In: Accounting
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000.
In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were $2,762,000, and $2,485,000 cash was collected. The project was completed in 2020 after additional costs of $3,810,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.
Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
  | 
2b. Prepare journal entries for 2019 to record the transactions described (credit "various accounts" for construction costs incurred).
| No | Year | General Journal | Debit | Credit | 
|---|---|---|---|---|
| 1 | 2019 | Construction in progress | 2,512,000 | |
| Various accounts | 2,512,000 | |||
| 2 | 2019 | Accounts receivable | 2,762,000 | |
| Billings on construction contract | 2,762,000 | |||
| 3 | 2019 | Cash | 2,485,000 | |
| Accounts receivable | 2,485,000 | |||
| 4 | ??? Record the expected loss | ???? | 
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018.
  | 
|||||||||||||||||||||||
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019.
  | 
|||||||||||||||||||||||
| Statement showing Revenue recogniztion for each year | |||||
| 2018 | 2019 | 2020 | Total | ||
| Revenue recognized in Current year | $2,648,250 | $1,845,750 | $3,531,000 | $8,025,000 | |
| Cost Incurred in Current Year | $2,010,000 | $2,512,000 | $3,810,000 | $8,332,000 | |
| Gross Profit | $638,250 | -$666,250 | -$279,000 | -$307,000 | |
| Working Notee | |||||
| Statement showing Revenue recogniztion for each year | |||||
| 2018 | 2019 | 2020 | |||
| Contract Price | $8,025,000.00 | ||||
| % of Cost of Completion | 33% | 56% | 100% | ||
| Revenue recognised to be recognized as on (a) | $2,648,250 | $4,494,000 | $8,025,000 | ||
| Revenue recognized in previous year (b) | $0 | $2,648,250 | $4,494,000 | ||
| Revenue recognized in Current year (a-b) | $2,648,250 | $1,845,750 | $3,531,000 | ||
| Computation of Percentage of cost of Completion | |||||
| 2018 | 2019 | 2020 | |||
| Cost incurred in Previous Year | $0 | $2,010,000 | $4,522,000 | ||
| Cost incurred during the year | $2,010,000 | $2,512,000 | $3,810,000 | ||
| Total Cost Incurred till date | $2,010,000 | $4,522,000 | $8,332,000 | ||
| Estminated cost to Complete at end of of year | $4,010,000 | $3,615,000 | $0 | ||
| Total Estimated Cost of Completion | $6,020,000 | $8,137,000 | $8,332,000 | ||
| % of Cost of Completion | 33% | 56% | 100% | ||
| ( Cost incurred as on /Total cost of Completion) | |||||
| 2.b Journal Entries | |||||
| No. | Year | General Journal | Debit | Credit | |
| 1 | 2019 | Construction in progress | $2,512,000.00 | ||
| Various Account | $2,512,000.00 | ||||
| 2 | 2019 | Account Receivable | $2,762,000.00 | ||
| Billing on Construction Contract | $2,762,000.00 | ||||
| 3 | |||||
| 2019 | Cash | $2,485,000.00 | |||
| Account Receivable | $2,485,000.00 | ||||
| 4 | 2019 | Construction Expense | $2,512,000.00 | ||
| Costruction Loss | $666,250.00 | ||||
| Construction Revenue | $1,845,750.00 | ||||
| 3.a. Balancesheet at Dec 31,2018 | |||||
| Current Asset | |||||
| Account Receivable | 252000 | ||||
| Construction in progress | 2010000 | ||||
| Current Liabilities | |||||
| 3.b. Balancesheet at Dec 31,2018 | |||||
| Current Asset | |||||
| Account Receivable | 277000 | ||||
| Construction in progress | 4522000 | ||||
| Current Liabilities | |||||