Question

In: Accounting

Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9]...

Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming Nortel recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming this project does not qualify for revenue recognition over time.

Solutions

Expert Solution

1.Percentages of completion
Choose numerator ÷ Choose denominator = % complete to date
2021 308000 ÷ 1540000 = 20%
2022 1923000 ÷ 1923000 = 100%
2021
To date Recognized in prior years Recognized in 2021
Construction revenue $         4,20,000 $                             -   $                 4,20,000
Construction expense $        -3,08,000 $                             -   $                -3,08,000
Gross profit (loss) $         1,12,000 $                             -   $                 1,12,000
2022
To date Recognized in prior years Recognized in 2022
Construction revenue $       21,00,000 $                 4,20,000 $               16,80,000
Construction expense $      -19,23,000 $                -3,08,000 $              -16,15,000
Gross profit (loss) $         1,77,000 $                 1,12,000 $                    65,000
2
Revenue Gross Profit (Loss)
2021 0 0
2022 $21,00,000 $1,77,000

3.

Balance Sheet (Partial)
At December 31, 2021
Current assets:
Account Receivables $     1,20,000
Costs and Profit in excess of billing $       30,000
Current liabilities:

4.

Balance Sheet (Partial)
At December 31, 2021
Current assets:
Account Receivables $       1,20,000
Current liabilities:
Billing in excess of cost $             82,000

Working Note:

2021 2022
Contract $      21,00,000 $      21,00,000
Cost incurred $        3,08,000 $      19,23,000
Estimated cost to complete as of 12/31 $      12,32,000 $                    -  
Estimated cost $      15,40,000 $      19,23,000
Gross Profit $        5,60,000 $        1,77,000
Revenue Recognised
2021: (308,000/1540000)*2100000 $        4,20,000
2022:(2100000-420000) $      16,80,000
2021 GP(420000-308000) $        1,12,000
2022 GP(1680000-1615000) $            65,000

Related Solutions

Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 46,000 Construction in progress $ 300,000 Less: Billings on construction contract (290,000...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9]...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000. In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were...
Revenue recognition at a point in time or over time Kleymenova Consulting, Inc., enters into a...
Revenue recognition at a point in time or over time Kleymenova Consulting, Inc., enters into a contract to provide consulting services 1. The consulting services are the provision of technical computer assistance as needed. For $25,000 per month, whenever the client has a problem, it contacts Kleymenova, which dispatches a consultant to address the problem at no additional charge. 2. The consulting services are to develop a new customer payment collection system for the client. The $300,000 contract price is...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3]...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3] Walsh Company manufactures and sells one product. The following information pertains to each of the company’s first two years of operations: Variable costs per unit: Manufacturing: Direct materials $ 23 Direct labor $ 16 Variable manufacturing overhead $ 4 Variable selling and administrative $ 3 Fixed costs per year: Fixed manufacturing overhead $ 240,000 Fixed selling and administrative expenses $ 90,000 During its first...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3]...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3] Walsh Company manufactures and sells one product. The following information pertains to each of the company’s first two years of operations: Variable costs per unit: Manufacturing: Direct materials $ 22 Direct labor $ 14 Variable manufacturing overhead $ 4 Variable selling and administrative $ 3 Fixed costs per year: Fixed manufacturing overhead $ 400,000 Fixed selling and administrative expenses $ 70,000 During its first...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3]...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3] Walsh Company manufactures and sells one product. The following information pertains to each of the company’s first two years of operations: Variable costs per unit: Manufacturing: Direct materials $ 25 Direct labor $ 17 Variable manufacturing overhead $ 2 Variable selling and administrative $ 1 Fixed costs per year: Fixed manufacturing overhead $ 400,000 Fixed selling and administrative expenses $ 80,000 During its first...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,000 $450,000 $610,000 Estimated costs to complete 330,000 150,000 –0– Progress billings...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT