In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800
Estimated costs to complete as of year-end 6,020,000 1,978,000 0
Billings during the year 2,060,000 4,562,000 3,378,000
Cash collections during the year 1,830,000 4,200,000 3,970,000


Westgate recognizes revenue over time according to percentage of completion.


rev: 09_15_2017_QC_CS-99734

Problem 5-10 Part 5

5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2018 2019 2020
Cost incurred during the year $ 2,580,000 $ 3,830,000 $ 3,990,000
Estimated costs to complete as of year-end 6,020,000 4,160,000 0

Solutions

Expert Solution

Year

2018

2019

2020

Cost incurred during the year

2580000

4042000

2175800

Cumulative cost incurred at end of year

2580000

6622000

8797800

Cumulative cost incurred at end of year

2580000

6622000

8797800

Add: Estimated costs to complete as of year-end

6020000

1978000

0

Total estimated cost

8600000

8600000

8797800

Percentage of completion (cumulative cost incurred at end of year / Total estimated cost)

30.00%

77.00%

100.00%

Revenue recognized till the date (10000000 * percentage of completion)

3000000

7700000

10000000

Less: revenue recognized up to earlier year

0

3000000

7700000

Revenue recognized in current year

3000000

4700000

2300000

Revenue recognized in current year

3000000

4700000

2300000

Less: cost incurred during the year

2580000

4042000

2175800

Gross profit

420000

658000

124200

As per our policy, we cannot able to post solution more than one question. But you can post second question in our site, if you want solution.


Related Solutions

Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9]...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000. In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9]...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long...
Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 46,000 Construction in progress $ 300,000 Less: Billings on construction contract (290,000...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,000 $450,000 $610,000 Estimated costs to complete 330,000 150,000 –0– Progress billings...
Required information Problem 9-42 Preparation of Master Budget (LO 9-3, 9-4, 9-5) [The following information applies...
Required information Problem 9-42 Preparation of Master Budget (LO 9-3, 9-4, 9-5) [The following information applies to the questions displayed below.] FreshPak Corporation manufactures two types of cardboard boxes used in shipping canned food, fruit, and vegetables. The canned food box (type C) and the perishable food box (type P) have the following material and labor requirements. Type of Box C P Direct material required per 100 boxes: Paperboard ($0.40 per pound) 35 pounds 75 pounds Corrugating medium ($0.20 per...
Revenue recognition at a point in time or over time Kleymenova Consulting, Inc., enters into a...
Revenue recognition at a point in time or over time Kleymenova Consulting, Inc., enters into a contract to provide consulting services 1. The consulting services are the provision of technical computer assistance as needed. For $25,000 per month, whenever the client has a problem, it contacts Kleymenova, which dispatches a consultant to address the problem at no additional charge. 2. The consulting services are to develop a new customer payment collection system for the client. The $300,000 contract price is...
Problem 9-42 Preparation of Master Budget (LO 9-3, 9-4, 9-5) [The following information applies to the...
Problem 9-42 Preparation of Master Budget (LO 9-3, 9-4, 9-5) [The following information applies to the questions displayed below.] FreshPak Corporation manufactures two types of cardboard boxes used in shipping canned food, fruit, and vegetables. The canned food box (type C) and the perishable food box (type P) have the following material and labor requirements. Type of Box C P Direct material required per 100 boxes: Paperboard ($0.34 per pound) 50 pounds 90 pounds Corrugating medium ($0.17 per pound) 40...
Problem 5-20 CVP Applications: Break-Even Analysis; Cost Structure; Target Sales [LO5-1, LO5-3, LO5-4, LO5-5, LO5-6, LO5-8]...
Problem 5-20 CVP Applications: Break-Even Analysis; Cost Structure; Target Sales [LO5-1, LO5-3, LO5-4, LO5-5, LO5-6, LO5-8] Northwood Company manufactures basketballs. The company has a ball that sells for $34. At present, the ball is manufactured in a small plant that relies heavily on direct labor workers. Thus, variable expenses are high, totaling $24.00 per ball, of which 71% is direct labor cost. Last year, the company sold 30,000 of these balls, with the following results: Sales (30,000 balls) $ 1,020,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT