Question

In: Operations Management

Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...

Question Relates to Project Management

TERMS

CPI – Cost Performance Index

SPI – Schedule Performance Index

SV- Schedule Variance

CV- Cost Variance

Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater?

Well, the answer to that is straightforward! Right people! Right?  The answer is … is what class? WHAT DO YOU THINK? EXAMPLES PLEASE…

Solutions

Expert Solution

SPI

The Schedule performance index demonstrates value of earned value to planned value. After calculation if result is less than '1', It means that the ongoing project is behind schedule, If result SPI is bigger than one, it tell you that project is running ahead of its time, Same as it a perfect SPI indicates a perfectly scheduled project.

To obtain the percentage of difference in the schedule timing we have to subtract the SPI from one.

CPI

The Cost performance index demonstrate ratio of earned value to actual costs. Bigger result than one indicates that expenses are being done efficiently & lesser than one indicates less efficient project. It is used to measure efficiency of total expenses on o project.

Providing SPI or CPI to the CIO helps project to overcome current situation & find best solution to overcome issue is project is late. If the project is on time then this info may be exchanged with CIO to maintain same.


Related Solutions

Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Question - Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
what is the cost performance index ? what is the Schedule at completion ?
what is the cost performance index ?what is the Schedule at completion ?and what is the Estimate at completion ?Based on your project scenario which has been suggested by you or by your instructor and approved by your instructor, answer the following questions? Project Title : Daycare Mobile Application. Scenario Overview: Our project is a mobile application that called "Daycare" which helps parents and workers to do a lot of things such as: they can find children daycares easily, they...
The corruption perceptions index (CPI) is a comparative assessment of integrity performance for a variety of...
The corruption perceptions index (CPI) is a comparative assessment of integrity performance for a variety of countries. What are the trends or similarities between countries with the highest and lowest CPI 2016 scores?
53. What are the three primary constraints in project management? -A Schedule, cost, and deadline -...
53. What are the three primary constraints in project management? -A Schedule, cost, and deadline - B Outsourcing, sponsors, and budget - C Time, scope, and resources - D Testing, accptance, and operation - -54. Which document outlines participation by various roles in a project? -A Communication plan B- PERT chart - C Responsibility matrix D Gantt chart 55. The relationship among the variables of the triple constraints is such that if any one variable changes, at least one other...
Explain the Schedule management in the manhattan project?
Explain the Schedule management in the manhattan project?
Transparency International's Corruption Perceptions Index (CPI) is a comparative assessment of a country's integrity performance. Provide...
Transparency International's Corruption Perceptions Index (CPI) is a comparative assessment of a country's integrity performance. Provide a brief analysis (not a description) of this index and its ranking using concepts from the readings and no less than one additional source. Using the most recent data, identify the five countries with the lowest and the five with the highest CPI scores according to this index. What are the trends and similarities between CPI scores and the level of economic, political, and...
How the time management: Project Schedule, Schedule Monitoring, and Approval of Schedule Changes be used in...
How the time management: Project Schedule, Schedule Monitoring, and Approval of Schedule Changes be used in the real project management?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT