In: Accounting
In 2020 Coco Corporation signed a contract to construct a major office building for a developer. The construction is expected to take 3 years. The contract price is $50 million. The actual costs incurred each year, the estimated costs of completing the project as of the end of each year, the progress billings for each year, and the collections of those billings each year are presented in the chart below.
2020 |
2021 |
2022 |
|
Actual costs incurred during each individual year |
$10,000,000 |
15,000,000 |
12,500,000 |
Estimated costs (in future years) to complete, as of the end of each individual year |
30,000,000 |
14,000,000 |
--- |
Billings during each individual year |
11,000,000 |
16,500,000 |
22,500,000 |
Collections during each individual year |
10,275,000 |
15,225,000 |
22,000,000 |
Sollution A
Computation of the amount of Gross profit to be recognized | |||||
Working | 2020 | 2021 | 2022 | ||
a | Cost to date(cumulative) | 10,000,000 | 25,000,000 | 37,500,000 | |
b | Estimated Total cost to complete | 40,000,000 | 39,000,000 | 37,500,000 | |
c | Billing | 11,000,000 | 16,500,000 | 22,500,000 | |
d | Cash collected | 10,275,000 | 15,225,000 | 22,000,000 | |
e | % Completed (a/b) | cost incurred to date /Estimated total cost | 25.00 | 64.10 | 100.00 |
f | Revenue Recognised | (Contract price *percentage Of Completion) - Revenue Recognised Previously | 12,500,000 | 19,551,282 | 17,948,718 |
g | Costs under the percentage of completion method: | 10,000,000 | 15,000,000 | 12,500,000 | |
h | Gross profit (f-g) | 2,500,000 | 4,551,282 | 5,448,718 |
Sollution B
Journal Entries - Coco Corporation for the year 2021 | |||
as per Percentage-of-completion method. | |||
Date | Particulars | Debit | Credit |
1 | Construction in progress | $15,000,000.00 | |
Accounts payable | $15,000,000.00 | ||
(To record Incurring cost) | |||
2 | Accounts Receivable a/c | $16,500,000.00 | |
Billing on Construction in progress | $16,500,000.00 | ||
(To record billing) | |||
3 | Cash A/c | $15,225,000.00 | |
Accounts Receivable | $15,225,000.00 | ||
(Being Received payment) | |||
4 | Construction Expense | $15,000,000.00 | |
Construction in progress | $4,551,282.05 | ||
construction Revenue | $19,551,282.05 | ||
(for period end adjustment for revenue ) |
Sollution C
Income Statement | 2020 | 2021 | 2022 |
Revenue recognized | 12,500,000 | 19,551,282 | 17,948,718 |
Costs Incurred | 10,000,000 | 15,000,000 | 12,500,000 |
Gross Profit/(Loss) | 2,500,000 | 4,551,282 | 5,448,718 |
Partial Balance sheet | |||
Balance sheet | 2020 | 2021 | 2022 |
Contract Assets: | |||
Construction in progress | 1,500,000 | 4,550,000 | 0 |
Accounts Receivable | 725,000 | 2,000,000 | 2,500,000 |
Total | 2,225,000 | 6,550,000 | 2,500,000 |
Working for Balance sheet | |||
2020 | 2021 | 2022 | |
Construction in progress | |||
Construction in progress | 12,500,000 | 32,050,000 | 50,000,000 |
Less:- Billing | 11,000,000 | 27,500,000 | 50,000,000 |
Cost In Excess of Billing | 1,500,000 | 4,550,000 | 0 |
Accounts Receivable | |||
Opening Balance | 0 | 725000 | 2000000 |
Add:- Billing During The year | 11,000,000 | 16,500,000 | 22,500,000 |
Less: Cash Collected | 10,275,000 | 15,225,000 | 22,000,000 |
Closing Balance | 725,000 | 2,000,000 | 2,500,000 |