In: Accounting
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term
Contract) Shanahan Construction Company has entered into
a contract beginning January 1, 2017, to build a parking complex.
It has been estimated that the complex will cost $600,000 and
will take 3 years to construct. The complex will be billed to the
purchasing company at $900,000. The following data pertain to
the construction period.
2017 2018 2019
Costs to date $270,000 $450,000 $610,000
Estimated costs to complete 330,000 150,000 –0–
Progress billings to date 270,000 550,000 900,000
Cash collected to date 240,000 500,000 900,000
Instructions
(a) Using the percentage-of-completion method, compute the
estimated gross profit that would be recognized during each
year of the construction period.
(b) Using the completed-contract method, compute the estimated
gross profit that would be recognized during each year
of the construction period.
(a)
Description | 2017 | 2018 | 2019 |
Contract price | $ 9,00,000 | $ 9,00,000 | $ 9,00,000 |
Costs to date | $ 2,70,000 | $ 4,50,000 | $ 6,10,000 |
Estimated costs to complete | $ 3,30,000 | $ 1,50,000 | |
Estimated total costs | $ 6,00,000 | $ 6,00,000 | $ 6,10,000 |
Estimated gross profit | $ 3,00,000 | $ 3,00,000 | $ 2,90,000 |
2017 | |||||
Gross profit for 2017 | |||||
Costs to date | x | Estimated total gross profit | |||
Estimated total costs | |||||
Percentage of completion | 270000/600000= 45% | ||||
Gross profit | $ 1,35,000 | (300000*45%) | |||
2018 | |||||
Gross profit for 2018 | |||||
Costs to date | x | Estimated total gross profit | - | Gross profit recognized until the end of the previous year | |
Estimated total costs | |||||
=(450000/600000) | x | 300000 | - | 135000 | |
Gross profit | $ 90,000 | ||||
2019 | |||||
Gross profit for 2019 | |||||
Costs to date | x | Estimated total gross profit | - | Gross profit recognized until the end of the previous year | |
Estimated total costs | |||||
=(610000/610000) | x | 290000 | - | 225000 | |
Gross profit | $ 65,000 |
(b)
2017 | Total Contract price = | 0 |
Total Contract costs = | 0 | |
Total Gross profit = | 0 | |
2018 | Total Contract price = | 0 |
Total Contract costs = | 0 | |
Total Gross profit = | 0 | |
2019 | Total Contract price = | $ 9,00,000 |
Total Contract costs = | $ 6,10,000 | |
Total Gross profit = | $ 2,90,000 |