Question

In: Accounting

Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...

Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060.

Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is required, select "No entry" for the account titles and enter 0 for the amounts.)

Account Titles and Explanation

Debit

Credit

enter an account title to record costs incurred enter a debit amount enter a credit amount
enter an account title to record costs incurred enter a debit amount enter a credit amount

(To record costs incurred.)

enter an account title to record billings enter a debit amount enter a credit amount
enter an account title to record billings enter a debit amount enter a credit amount

(To record billings.)

enter an account title to record collections enter a debit amount enter a credit amount
enter an account title to record collections enter a debit amount enter a credit amount

(To record collections.)

enter an account title to recognize revenue enter a debit amount enter a credit amount
enter an account title to recognize revenue enter a debit amount enter a credit amount
enter an account title to recognize revenue enter a debit amount enter a credit amount

(To recognize revenue.)

Solutions

Expert Solution

Account Titles and Explanation

Debit

Credit

Construction in Process

$1,589,940

Materials,Cash, Payables, etc

$1,589,940

(To record costs incurred.)

Accounts Receivable

$1,156,000

Billingson Construction in Process

$1,156,000

(To record billings.)

Cash

$894,000

Accounts Receivable

$894,000

(To record collections.)

Construction in Process

[1494000*33%]

$493020

Construction Expenses

$1,589,940

Revenue from Long-Term Contracts

(6,312,000*33%)

$2082960

(To recognize revenue.)

Working:

Total Cost   =   Cost Incurred + the estimated future costs to complete the project

                  =$1,589,940+$3,228,060 = $4818000

Total Profit = Contract Value -Total cost

=$6,312,000-4818000 = $1494000

Percent of Completion = Cost Incurred / Total Cost

                                    =   $1,589,940/ 4818000

                                    =   33%


Related Solutions

Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During 2020, Crane, Inc. incurred costs of $1,798,560, billed its customers for $1,125,000, and collected $910,000. At December 31, 2020, the estimated additional costs to complete the project total $3,197,440. Prepare Crane’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During 2020, Stellar, Inc. incurred costs of $1,941,020, billed its customers for $1,138,000, and collected $904,000. At December 31, 2020, the estimated additional costs to complete the project total $3,304,980. Prepare Stellar’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During...
Sarasota, Inc. began work on a $6,504,000 contract in 2020 to construct an office building. During 2020, Sarasota, Inc. incurred costs of $1,639,900, billed its customers for $1,300,000, and collected $1,055,000. At December 31, 2020, the estimated additional costs to complete the project total $3,650,100. Prepare Sarasota’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Concord, Inc. began work on a $6,466,000 contract in 2017 to construct an office building. During...
Concord, Inc. began work on a $6,466,000 contract in 2017 to construct an office building. During 2017, Concord, Inc. incurred costs of $1,547,340, billed its customers for $1,085,000, and collected $1,013,000. At December 31, 2017, the estimated additional costs to complete the project total $3,003,660. Prepare Concord’s 2017 journal entries using the percentage-of-completion method.
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The construction is expected to take 3 years.  The contract price is $50 million.  The actual costs incurred each year, the estimated costs of completing the project as of the end of each year, the progress billings for each year, and the collections of those billings each year are presented in the chart below. 2020 2021 2022 Actual costs incurred during each individual year $10,000,000 15,000,000 12,500,000...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred costs of $292,500, billed its customer for $213,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $161,340. Prepare Tamarisk’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred costs of $250,000, billed its customer for $200,000, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $178,890. Prepare Cullumber’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          24,000         29,000 Collections to date                     4,000           14,000         25,000 The journal entry to record Billings on Construction in Process in 2021 has the amount of _________.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT