ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of...

ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of Arizona. The project will begin in 2017 and be completed in 2018. The cost of construction is expected to be $1,875,000.

Below is a summary of events for 2017 and 2018:

2017

2018

Costs incurred during the year

$ 712,500

$1,138,250

Estimated costs to complete

1,037,500

0

Billings during the year

850,000

1,150,000

Cash collections during the year

750,000

1,000,000

ABC Construction Co. recognizes revenue upon completion when accounting for long-term contracts.

a. Prepare all journal entries to record costs, billings, collections, and any profit recognition for ABC Construction Co. activities for 2017 only.

b. Prepare any journal entry needed for profit recognition only for ABC Construction Co. activities for 2018.

Solutions

Expert Solution


Related Solutions

In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The construction is expected to take 3 years.  The contract price is $50 million.  The actual costs incurred each year, the estimated costs of completing the project as of the end of each year, the progress billings for each year, and the collections of those billings each year are presented in the chart below. 2020 2021 2022 Actual costs incurred during each individual year $10,000,000 15,000,000 12,500,000...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract provided for progress payments. RCL’s accounting year ends December 31. Work began under the contract on August 1, 2019, and was completed on October 31, 2021. RCL uses the percentage-of-completion method to account for this long-term contract. Construction activities are summarized below: 2019 2020 2021 Construction costs incurred to date 180,000 630,000 825,000 Estimated remaining costs to complete 630,000 190,000 0 Progress Billings during...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by...
Thrasher Construction Co. was contracted to construct a building for $975,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher’s accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: 20X5 Construction costs incurred during the year, $180,000; estimated costs to complete, $630,000; progress billings during the year, $153,000; and collections, $140,000. 20X6...
In January, ABC Co. in U.S. signed a contract to buy a factory in U.K for...
In January, ABC Co. in U.S. signed a contract to buy a factory in U.K for £ 2,500,000 payable 3 months later in April. Since the contract is in pound rather than dollar, ABC Co. is considering hedging alternatives to reduce the risk of exchange rate from the purchase. Given the information below: Spot rate = $1.40/£ 3 month forward rate = $1.38/£ ABC's cost of capital is 11% p.a UK 3-month borrowing rate is 2.5% UK 3-month lending rate...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office building for $40,000,000. The scheduled construction costs follow. Year Cost 2016 $9,000,000 2017 15,000,000 2018 6,000,000 Total $30,000,000 The building is completed in 2018. For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods. a. Percentage-of-completion method 2016 2017 2018 Revenue Answer Answer Answer Expense Answer Answer Answer Gross Profit Answer Answer Answer...
On January 12, 2009, Capsule Corp. signed a $4 million contract to construct an office and...
On January 12, 2009, Capsule Corp. signed a $4 million contract to construct an office and warehouse for a small wholesale company. The project was originally expected to be completed in two years, but difficulties in hiring a sufficient pool of skilled workers extended the completion date by an extra year. As well, significant increases in the price of steel in the second year resulted in cost overruns on the project. Capsule Corp. was able to negotiate a partial recovery...
During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000.   The job...
During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000.   The job was completed in 2017. The following information is available: 2015 2016 2017 Costs incurred to date 500,000 900,000 1,100,000 Estimated costs to complete 600,000 200,000 0 Billings to date 500,000 1,400,000 2,000,000 Collections to date 450,000 1,300,000 1,800,000 Instructions: (a) Compute the amount of gross profit to be recognized each year assuming the percentage of       completion method is used. (b) ****EXTRA CREDIT -...
Brick Ltd is a building construction company. On 1July 2017, Brick Ltd signed a contract with...
Brick Ltd is a building construction company. On 1July 2017, Brick Ltd signed a contract with Pear Ltd to build a factory. The contract price was $ 12,000,000. The relevant information is as follows: Financial year ending 30 June: Construction costs for year Billings and payments for year 2018 $ 3,500,000 $ 3,000,000 2019 $ 5,000,000 $ 5,000,000 2020 $ 1,500,000 $ 4,000,000 Pear Ltd will be in control of the asset throughout the construction process. The contract is completed...
ABC Corp (a French company) signed a contract with XYZ Co (a Moroccan company) that contains...
ABC Corp (a French company) signed a contract with XYZ Co (a Moroccan company) that contains the following clause: "Any dispute between the parties that is not settled amicably within 30 days shall be finally settled through arbitration in accordance with the rules of the ICC. The location of the arbitration shall be Paris, France and the language shall be French."   ABC pursued XYZ for breach of contract and was awarded damages by the arbitration tribunal in the amount of...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060. Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT