Question

In: Accounting

In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The...

In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The construction is expected to take 3 years.  The contract price is $50 million.  The actual costs incurred each year, the estimated costs of completing the project as of the end of each year, the progress billings for each year, and the collections of those billings each year are presented in the chart below.

2020

2021

2022

Actual costs incurred during each individual year

$10,000,000

15,000,000

12,500,000

Estimated costs (in future years) to complete, as of the end of each individual year

30,000,000

14,000,000

---

Billings during each individual year

11,000,000

16,500,000

22,500,000

Collections during each individual year

10,275,000

15,225,000

22,000,000

  1. Prepare, in good, easy-to-follow form, a schedule computing the amount of revenues or gross profit (your choice) to be recognized on this project in each year using the percentage-of-completion.
  2. Prepare all the journal entries required in 2021 by the information provided.
  3. Explain, precisely, the amounts to be reported in the 2020 income statement and the December 31, 2017 balance sheet for this contract.

Solutions

Expert Solution

Sollution A

Computation of the amount of Gross profit to be recognized
Working 2020 2021 2022
a Cost to date(cumulative) 10,000,000 25,000,000 37,500,000
b Estimated Total cost to complete 40,000,000 39,000,000 37,500,000
c Billing 11,000,000 16,500,000 22,500,000
d Cash collected 10,275,000 15,225,000 22,000,000
e % Completed (a/b) cost incurred to date /Estimated total cost 25.00 64.10 100.00
f Revenue Recognised (Contract price *percentage Of Completion) - Revenue Recognised Previously 12,500,000 19,551,282 17,948,718
g Costs under the percentage of completion method: 10,000,000 15,000,000 12,500,000
h Gross profit (f-g) 2,500,000 4,551,282 5,448,718

Sollution B

Journal Entries - Coco Corporation for the year 2021
as per Percentage-of-completion method.
Date Particulars Debit Credit
1 Construction in progress $15,000,000.00
Accounts payable $15,000,000.00
(To record Incurring cost)
2 Accounts Receivable a/c $16,500,000.00
Billing on Construction in progress $16,500,000.00
(To record billing)
3 Cash A/c   $15,225,000.00
Accounts Receivable $15,225,000.00
(Being Received payment)
4 Construction Expense $15,000,000.00
Construction in progress $4,551,282.05
construction Revenue $19,551,282.05
(for period end adjustment for revenue )

Sollution C

Income Statement 2020 2021 2022
Revenue recognized 12,500,000 19,551,282 17,948,718
Costs Incurred 10,000,000 15,000,000 12,500,000
Gross Profit/(Loss) 2,500,000 4,551,282 5,448,718
Partial Balance sheet
Balance sheet 2020 2021 2022
Contract Assets:
Construction in progress 1,500,000 4,550,000 0
Accounts Receivable 725,000 2,000,000 2,500,000
Total 2,225,000 6,550,000 2,500,000
Working for Balance sheet
2020 2021 2022
Construction in progress
Construction in progress 12,500,000 32,050,000 50,000,000
Less:- Billing 11,000,000 27,500,000 50,000,000
Cost In Excess of Billing 1,500,000 4,550,000 0
Accounts Receivable
Opening Balance 0 725000 2000000
Add:- Billing During The year 11,000,000 16,500,000 22,500,000
Less: Cash Collected 10,275,000 15,225,000 22,000,000
Closing Balance 725,000 2,000,000 2,500,000

Related Solutions

ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of...
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of Arizona. The project will begin in 2017 and be completed in 2018. The cost of construction is expected to be $1,875,000. Below is a summary of events for 2017 and 2018: 2017 2018 Costs incurred during the year $ 712,500 $1,138,250 Estimated costs to complete 1,037,500 0 Billings during the year 850,000 1,150,000 Cash collections during the year 750,000 1,000,000 ABC Construction Co. recognizes...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060. Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During 2020, Crane, Inc. incurred costs of $1,798,560, billed its customers for $1,125,000, and collected $910,000. At December 31, 2020, the estimated additional costs to complete the project total $3,197,440. Prepare Crane’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During 2020, Stellar, Inc. incurred costs of $1,941,020, billed its customers for $1,138,000, and collected $904,000. At December 31, 2020, the estimated additional costs to complete the project total $3,304,980. Prepare Stellar’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During...
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During 2020, Sarasota, Inc. incurred costs of $1,639,900, billed its customers for $1,300,000, and collected $1,055,000. At December 31, 2020, the estimated additional costs to complete the project total $3,650,100. Prepare Sarasota’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office building for $40,000,000. The scheduled construction costs follow. Year Cost 2016 $9,000,000 2017 15,000,000 2018 6,000,000 Total $30,000,000 The building is completed in 2018. For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods. a. Percentage-of-completion method 2016 2017 2018 Revenue Answer Answer Answer Expense Answer Answer Answer Gross Profit Answer Answer Answer...
On January 12, 2009, Capsule Corp. signed a $4 million contract to construct an office and...
On January 12, 2009, Capsule Corp. signed a $4 million contract to construct an office and warehouse for a small wholesale company. The project was originally expected to be completed in two years, but difficulties in hiring a sufficient pool of skilled workers extended the completion date by an extra year. As well, significant increases in the price of steel in the second year resulted in cost overruns on the project. Capsule Corp. was able to negotiate a partial recovery...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          24,000         29,000 Collections to date                     4,000           14,000         25,000 The journal entry to record Billings on Construction in Process in 2021 has the amount of _________.
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date $8,000 $10,000 $22,000 Estimated costs to complete 12,000 6,000 -0- Customer billings to date 9,000 21,000 29,000 Collections to date 4,000 14,000 25,000 If the company uses the percentage-of-completion method, an inventory/current...
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400....
On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400. Joe estimated total construction costs would be $12,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                                              2020                       2021                      2022        Total costs incurred to date                                        $4,500                    $7,920                  $13,800 Estimated costs to complete                                         7,500                      5,280                     -0- Customer billings to date                                             6,600                    12,000                    16,800 Collections to date                                                      6,000                    10,500                    16,500 Instructions: Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT