In: Computer Science
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value):
The data identified below was listed in a project’s status report.
At time of status report:
Planned Value of work (PV) = $70,000
Earned Value of work performed (EV) = $50,000
Actual Cost of work performed (AC) = $75,000
Original Planning:
Budgeted cost At Completion (BAC) = $110,000
Original length of the project is 15 months
Using the data, calculate the following:
a) Cost Performance Index (CPI). (1 mark)
b) Schedule Performance Index (SPI). (1 mark)
c) Expected cost At Completion (EAC). (1 mark)
d) Estimate To Complete (ETC).
e) The Schedule Variance (SV).
f) Discuss how the project is tracking (e.g. ahead or behind schedule, under or over budget)?
Answer a) through f) in one text box below:
a) Cost Performance Index (CPI).
Earned Value of work performed (EV) = $50,000
Actual Cost of work performed (AC) = $75,000
Cost Performance Index = (Earned Value) / (Actual Cost)
CPI = EV / AC
= $50,000/$75,000
=$0.666666667
Cost Performance Index=66.66%
You are earning less than what you are spending or are over budget if the CPI is less than one.
CPI is less than 1, the task is over budget.
b) Schedule Performance Index (SPI).
Planned Value of work (PV) = $70,000
Earned Value of work performed (EV) = $50,000
Schedule Performance Index = (Earned Value) / (Planned Value)
SPI = EV / PV
=$50,000/$70,000
=$0.714285714
Schedule Performance Index=71.42%
c) Expected cost At Completion (EAC).
Cost Performance Index(CPI)=$0.666666667
Budgeted cost At Completion (BAC) = $110,000
EAC= BAC / CPI
EAC=$110,000/$0.666666667
= $165 000
Expected cost At Completion=$165 000
d) Estimate To Complete (ETC).
Expected cost At Completion (EAC)=$165 000
Cost Performance Index(CPI)=$0.666666667
Actual Cost of work performed (AC) = $75,000
Estimate To Complete (ETC)=(Budgeted cost At Completion (BAC)-Earned Value of work performed (EV) /Cost Performance Index(CPI))
ETC = (EAC – AC)/CPI
= ( $165 000 -$75000)/$0.666666667
Estimate To Complete= $135,000
e) The Schedule Variance (SV).
Planned Value of work (PV) = $70,000
Earned Value of work performed (EV) = $50,000
Schedule Variance = Earned Value – Planned Value
SV = EV – PV
=$50,000-$70,000
=-$20,000
Schedule Variance =-$20,000
You are behind schedule if the Schedule Variance is negative.
f) Discuss how the project is tracking (e.g. ahead or behind schedule, under or over budget)?
SV = EV – PV
As SV is negative we are behind the schedule
Earned Value of work performed (EV) = $50,000
Actual Cost of work performed (AC) = $75,000
CV = EV – AC
=$50,000- $75,000
=-$25,000
You are over budget as the Cost Variance is negative.