

$

$

Design B

DIRECT MAT

DIRECT MAT

Units produced

20,000

$15 X 15.75

236.25

$35 X 15.75

551.25

Direct material usage

315,000 parts

DIRECT ACTIVITY ON LABOUR

DIRECT LABOUR

Labor usage

120,000 hours

6 HRS X $110

660

6 HRS X $30

180

Machine hours

60,000

Purchase orders

2,500

TOTAL

896.25

MACHINE HOURS

Setup hours

300

3 HRS X $85

255

Returned units

300

PURCHASE

ACTIVITY

Repair time (customer)

500

.125 X 160

20

SET UP

.015 X 4000

60

TOAL

1066.25

QUESTION 1

UNIT COST - DESIGN A

QUESTION 2

ABC   -   DESIGN A

QUESTION 3 Are logistical and post-purchase activities considered in this analysis?
- Select your answer –No  

3. What if the post-purchase cost was an environmental contaminant and amounted to $20 per unit for Design A and $40 per unit for Design B? Compute the Post-purchase cost for each design.

Post-Purchase Cost

1036.50

1066.25

Design A

$ 20

Design B

$40

1056.50

1106.25

Assume that the environmental cost is borne by society. Now which is the better design?
- Select your answer - Design B


Related Solutions

Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing...
Cornerstone Exercise 11.4 (Algorithmic) Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $650 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system....
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product,...
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $500 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of...
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product,...
Activity-Based Life-Cycle Costing Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $500 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of...
Kagle design engineers are in the process of developing a new “green” product, one that will...
Kagle design engineers are in the process of developing a new “green” product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed $550 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of the Engineering Department,...
Cornerstone Exercise 11.2 (Algorithmic) Activity-Based Supplier Costing Ventana Company is a car window repair and replacement...
Cornerstone Exercise 11.2 (Algorithmic) Activity-Based Supplier Costing Ventana Company is a car window repair and replacement company operating in the after-sales market. Ventana’s purchasing manager uses two suppliers (Jones Glass and Claro Glass) for the source of its passenger car windows. Data relating to side windows (Side) and windshields (WS) are given below. I. Activity costs Activity Adverse buying* 652,500 Supplier returns** 64,900 * Extra cost of purchasing from local car dealer because of insufficient delivery of supplier. ** Windows...
Cornerstone Exercise 5.3 (Algorithmic) Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm...
Cornerstone Exercise 5.3 (Algorithmic) Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $62,500 Number of moves 2,500 Engineering 113,750 Number of change orders 6,500 Other overhead 343,200 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job...
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced....
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic      Advanced      Total Units produced         150,000         450,000         ------ Prime costs         $10,500,000         $52,200,000         $62,700,000 Machine hours         150,000         750,000         900,000 Engineering hours         400         3,600         4,000 Receiving orders         200         600        ...
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced....
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 80,000 240,000 ------ Prime costs $6,720,000 $27,360,000 $34,080,000 Machine hours 80,000 400,000 480,000 Engineering hours 500 4,500 5,000 Receiving orders 200 600 800 Inspection hours 800 1,600 2,400 Overhead costs: Machining $7,200,000 Engineering 2,250,000 Receiving 192,000 Inspecting products 336,000...
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced....
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic      Advanced      Total Units produced         130,000         390,000         ------ Prime costs         $9,360,000         $39,780,000         $49,140,000 Machine hours         130,000         650,000         780,000 Engineering hours         400         3,600         4,000 Receiving orders         400         1,200        ...
Cornerstone Exercise 11.3 (Algorithmic) Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment...
Cornerstone Exercise 11.3 (Algorithmic) Activity-Based Customer Costing Deeds Company sells custom-made machine parts to industrial equipment manufacturers by bidding cost plus 40 percent, where cost is defined as manufacturing cost plus order processing cost. There are two types of customers: those who place small, frequent orders and those who place larger, less frequent orders. Cost and sales information by customer category is provided below. Frequently Ordering Customers Less Frequently Ordering Customers Sales orders 39,000 3,900 Order size 15 150 Average...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT