Question

In: Finance

Chapter 12 Problem 3 (Excel functions needed) Consider the project contained in Problem 7 in Chapter...

Chapter 12 Problem 3 (Excel functions needed)

Consider the project contained in Problem 7 in Chapter 11 (California Health Center).

a. Perform a sensitivity analysis to see how NPV is affected by changes in the number of procedures per day, average collection amount, and salvage value. Remember supplies vary with number of procedures.

b. Conduct a scenario analysis. Suppose that the hospital's staff concluded that the three most uncertain variables were number of procedures per day, average collection amount, and the equipment's salvage value. Furthermore, the following data were developed:

Scenario

Probabilty Number of Procedures Average Collection Equipment Salvage Value
Worst 0.25 10 $60 $100,000
Most Likely 0.5 15 $80 $200,000
Best 0.25 20 $100 $300,000

c. Finally, assume that California Health Center's average project has a coefficient of variation of NPV in the range of 1.0 - 2.0. (Hint: Coefficient of variation is defined as the standard deviation of NPV divided by the expected NPV.) The hospital adjusts for risk by adding or subtracting 3 percentage points to its 10 percent corporate cost of capital. After adjusting for differential risk, is the project still profitable?

d. What type of risk was measured and accounted for in Parts b. and c.? Should this be of concern to the hospital's managers?

Solutions

Expert Solution

15.3 Consider the project contained in Problem 14.7 in Chapter 14.

a. Perform a sensitivity analysis to see how NPV is affected by changes in the number of procedures per day, average collection amount, and salvage value.

Base NPV

NPV with change

%Change in NPV for variable

Rate of NPV's sensitivity to change in procedures per day

$50,871

$57,694.85

12%

Rate of NPV's sensitivity to change in collection period

$50,871

($112,764.93)

145%

Rate of NPV's sensitivity to change in salvage value

$50,871

$52,113.28

2%

b. Conduct a scenario analysis. Suppose that the hospital%u2019s staff concluded that the three most uncertain variables were number of procedures per day, average collection amount, and the equipment%u2019s salvage value. Furthermore, the following data were developed:

Number of Average Equipment

Scenario Probability Procedures Collection Salvage Value

Worst 0.25 10 $ 60 $100,000

Most likely 0.50 15 80 200,000

Best 0.25 20 100 300,000

Scenario

Probability

Procedures

Collection

salvage value

Worst

0.25

10

60

100,000

Most Likely

0.5

15

80

200,000

Best

0.25

20

100

300,000

Scenario

Probability

Procedures

Collection

salvage value

Worst

0.25

10

60

100,000

Most Likely

0.5

15

80

200,000

Best

0.25

20

100

300,000

Expected value

15

80

            200,000

NPV for expected value of variable

$50,871.44

($261,525.26)

$50,871.44

c. Finally, assume that California Health Center%u2019s average project has a coefficient of variation of NPV in the range of 1.0%u20132.0. (Hint:

The coefficient of variation is defined as the standard deviation of NPV divided by the expected NPV.) The hospital adjusts for risk by adding or subtracting 3 percentage points to its 10 percent corporate cost of capital. After adjusting for differential risk, is the project still profitable?

Rate

NPV

+3% to cost of capital

$109,349.18

-3% to cost of capital

($373.08)

d. What type of risk was measured and accounted for in Parts b and c? Should this be of concern to the hospital%u2019s managers?

In part B, the essence was to measure how each variable would affect the expected NPV of the project. The risk is therefore the possibility that the variables would not be as expected.

On the other hand, the risk being evaluated in Part C is the interest rate risk. With this risk we measure the possibility that the NPV would become unfavorable for any change in interest rate.

From the computations, you will observe that under the scenario analysis, the expected values are highly sensitive to the collection period. As the collection period should therefore be of particular importance to management. On the other hand, the interest rate risk does not show any particularly unfavorable possibility of an unfavorable result.


Related Solutions

3. Consider the following problem related to Chapter 12 of the text. City utility people have...
3. Consider the following problem related to Chapter 12 of the text. City utility people have observed over time that as temperatures warm up, water consumption in the city increases. Examine the following data gathered on various days over a yearly period. For each of the eight days, the high temperature and the water usage in millions of gallons is given.                 Temperature                       Water Use                             (degrees Fahrenheit)               (millions of gallons)                                           103                                          219                                           39        ...
SOLVE WITH EXCEL FUNCTIONS: A certain construction project, which is expected to take 3 years, will...
SOLVE WITH EXCEL FUNCTIONS: A certain construction project, which is expected to take 3 years, will require the first month of $ 50,000 increasing at a rate of $ 5,000 per month during the first 6 months. Then, for 1.5 years, the cash requirements will increase at a rate of 12% per month, taking into account the amount required in month 6. The last 12 months, these amounts would decrease at a rate of $ 25,000 per month. Assuming that...
Problem 3. Plot the following binomial probability functions as a function of outcome (x) using EXCEL...
Problem 3. Plot the following binomial probability functions as a function of outcome (x) using EXCEL on the same graph, and then comment on the effect of the value of p. a. b(x;10,0.1) b. b(x;10,0.5) c. b(x;10,0.9)
*Excel formulas needed* A Canadian firm is evaluating a project in the United States. This project...
*Excel formulas needed* A Canadian firm is evaluating a project in the United States. This project involves the establishment of a lumber mill in Wisconsin to process Canadian timber. The factory expects to service clients in the construction industry. All cash flow figures are in thousands. Initial Investment. The initial investment is CAD 60,000. The project is over a period of three years. This investment will be depreciated straight line to zero. Operating Results. The firm expects two likely scenarios...
Chapter 3 Problem to be completed with Excel P3-1A On April 1, Wonder Travel Agency Inc....
Chapter 3 Problem to be completed with Excel P3-1A On April 1, Wonder Travel Agency Inc. was established. These transactions were completed during the month. • 1.Stockholders invested $30,000 cash in the company in exchange for common stock. • 2.Paid $900 cash for April office rent. • 3.Purchased office equipment for $3,400 cash. • 4.Purchased $200 of advertising in the Chicago Tribune, on account. • 5.Paid $500 cash for office supplies. • 6.Performed services worth $12,000. Cash of $3,000 is...
This problem is to be done in R. Consider two populations A = {3, 5, 7,...
This problem is to be done in R. Consider two populations A = {3, 5, 7, 9, 10, 16} and B = {8, 10, 11, 15, 18, 25, 28}. a) Using R, draw random samples (without replacement) of size 3 from each population, and simulate the sampling distribution of the sum of their maximum. Describe the distribution. b) Use your simulation to estimate the probability that the sum of the maximums is less than 20. c) Draw random samples of...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times...
Problem 12-3: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
Required information Chapter 7: Applying Excel Step 1: Download the Applying Excel form located on the...
Required information Chapter 7: Applying Excel Step 1: Download the Applying Excel form located on the left-hand side, under files. Step 2: Then enter formulas in all cells that contain question marks. For example, in cell B26 enter the formula "= B17". Step 3: Check your worksheet by changing the units sold in the Data to 6,000 for Year 2. The cost of goods sold under absorption costing for Year 2 should now be $240,000. If it isn’t, check cell...
Consider the project described in the below Excel a. Use Excel to find the critical path...
Consider the project described in the below Excel a. Use Excel to find the critical path and the project duration using normal activity times. b. What is the shortest duration the project can be crashed down to? c. If you were to crash the project manually and your goal is to minimize crashing cost, which activity would you start with? d. Find the cheapest way to crash the project to 33 weeks. What are the critical activities in the crashed...
Chapter 7 Develop a response in either Word or Excel and follow the instructions outlined in...
Chapter 7 Develop a response in either Word or Excel and follow the instructions outlined in the Assignments Menu for submission. On December 31, 2010, Palli Company finished consultation services and accepted in exchange a promissory note with a face value of $240,000, a due date of December 31, 2013, and a stated rate of 5%, with interest receivable at the end of each year. The fair value of the services is not readily determinable and the note is not...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT