In: Operations Management
In managing project conflicts, what does it mean to employ “a smoothing” approach to resolve a particular conflict? ……………………………………………………………… ………………………………………………………………………………………………………………………………………………………………………………………………
What makes an individual a stakeholder in a project? ………………………………………………………………………………………………………………………………………………………………………………………………
A process that ensures that the descriptions of a project’s products and deliverables are correct and complete is known as ………………………………………………………..
The variance and the pessimistic time estimate of a project activity are 32/3 and 12 days respectively. Find the activity’s optimistic time estimate. ……………………………..
All fast-tracked projects are crashed. True or False?
The total float along a critical path in a project network is zero. True or False?
AOA is a precedence diagramming method of project activity sequencing. True or False?
A project team comprises 5 members. The number of communication channels available to them is 15. True or False?
An insurable risk presents opportunity for loss only. True or False?
Q1) When the relationships are more important than the goals of the project, people make use of a smoothing approach to resolve project conflict. in this approach, people try to accommodate , E.g., Its's okay, i will make it work". In this although relationships are saved, bitterness gets in for a longer run. The person who accommodates is been taken advantage of.
Q2) An individual who is actively involved, have his influence over the project or its deliverables and can get affected positively or negatively due to work or output of the project is a stakeholder.
Q3) The process is known as Project Scope Management. It ensure that the project has been defined properly, it includes what work is to be done and what work is not to be included for project completion. It ensures that the project is completely without any unnecessary effort.
Q4) Variance = {(P-O)/6}2
32/3 = {(12-O)/6}2
32/3*36 = (12-O)2
384 = (12-O)2
19.59 = 12-O
O= - 7.595 i.e. Optimistic time estimate