Question

In: Accounting

Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...

Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]

[The following information applies to the questions displayed below.]

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600
Estimated costs to complete as of year-end 5,810,000 1,826,000 0
Billings during the year 2,030,000 4,444,000 3,526,000
Cash collections during the year 1,815,000 3,900,000 4,285,000


Westgate recognizes revenue over time according to percentage of completion.

Problem 6-10 (Algo) Part 1

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.

2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).

Solutions

Expert Solution

Requirement 1

2021

2022

2023

Revenue

$3,000,000

$4,800,000

$2,200,000

Gross Profits (Loss)

$510,000

$816,000

$191,400

--Working

Working

2021

2022

2023

A

Contract Price

$10,000,000

$10,000,000

$10,000,000

B

Cost Incurred to Date

$2,490,000

$6,474,000

$8,482,600

C

Estimated cost yet to be incurred to complete the contract

$5,810,000

$1,826,000

$0

D = B+C

Total Cost

$8,300,000

$8,300,000

$8,482,600

E = (B/D) x 100

% of Completion

30.00%

78.00%

100.00%

F = A x E

Revenue to date

$3,000,000

$7,800,000

$10,000,000

G

Revenue of Previous year

$0

$3,000,000

$7,800,000

H = F - G

Net Revenue this year

$3,000,000

$4,800,000

$2,200,000

I (=B)

Cost to date

$2,490,000

$6,474,000

$8,482,600

J

Cost to date of previous year

$0

$2,490,000

$6,474,000

K = I - J

Net Cost for the year

$2,490,000

$3,984,000

$2,008,600

L = H - K

Gross Profits

$510,000

$816,000

$191,400

Requirement 2A

Date

Accounts title

Debit

Credit

2021

Construction in Progress

$2,490,000

   Various accounts

$2,490,000

(construction cost incurred)

2021

Accounts receivables

$2,030,000

Billing on Construction contracts

$2,030,000

(amount billed during the year)

2021

Cash

$1,815,000

Accounts receivables

$1,815,000

(cash received)

2021

Construction in Progress

$510,000

Cost of construction

$2,490,000

Revenue from Long Term contract

$3,000,000

(revenue recognised)

Requirement 2B

Date

Accounts title

Debit

Credit

2022

Construction in Progress

$3,984,000

   Various accounts

$3,984,000

(construction cost incurred)

2022

Accounts receivables

$4,444,000

Billing on Construction contracts

$4,444,000

(amount billed during the year)

2022

Cash

$3,900,000

Accounts receivables

$3,900,000

(cash received)

2022

Construction in Progress

$816,000

Cost of construction

$3,984,000

Revenue from Long Term contract

$4,800,000

(revenue recognised)

Requirement 2C

Date

Accounts title

Debit

Credit

2023

Construction in Progress

$2,008,600

   Various accounts

$2,008,600

(construction cost incurred)

2023

Accounts receivables

$3,526,000

Billing on Construction contracts

$3,526,000

(amount billed during the year)

2023

Cash

$4,285,000

Accounts receivables

$4,285,000

(cash received)

2023

Construction in Progress

$191,400

Cost of construction

$2,008,600

Revenue from Long Term contract

$2,200,000

(revenue recognised)

2023

Billing on Construction contracts

$10,000,000

   Construction in Progress

$10,000,000

(to record completion of contract)


Related Solutions

Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9]...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 46,000 Construction in progress $ 300,000 Less: Billings on construction contract (290,000...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9]...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000. In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,000 $450,000 $610,000 Estimated costs to complete 330,000 150,000 –0– Progress billings...
P9-11 (Algo) Computing Present Values LO9-7, 9-8 [The following information applies to the questions displayed below.]...
P9-11 (Algo) Computing Present Values LO9-7, 9-8 [The following information applies to the questions displayed below.] On January 1, Boston Company completed the following transactions (use a 7% annual interest rate for all transactions): (FV of $1, PV of $1, FVA of $1, and PVA of $1) (Use the appropriate factor(s) from the tables provided.) Promised to pay a fixed amount of $7,700 at the end of each year for eight years and a one-time payment of $118,400 at the...
Problem 13-53 & 13-54 (Algo) (LO 13-4, 5, 6) [The following information applies to the questions...
Problem 13-53 & 13-54 (Algo) (LO 13-4, 5, 6) [The following information applies to the questions displayed below.] Gulf States Manufacturing has the following data from year 1 operations, which are to be used for developing year 2 budget estimates: Sales revenues (18,000 units) $ 1,620,000 Manufacturing costs Materials $ 289,000 Variable cash costs 395,000 Fixed cash costs 159,000 Depreciation (fixed) 195,000 Marketing and administrative costs Marketing (variable, cash) 208,000 Marketing depreciation 51,000 Administrative (fixed, cash) 204,000 Administrative depreciation $...
Problem 13-53 & 13-54 (Algo) (LO 13-4, 5, 6) [The following information applies to the questions...
Problem 13-53 & 13-54 (Algo) (LO 13-4, 5, 6) [The following information applies to the questions displayed below.] Gulf States Manufacturing has the following data from year 1 operations, which are to be used for developing year 2 budget estimates: Sales revenues (18,000 units) $ 1,620,000 Manufacturing costs Materials $ 289,000 Variable cash costs 395,000 Fixed cash costs 159,000 Depreciation (fixed) 195,000 Marketing and administrative costs Marketing (variable, cash) 208,000 Marketing depreciation 51,000 Administrative (fixed, cash) 204,000 Administrative depreciation $...
Exercise 6-16 Working with a Segmented Income Statement; Break-Even Analysis [LO6-4, LO6-5] [The following information applies...
Exercise 6-16 Working with a Segmented Income Statement; Break-Even Analysis [LO6-4, LO6-5] [The following information applies to the questions displayed below.]    Raner, Harris & Chan is a consulting firm that specializes in information systems for medical and dental clinics. The firm has two offices—one in Chicago and one in Minneapolis. The firm classifies the direct costs of consulting jobs as variable costs. A contribution format segmented income statement for the company’s most recent year is given: Office Total Company...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT