In: Accounting
Cornerstone Exercise 4.5 (Algorithmic) Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below.
Required: 1. Calculate the four activity rates.
2. Calculate the unit costs using activity rates. Round your answers to the nearest cent.
Calculate the overhead cost per unit. Round your answers to the nearest cent.
3. What if consumption ratios instead of activity rates were used to assigned costs? Show the cost assignment for the inspection activity.
|
Hide Feedback
Partially Correct
Check My Work Feedback
1. Machining rate: Overhead costs ÷ Total machine hours. The other three activity rates are calculated the same way using each activity's Overhead costs and totals.
2. Use the calculations from Requirement 1 to calculate the unit costs and also calculate OH cost per unit. Example of Total cost: Activity rate (above) × Basic OH costs and also Activity rate × Advanced OH costs. Example of OH costs per units: Total manufacturing costs÷ Units of production = Unit Cost (for Basic and Advanced).
3. Calculate unit costs using consumption ratios. Compare to activity rate unit costs. To assign inspection cost use the inspection hrs. for basic/advanced ÷ total inspection hrs. for both and give a conclusion.
Overhead cost |
Total cost drivers |
Activity Rates |
||
Machining |
$ 135,00,000.00 |
900000 |
$ 15.00 |
per machine hour |
Engineering |
$ 19,20,000.00 |
4000 |
$ 480.00 |
per hour |
Receiving |
$ 2,16,000.00 |
800 |
$ 270.00 |
per order |
Inspection Products |
$ 4,80,000.00 |
2400 |
$ 200.00 |
per hour |
Total |
$ 161,16,000.00 |
Basic’s Overhead cost per unit
Activity rate |
No. of cost driver |
Overhead cost allocated |
|
Machining |
$ 15.00 |
150000 |
$ 22,50,000.00 |
Engineering |
$ 480.00 |
400 |
$ 1,92,000.00 |
Receiving |
$ 270.00 |
200 |
$ 54,000.00 |
Inspection Products |
$ 200.00 |
800 |
$ 1,60,000.00 |
Total Overhead cost allocated |
$ 26,56,000.00 |
||
Total Units |
$ 1,50,000.00 |
||
Overhead cost per unit |
$ 17.71 |
Advanced Overhead cost per unit
Activity rate |
No. of cost driver |
Overhead cost allocated |
|
Machining |
$ 15.00 |
750000 |
$ 112,50,000.00 |
Engineering |
$ 480.00 |
3600 |
$ 17,28,000.00 |
Receiving |
$ 270.00 |
600 |
$ 1,62,000.00 |
Inspection Products |
$ 200.00 |
1600 |
$ 3,20,000.00 |
Total Overhead cost allocated |
$ 134,60,000.00 |
||
Total Units |
$ 4,50,000.00 |
||
Overhead cost per unit |
$ 29.91 |
Product Unit Cost
Basic |
Advanced |
|
Prime Costs |
$ 105,00,000.00 |
$ 522,00,000.00 |
Total Units |
150000 |
450000 |
Prime cost per unit |
$ 70.00 |
$ 116.00 |
Overhead cost per unit |
$ 17.71 |
$ 29.91 |
Total Unit Cost |
$ 87.71 |
$ 145.91 |
Working
Total Overhead cost |
$ 161,16,000.00 |
Total Prime cost |
$ 627,00,000.00 |
Overhead cost per Prime cost $ (Consumption) |
$ 0.26 |
Basic' Prime cost |
$ 105,00,000.00 |
Basic's Overhead cost allocated |
$ 27,30,000.00 |
Overhead cost per unit |
$ 18.20 |
Advanced Prime Costs |
$ 522,00,000.00 |
Advanced's Overhead cost allocated |
$ 135,72,000.00 |
Overhead cost per unit |
$ 30.16 |
Basic |
Advanced |
|
Prime cost per unit |
$ 70.00 |
$ 116.00 |
Overhead cost per unit |
$ 18.20 |
$ 30.16 |
Total Unit Cost |
$ 88.20 |
$ 146.16 |