Question

In: Statistics and Probability

Priority Dispatching Rules Consider the following data: Job Remaining Processing time (days) Remaining time until due...

Priority Dispatching Rules

  1. Consider the following data:

Job

Remaining Processing time

(days)

Remaining time until due date

(days)

Critical ratio

(?)

A

20

30

B

30

50

C

10

25

D

16

80

E

18

12

  1. Calculate for each job the relative critical ratio.
  2. Analyze the calculated critical ratio.
  3. Basing on the calculated CR, specify the scheduling order of each job. Justify your answer.
  4. Specify and explain a second dispatch rule that can be adopted.   
  5. Among the two rules which seems to be the most effective. Justify your answer.

Solutions

Expert Solution


Related Solutions

Job Remaining Processing time (days) Remaining time until due date (days) Critical ratio (?) A 20...
Job Remaining Processing time (days) Remaining time until due date (days) Critical ratio (?) A 20 30 B 30 50 C 10 25 D 16 80 E 18 12 Calculate for each job the relative critical ratio. Analyze the calculated critical ratio. Basing on the calculated CR, specify the scheduling order of each job. Justify your answer. Specify and explain a second dispatch rule that can be adopted.    Among the two rules which seems to be the most effective....
Consider the following information on job times and due dates (in hours). Job Job Time Due...
Consider the following information on job times and due dates (in hours). Job Job Time Due Date A 4.00 8.00 B 1.50 5.00 C 4.50 9.00 D 4.25 17.00 E 2.25 6.00 You are asked to determine the processing sequence using Shortest Processing Time (SPT) and Earliest Due Date (EDD) rule; and to decide which sequence is better for average job flow time and the average job tardiness performance measures. FORMAT FOR ENTRIES: • Sequence should be entered in the...
Average flow and average delay based on FCFS, EDD, and SPT Job Job time (days) Due...
Average flow and average delay based on FCFS, EDD, and SPT Job Job time (days) Due date (days from now) A 12 15 B 6 24 C 14 20 D 3 8
Consider the following consumption data of the same individual over time (two days). Day p1 x1...
Consider the following consumption data of the same individual over time (two days). Day p1 x1 p2 x2 1 2 1 3 2 2 3 2 2 1 Part a. Is the consumer exhibiting consistent revealed preferences? Show your conclusion mathematically. Part b. What if the data of the two days above are actually coming from two different individuals?
Customer A's order arrived 8 days ago. Processing time is estimated to be 25 days. The...
Customer A's order arrived 8 days ago. Processing time is estimated to be 25 days. The promised due date is 40 days from now. What is customer A's flow time in the system?
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity C is __________ a. 0 b. 2 c. 8 d. 4
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) MOST LIKELY TIME (days) PESSIMISTIC TIME (days) A - 5 10 15 B - 10 12 14 C - 10 10 10 D B,C 2 4 6 E A 4 8 12 F A 4 8 12 G D,E 10 12 14 I F 4 8 12 J G 2 4 6 The total slack for activity F is __________ a. 8 b. 4 c. 2 d. 0
Consider the following time series data.
Consider the following time series data. Week123456Value181516131716a. Choose the correct time series plot.What type of pattern exists in the data? b. Develop a three-week moving average for this time series. Compute MSE and a forecast for week 7. Round your answers to two decimal places. WeekTime Series ValueForecast118215316413517616 MSE: The forecast for week 7: c. Use α = 0.2 to compute the exponential smoothing values for the time series. Compute MSE and a forecast for week 7. Round your answers to two decimal places. WeekTime Series ValueForecast118215316413517616MSE: The...
Consider the following time series data.
  Consider the following time series data. Quarter Year 1 Year 2 Year 3 1 5 8 10 2 2 4 8 3 1 4 6 4 3 6 8 (b) Use a multiple regression model with dummy variables as follows to develop an equation to account for seasonal effects in the data. Qtr1 = 1 if Quarter 1, 0 otherwise; Qtr2 = 1 if Quarter 2, 0 otherwise; Qtr3 = 1 if Quarter 3, 0 otherwise.   If required,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT