In: Accounting
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000.
In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were $2,762,000, and $2,485,000 cash was collected. The project was completed in 2020 after additional costs of $3,810,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.
Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
|
2b. Prepare journal entries for 2019 to record the transactions described (credit "various accounts" for construction costs incurred).
No | Year | General Journal | Debit | Credit |
---|---|---|---|---|
1 | 2019 | Construction in progress | 2,512,000 | |
Various accounts | 2,512,000 | |||
2 | 2019 | Accounts receivable | 2,762,000 | |
Billings on construction contract | 2,762,000 | |||
3 | 2019 | Cash | 2,485,000 | |
Accounts receivable | 2,485,000 | |||
4 | ??? Record the expected loss | ???? |
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018.
|
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019.
|
Statement showing Revenue recogniztion for each year | |||||
2018 | 2019 | 2020 | Total | ||
Revenue recognized in Current year | $2,648,250 | $1,845,750 | $3,531,000 | $8,025,000 | |
Cost Incurred in Current Year | $2,010,000 | $2,512,000 | $3,810,000 | $8,332,000 | |
Gross Profit | $638,250 | -$666,250 | -$279,000 | -$307,000 | |
Working Notee | |||||
Statement showing Revenue recogniztion for each year | |||||
2018 | 2019 | 2020 | |||
Contract Price | $8,025,000.00 | ||||
% of Cost of Completion | 33% | 56% | 100% | ||
Revenue recognised to be recognized as on (a) | $2,648,250 | $4,494,000 | $8,025,000 | ||
Revenue recognized in previous year (b) | $0 | $2,648,250 | $4,494,000 | ||
Revenue recognized in Current year (a-b) | $2,648,250 | $1,845,750 | $3,531,000 | ||
Computation of Percentage of cost of Completion | |||||
2018 | 2019 | 2020 | |||
Cost incurred in Previous Year | $0 | $2,010,000 | $4,522,000 | ||
Cost incurred during the year | $2,010,000 | $2,512,000 | $3,810,000 | ||
Total Cost Incurred till date | $2,010,000 | $4,522,000 | $8,332,000 | ||
Estminated cost to Complete at end of of year | $4,010,000 | $3,615,000 | $0 | ||
Total Estimated Cost of Completion | $6,020,000 | $8,137,000 | $8,332,000 | ||
% of Cost of Completion | 33% | 56% | 100% | ||
( Cost incurred as on /Total cost of Completion) | |||||
2.b Journal Entries | |||||
No. | Year | General Journal | Debit | Credit | |
1 | 2019 | Construction in progress | $2,512,000.00 | ||
Various Account | $2,512,000.00 | ||||
2 | 2019 | Account Receivable | $2,762,000.00 | ||
Billing on Construction Contract | $2,762,000.00 | ||||
3 | |||||
2019 | Cash | $2,485,000.00 | |||
Account Receivable | $2,485,000.00 | ||||
4 | 2019 | Construction Expense | $2,512,000.00 | ||
Costruction Loss | $666,250.00 | ||||
Construction Revenue | $1,845,750.00 | ||||
3.a. Balancesheet at Dec 31,2018 | |||||
Current Asset | |||||
Account Receivable | 252000 | ||||
Construction in progress | 2010000 | ||||
Current Liabilities | |||||
3.b. Balancesheet at Dec 31,2018 | |||||
Current Asset | |||||
Account Receivable | 277000 | ||||
Construction in progress | 4522000 | ||||
Current Liabilities | |||||