Question

In: Accounting

(Recognition of Profit on Long-Term Contract —Overall Loss) Assume the facts given in E6.37 except that...

(Recognition of Profit on Long-Term Contract
—Overall Loss) Assume the facts given in E6.37 except that
Vaughn's non-cancellable fixed price contract with Atlantis is for $9.5
million. Billings and collections are lower in 2022 by $500,000 each.


2020 2021 2022
Costs for the year $3,825 $4,675 $1,200
Estimated costs to complete 4,675 1,270 –0–
Progress billings for the year (non-refundable) 3,500 4,100 1,900
Cash collected for the year 3,100 4,150 2,250
Instructions
a. Using the percentage-of-completion method, calculate the
percent complete for 2020 and 2021. Round the percent complete
to the nearest whole percentage point.


b. Calculate the amount of revenue to be recognized in 2020 and
2021.


c. Calculate the construction costs to be expensed in 2021.


d. Prepare the journal entry at December 31, 2021, to record longterm
contract revenues, expenses, and losses for 2021.


e. What is the balance in the Contract Asset/Liability account at
December 31, 2020 and 2021?


f. Show how the construction contract would be reported on the
SFP and the income statement for the year ended December 31,
2021.


g. Assume that Vaughn uses the zero-profit or completed-contract
method. What would be the journal entry recorded on December 31, 2021?

Solutions

Expert Solution

(Recognition of Profit on Long-Term Contract —Overall Loss) Assume the facts given in E6.37 except that Vaughn's non-cancellable fixed price contract with Atlantis is for $9.5 million. Billings and collections are lower in 2022 by $500,000 each.


Related Solutions

P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,000 $450,000 $610,000 Estimated costs to complete 330,000 150,000 –0– Progress billings...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9]...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000. In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 46,000 Construction in progress $ 300,000 Less: Billings on construction contract (290,000...
For Long term Memory, Please provide informtion on the following facts on Long term memory.: 1....
For Long term Memory, Please provide informtion on the following facts on Long term memory.: 1. Features 2. Functions 3.Strengths 4, Weaknesses 5. Examples
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9]...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000...
All of the following OCI items may not be reclassified to profit or loss, except A....
All of the following OCI items may not be reclassified to profit or loss, except A. Unrealized loss on debt investment at FVOCI B. Unrealized loss on equity investment at FVOCI C. Remeasurement loss on defined benefit plans D. Revaluation surplus
For 2015, Sherri has a short-term loss of $2,960 and a long-term loss of $4,800. 1.How...
For 2015, Sherri has a short-term loss of $2,960 and a long-term loss of $4,800. 1.How much loss can Sherri deduct in 2015 2.How much loss will Sherri carryover to 2016, and what is the character of the loss carryover? Rich and Shauna Nielson file a joint tax return, and they itemize deductions. Assume their marginal tax rate on ordinary income is 25 percent. The Nielsons incur $2,100 in miscellaneous itemized deductions, excluding investment expenses. They also incur $1,500 in...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during...
Assume all of the same facts as in Part I, except that Soccer Inc. uses the...
Assume all of the same facts as in Part I, except that Soccer Inc. uses the percent of receivables or "aging of receivables" method to determine bad debt expense. I will repeat the facts for your convenience: Soccer Inc. had credit sales of $775,000 during 2020. At the end of 2020, the unadjusted ending balance in Soccer’s Allowance for Bad Debt account was $7,600, and the unadjusted balance in its gross accounts receivable account was $239,000. The company has a...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT