In: Operations Management
Job |
Remaining Processing time (days) |
Remaining time until due date (days) |
Critical ratio (?) |
A |
20 |
30 |
|
B |
30 |
50 |
|
C |
10 |
25 |
|
D |
16 |
80 |
|
E |
18 |
12 |
Given:
Job |
Remaining Processing time (days) |
Remaining time until due date (days) |
A | 20 | 30 |
B | 30 | 50 |
C | 10 | 25 |
D | 16 | 80 |
E | 18 | 12 |
Calculate for each job the relative critical ratio.
Answer: Critical ratio is calculated as Time remained for due date/ Remiaining processing time.
Therefore, Critical ratio of Job A is 30/20= 1.5
Critical ratios are calculated in the same manner for all the jobs. The calculated critical ratios are included in the table below
Job |
Remaining Processing time (days) |
Remaining time until due date (days) |
Critical ratio |
A | 20 | 30 | 1.5 |
B | 30 | 50 | 1.67 |
C | 10 | 25 | 2.5 |
D | 16 | 80 | 5 |
E | 18 | 12 | 0.66 |
Analyze the calculated critical ratio.
The critical ratio is lowest for Job E. Therefore, it should be scheduled first
Basing on the calculated CR, specify the scheduling order of each job. Justify your answer.
The sequence of job is E-A-B-C-D. The jobs are scheduled based on the their critical ratios. The job with lowest critical ratio is scheduled at the beginnng and subsequent jobs are scheduled in the increasing ratio of critical ratio.
Specify and explain a second dispatch rule that can be adopted.
The second rule which can be adopted is Earliest due date first. Both the methods are expalined below
Job |
Remaining Processing time (days) |
Remaining time until due date (days) |
Critical ratio | Start | Finish | Flow time | Lateness |
A | 18 | 12 | 0.66 | 0 | 18 | 18 | 6 |
B | 20 | 30 | 1.5 | 18 | 38 | 38 | 8 |
C | 30 | 50 | 1.67 | 38 | 68 | 68 | 18 |
D | 10 | 25 | 2.5 | 68 | 78 | 78 | 53 |
E | 16 | 80 | 5 | 78 | 94 | 94 | 14 |
mean | 59.2 | 19.8 |
second dispatch rule: Earliest due date first
Job |
Remaining Processing time (days) |
Remaining time until due date (days) |
Critical ratio | Start | Finish | Flow time | Lateness |
E | 18 | 12 | 0.66 | 0 | 18 | 18 | 6 |
A | 20 | 30 | 1.5 | 18 | 28 | 28 | 3 |
B | 30 | 50 | 1.67 | 28 | 48 | 48 | 18 |
C | 10 | 25 | 2.5 | 48 | 78 | 78 | 28 |
D | 16 | 80 | 5 | 78 | 94 | 94 | 14 |
mean | 53.2 | 13.8 |
Among the two rules which seems to be the most effective. Justify your answer
Among the two methods, the second method: Earliest due date is most effectoive because it has an average lateness less than first method.