Question

In: Operations Management

Average flow and average delay based on FCFS, EDD, and SPT Job Job time (days) Due...

Average flow and average delay based on FCFS, EDD, and SPT

Job

Job time (days)

Due date (days from now)

A

12

15

B

6

24

C

14

20

D

3

8

Solutions

Expert Solution

1. FIRST COME FIRST SERVE


JOB

PROCESSING TIME

DUE TIME

FLOW TIME

JOB LATENESS

A

12

15

0 + 12 = 12

B

6

24

12 + 6 = 18

C

14

20

18 + 14 = 32

12

D

3

8

32 + 3 = 35

27


TOTAL FLOW TIME = 12 + 18 + 32 + 35 = 97

AVERAGE COMPLETION TIME = FLOW TIME / N = 97 / 4 = 24.25

AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 39 / 4 = 9.75


2. EARLIEST DUE DATE



JOB

PROCESSING TIME

DUE TIME

FLOW TIME

JOB LATENESS

D

3

8

0 + 3 = 3

A

12

15

3 + 12 = 15

0

C

14

20

15 + 14 = 29

9

B

6

24

29 + 6 = 35

11


TOTAL FLOW TIME = 3 + 15 + 29 + 35 = 82

AVERAGE COMPLETION TIME = FLOW TIME / N = 82 / 4 = 20.5

AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 20 / 4 = 5


3. SHORTEST PROCESSING TIME


JOB

PROCESSING TIME

DUE TIME

FLOW TIME

JOB LATENESS

D

3

8

0 + 3 = 3

B

6

24

3 + 6 = 9

A

12

15

9 + 12 = 21

6

C

14

20

21 + 14 = 35

15

TOTAL FLOW TIME = 3 + 9 + 21 + 35 = 68

AVERAGE COMPLETION TIME = FLOW TIME / N = 68 / 4 = 17

AVERAGE JOB LATENESS = TOTAL JOB LATENESS / N = 21 / 4 = 5.25

** Leaving a thumbs-up would really help me out. Let me know if you face any problems.


Related Solutions

Job Remaining Processing time (days) Remaining time until due date (days) Critical ratio (?) A 20...
Job Remaining Processing time (days) Remaining time until due date (days) Critical ratio (?) A 20 30 B 30 50 C 10 25 D 16 80 E 18 12 Calculate for each job the relative critical ratio. Analyze the calculated critical ratio. Basing on the calculated CR, specify the scheduling order of each job. Justify your answer. Specify and explain a second dispatch rule that can be adopted.    Among the two rules which seems to be the most effective....
Priority Dispatching Rules Consider the following data: Job Remaining Processing time (days) Remaining time until due...
Priority Dispatching Rules Consider the following data: Job Remaining Processing time (days) Remaining time until due date (days) Critical ratio (?) A 20 30 B 30 50 C 10 25 D 16 80 E 18 12 Calculate for each job the relative critical ratio. Analyze the calculated critical ratio. Basing on the calculated CR, specify the scheduling order of each job. Justify your answer. Specify and explain a second dispatch rule that can be adopted.    Among the two rules...
Consider the following information on job times and due dates (in hours). Job Job Time Due...
Consider the following information on job times and due dates (in hours). Job Job Time Due Date A 4.00 8.00 B 1.50 5.00 C 4.50 9.00 D 4.25 17.00 E 2.25 6.00 You are asked to determine the processing sequence using Shortest Processing Time (SPT) and Earliest Due Date (EDD) rule; and to decide which sequence is better for average job flow time and the average job tardiness performance measures. FORMAT FOR ENTRIES: • Sequence should be entered in the...
Suppose an airline claims that its flights are consistently on time with an average delay of...
Suppose an airline claims that its flights are consistently on time with an average delay of at most 15 minutes. It claims that the average delay is so consistent that the variance is no more than 150 minutes. Doubting the consistency part of the claim, a disgruntled traveler calculates the delays for his next 25 flights. The average delay for those 25 flights is 22 minutes with a standard deviation of 15 minutes. Use .05 level of significance. What is...
Suppose an airline claims that its flights are consistently on time with an average delay of...
Suppose an airline claims that its flights are consistently on time with an average delay of at most 15 minutes. It claims that the average delay is so consistent that the variance is no more than 15 minutes. Doubting the consistency part of the claim, a disgruntled traveler calculates the delays for his next 25 flights. The average delay for those 25 flights is 22 minutes with a standard deviation of 15 minutes. a) Hypothesis b) Test statistics c) P...
On Time Airlines claims their average delay is less than 15 minutes per flight. A random...
On Time Airlines claims their average delay is less than 15 minutes per flight. A random sample of 35 flights has a sample mean of 14 minutes and standard deviation of 7 minutes. You will need to test the claim that the average delay is less than 15 minutes per flight using a 2.5% level of significance. a) State the hypotheses b) Find the rejection region. c) Will you reject or retain the null hypothesis? Show all work to support...
Delta Air Lines reports that the average delay time of all arriving domestic flights in 2018 was 60 minutes.
Delta Air Lines reports that the average delay time of all arriving domestic flights in 2018 was 60 minutes. A flight is considered delayed if it arrives more than 15 minutes later than the scheduled arrival time. Average delayed minutes are calculated from delayed flights only. A random sample of 20 Delta flights in 2018 had an average delay of 65 minutes with a standard deviation of 5 minutes. a) Categorical or Quantitative Variable? b) Is 60 minutes a Sample...
it has been hypothesized that the average germination time for a certain seed is 4 days....
it has been hypothesized that the average germination time for a certain seed is 4 days. an experiment involving 32 seeds revealed an average germination time of 6 days. at the level of significance 0.05. is there evidence that average germination times has increased? (standard deviation=0.80 days). P-value method
Based on recent data, there are on average 1.3 days per winter where snowfall reaches more...
Based on recent data, there are on average 1.3 days per winter where snowfall reaches more than 6 inches in Central Park, New York City. We’ll call these “snow days”. Assume that there were more than 2 “snow days” this winter. What is the chance that exactly 4 such days occur?
2018 average figures (i.e.: not job-specific) show women working a full-time job earning 81.1% as much...
2018 average figures (i.e.: not job-specific) show women working a full-time job earning 81.1% as much as male counterparts. When controlling for occupational distributions this gap noticeably narrows (although it does not eliminate the disparity). Part 1. Although a gender pay gap is unfortunately still present even when controlling for occupational distributions, explain why the gap narrows. In other words, why does an average (woman/men) pay gap figure show a larger degree of disparity? Make sure to use proper terminology...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT