Question

In: Accounting

Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long...

Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9]

In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $3,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows:

Balance Sheet
Accounts receivable (from construction progress billings) $ 46,000
Construction in progress $ 300,000
Less: Billings on construction contract (290,000 )
Cost and profit of uncompleted contracts in excess of billings 10,000
Income Statement
Income (before tax) on the contract recognized in 2021 $ 36,000


Required:
1. What was the cost of construction actually incurred in 2021?
2. How much cash was collected in 2021 on this contract?
3. What was the estimated cost to complete as of the end of 2021?
4. What was the estimated percentage of completion used to calculate revenue in 2021? (Round your percentage answer to 2 decimal places.)

1. Actual costs incurred in 2021
2. Cash collections in 2021
3. Estimated cost to complete
4. Estimated percentage %

Solutions

Expert Solution

PLEASE....UPVOTE....THANK.YOU....SO..MUCH....


Related Solutions

Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9]...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,100,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 308,000 $ 1,615,000 Estimated costs to complete as of 12/31 1,232,000 0 Billings during the year 390,000 1,640,000 Cash collections during the year 270,000 1,760,000...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9]...
Exercise 5-20 Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO5-8, 5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000. In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3]...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3] Walsh Company manufactures and sells one product. The following information pertains to each of the company’s first two years of operations: Variable costs per unit: Manufacturing: Direct materials $ 23 Direct labor $ 16 Variable manufacturing overhead $ 4 Variable selling and administrative $ 3 Fixed costs per year: Fixed manufacturing overhead $ 240,000 Fixed selling and administrative expenses $ 90,000 During its first...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3]...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3] Walsh Company manufactures and sells one product. The following information pertains to each of the company’s first two years of operations: Variable costs per unit: Manufacturing: Direct materials $ 22 Direct labor $ 14 Variable manufacturing overhead $ 4 Variable selling and administrative $ 3 Fixed costs per year: Fixed manufacturing overhead $ 400,000 Fixed selling and administrative expenses $ 70,000 During its first...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3]...
Exercise 6-9 (Algo) Variable and Absorption Costing Unit Product Costs and Income Statements [LO6-1, LO6-2, LO6-3] Walsh Company manufactures and sells one product. The following information pertains to each of the company’s first two years of operations: Variable costs per unit: Manufacturing: Direct materials $ 25 Direct labor $ 17 Variable manufacturing overhead $ 2 Variable selling and administrative $ 1 Fixed costs per year: Fixed manufacturing overhead $ 400,000 Fixed selling and administrative expenses $ 80,000 During its first...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a...
P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,000 $450,000 $610,000 Estimated costs to complete 330,000 150,000 –0– Progress billings...
Exercise 3-19 (Algo) Calculating ratios; solve for unknowns [LO3-8] The current asset section of Guardian Consultant’s...
Exercise 3-19 (Algo) Calculating ratios; solve for unknowns [LO3-8] The current asset section of Guardian Consultant’s balance sheet consists of cash, accounts receivable, and prepaid expenses. The 2021 balance sheet reported the following: cash, $1,330,000; prepaid expenses, $390,000; long-term assets, $2,700,000; and shareholders’ equity, $2,800,000. The current ratio at the end of the year was 2.5 and the debt to equity ratio was 1.3. Required: Determine the following 2021 amounts and ratios: (Round your "The acid-test ratio" answer to 1...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT