Question

In: Accounting

Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...

Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]

[The following information applies to the questions displayed below.]

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600
Estimated costs to complete as of year-end 5,810,000 1,826,000 0
Billings during the year 2,030,000 4,444,000 3,526,000
Cash collections during the year 1,815,000 3,900,000 4,285,000


Westgate recognizes revenue over time according to percentage of completion.

Problem 6-10 (Algo) Part 1

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.

2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).

Solutions

Expert Solution

Requirement 1

2021

2022

2023

Revenue

$3,000,000

$4,800,000

$2,200,000

Gross Profits (Loss)

$510,000

$816,000

$191,400

--Working

Working

2021

2022

2023

A

Contract Price

$10,000,000

$10,000,000

$10,000,000

B

Cost Incurred to Date

$2,490,000

$6,474,000

$8,482,600

C

Estimated cost yet to be incurred to complete the contract

$5,810,000

$1,826,000

$0

D = B+C

Total Cost

$8,300,000

$8,300,000

$8,482,600

E = (B/D) x 100

% of Completion

30.00%

78.00%

100.00%

F = A x E

Revenue to date

$3,000,000

$7,800,000

$10,000,000

G

Revenue of Previous year

$0

$3,000,000

$7,800,000

H = F - G

Net Revenue this year

$3,000,000

$4,800,000

$2,200,000

I (=B)

Cost to date

$2,490,000

$6,474,000

$8,482,600

J

Cost to date of previous year

$0

$2,490,000

$6,474,000

K = I - J

Net Cost for the year

$2,490,000

$3,984,000

$2,008,600

L = H - K

Gross Profits

$510,000

$816,000

$191,400

Requirement 2A

Date

Accounts title

Debit

Credit

2021

Construction in Progress

$2,490,000

   Various accounts

$2,490,000

(construction cost incurred)

2021

Accounts receivables

$2,030,000

Billing on Construction contracts

$2,030,000

(amount billed during the year)

2021

Cash

$1,815,000

Accounts receivables

$1,815,000

(cash received)

2021

Construction in Progress

$510,000

Cost of construction

$2,490,000

Revenue from Long Term contract

$3,000,000

(revenue recognised)

Requirement 2B

Date

Accounts title

Debit

Credit

2022

Construction in Progress

$3,984,000

   Various accounts

$3,984,000

(construction cost incurred)

2022

Accounts receivables

$4,444,000

Billing on Construction contracts

$4,444,000

(amount billed during the year)

2022

Cash

$3,900,000

Accounts receivables

$3,900,000

(cash received)

2022

Construction in Progress

$816,000

Cost of construction

$3,984,000

Revenue from Long Term contract

$4,800,000

(revenue recognised)

Requirement 2C

Date

Accounts title

Debit

Credit

2023

Construction in Progress

$2,008,600

   Various accounts

$2,008,600

(construction cost incurred)

2023

Accounts receivables

$3,526,000

Billing on Construction contracts

$3,526,000

(amount billed during the year)

2023

Cash

$4,285,000

Accounts receivables

$4,285,000

(cash received)

2023

Construction in Progress

$191,400

Cost of construction

$2,008,600

Revenue from Long Term contract

$2,200,000

(revenue recognised)

2023

Billing on Construction contracts

$10,000,000

   Construction in Progress

$10,000,000

(to record completion of contract)


Related Solutions

Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9]...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 46,000 Construction in progress $ 300,000 Less: Billings on construction contract (290,000...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9]...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000. In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,000 $450,000 $610,000 Estimated costs to complete 330,000 150,000 –0– Progress billings...
P9-11 (Algo) Computing Present Values LO9-7, 9-8 [The following information applies to the questions displayed below.]...
P9-11 (Algo) Computing Present Values LO9-7, 9-8 [The following information applies to the questions displayed below.] On January 1, Boston Company completed the following transactions (use a 7% annual interest rate for all transactions): (FV of $1, PV of $1, FVA of $1, and PVA of $1) (Use the appropriate factor(s) from the tables provided.) Promised to pay a fixed amount of $7,700 at the end of each year for eight years and a one-time payment of $118,400 at the...
Problem 13-53 & 13-54 (Algo) (LO 13-4, 5, 6) [The following information applies to the questions...
Problem 13-53 & 13-54 (Algo) (LO 13-4, 5, 6) [The following information applies to the questions displayed below.] Gulf States Manufacturing has the following data from year 1 operations, which are to be used for developing year 2 budget estimates: Sales revenues (18,000 units) $ 1,620,000 Manufacturing costs Materials $ 289,000 Variable cash costs 395,000 Fixed cash costs 159,000 Depreciation (fixed) 195,000 Marketing and administrative costs Marketing (variable, cash) 208,000 Marketing depreciation 51,000 Administrative (fixed, cash) 204,000 Administrative depreciation $...
Problem 13-53 & 13-54 (Algo) (LO 13-4, 5, 6) [The following information applies to the questions...
Problem 13-53 & 13-54 (Algo) (LO 13-4, 5, 6) [The following information applies to the questions displayed below.] Gulf States Manufacturing has the following data from year 1 operations, which are to be used for developing year 2 budget estimates: Sales revenues (18,000 units) $ 1,620,000 Manufacturing costs Materials $ 289,000 Variable cash costs 395,000 Fixed cash costs 159,000 Depreciation (fixed) 195,000 Marketing and administrative costs Marketing (variable, cash) 208,000 Marketing depreciation 51,000 Administrative (fixed, cash) 204,000 Administrative depreciation $...
Required information Problem 9-1A Short-term notes payable transactions and entries LO P1 [The following information applies...
Required information Problem 9-1A Short-term notes payable transactions and entries LO P1 [The following information applies to the questions displayed below.] Tyrell Co. entered into the following transactions involving short-term liabilities. Year 1 Apr. 20 Purchased $40,250 of merchandise on credit from Locust, terms n/30. May 19 Replaced the April 20 account payable to Locust with a 90-day, 10%, $35,000 note payable along with paying $5,250 in cash. July 8 Borrowed $80,000 cash from NBR Bank by signing a 120-day,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT