Question

In: Accounting

Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9]...

Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000.

In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were $2,762,000, and $2,485,000 cash was collected. The project was completed in 2020 after additional costs of $3,810,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.

Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.

Year Revenue recognized Gross profit (loss) recognized
2018 $0
2019 0
2020 8,025,000
Total $8,025,000

2b. Prepare journal entries for 2019 to record the transactions described (credit "various accounts" for construction costs incurred).

No Year General Journal Debit Credit
1 2019 Construction in progress 2,512,000
Various accounts 2,512,000
2 2019 Accounts receivable 2,762,000
Billings on construction contract 2,762,000
3 2019 Cash 2,485,000
Accounts receivable 2,485,000
4 ??? Record the expected loss ????

3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018.

Balance Sheet
At December 31, 2018
Current assets:
Accounts receivable $252,000
Construction in progress 2,010,000
Current liabilities:

3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019.

Balance Sheet
At December 31, 2019
Current assets:
Accounts receivable
Construction in progress
Current liabilities:

Solutions

Expert Solution

Statement showing Revenue recogniztion for each year
2018 2019 2020 Total
Revenue recognized in Current year $2,648,250 $1,845,750 $3,531,000 $8,025,000
Cost Incurred in Current Year $2,010,000 $2,512,000 $3,810,000 $8,332,000
Gross Profit $638,250 -$666,250 -$279,000 -$307,000
Working Notee
Statement showing Revenue recogniztion for each year
2018 2019 2020
Contract Price $8,025,000.00
% of Cost of Completion 33% 56% 100%
Revenue recognised to be recognized as on (a) $2,648,250 $4,494,000 $8,025,000
Revenue recognized in previous year (b) $0 $2,648,250 $4,494,000
Revenue recognized in Current year (a-b) $2,648,250 $1,845,750 $3,531,000
Computation of Percentage of cost of Completion
2018 2019 2020
Cost incurred in Previous Year $0 $2,010,000 $4,522,000
Cost incurred during the year $2,010,000 $2,512,000 $3,810,000
Total Cost Incurred till date $2,010,000 $4,522,000 $8,332,000
Estminated cost to Complete at end of of year $4,010,000 $3,615,000 $0
Total Estimated Cost of Completion $6,020,000 $8,137,000 $8,332,000
% of Cost of Completion 33% 56% 100%
( Cost incurred as on /Total cost of Completion)
2.b Journal Entries
No. Year General Journal Debit Credit
1 2019 Construction in progress $2,512,000.00
Various Account $2,512,000.00
2 2019 Account Receivable $2,762,000.00
Billing on Construction Contract $2,762,000.00
3
2019 Cash $2,485,000.00
Account Receivable $2,485,000.00
4 2019 Construction Expense $2,512,000.00
Costruction Loss $666,250.00
Construction Revenue $1,845,750.00
3.a. Balancesheet at Dec 31,2018
Current Asset
Account Receivable 252000
Construction in progress 2010000
Current Liabilities
3.b. Balancesheet at Dec 31,2018
Current Asset
Account Receivable 277000
Construction in progress 4522000
Current Liabilities

Related Solutions

Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9]...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 46,000 Construction in progress $ 300,000 Less: Billings on construction contract (290,000...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0...
(Recognition of Profit on Long-Term Contract —Overall Loss) Assume the facts given in E6.37 except that...
(Recognition of Profit on Long-Term Contract —Overall Loss) Assume the facts given in E6.37 except that Vaughn's non-cancellable fixed price contract with Atlantis is for $9.5 million. Billings and collections are lower in 2022 by $500,000 each. 2020 2021 2022 Costs for the year $3,825 $4,675 $1,200 Estimated costs to complete 4,675 1,270 –0– Progress billings for the year (non-refundable) 3,500 4,100 1,900 Cash collected for the year 3,100 4,150 2,250 Instructions a. Using the percentage-of-completion method, calculate the percent...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,000 $450,000 $610,000 Estimated costs to complete 330,000 150,000 –0– Progress billings...
Exercise 5-9 Compute and Use the Degree of Operating Leverage [LO5-8] Engberg Company installs lawn sod...
Exercise 5-9 Compute and Use the Degree of Operating Leverage [LO5-8] Engberg Company installs lawn sod in home yards. The company’s most recent monthly contribution format income statement follows: Amount Percent of Sales Sales $ 149,000 100% Variable expenses 59,600 40% Contribution margin 89,400 60% Fixed expenses 24,000 Net operating income $ 65,400 Required: 1. Compute the company’s degree of operating leverage. (Round your answer to 2 decimal places.) 2. Using the degree of operating leverage, estimate the impact on...
Brief Exercise 9-64(Appendix 9A) Bond Issue Price Objective 8(Appendix 9A) Calculate the market price of long-term...
Brief Exercise 9-64(Appendix 9A) Bond Issue Price Objective 8(Appendix 9A) Calculate the market price of long-term debt using present value techniques. On January 1, 2020, Ruby Inc. issued 3,000 $1,000 par value bonds with a stated rate of 6% and a 10-year maturity. Interest is payable semiannually on June 30 and December 31. Required: What is the issue price if the bonds are sold to yield 8%? (Note: Round to nearest dollar.) Brief Exercise 9-65(Appendix 9A) Bond Issue Price Objective...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT