Question

In: Computer Science

Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...

Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value):

The data identified below was listed in a project’s status report.

At time of status report:

Planned Value of work (PV) = $70,000

Earned Value of work performed (EV) = $50,000

Actual Cost of work performed (AC) = $75,000

Original Planning:

Budgeted cost At Completion (BAC) = $110,000

Original length of the project is 15 months

Using the data, calculate the following:

a) Cost Performance Index (CPI). (1 mark)

b) Schedule Performance Index (SPI). (1 mark)

c) Expected cost At Completion (EAC). (1 mark)

d) Estimate To Complete (ETC).

e) The Schedule Variance (SV).

f) Discuss how the project is tracking (e.g. ahead or behind schedule, under or over budget)?

Solutions

Expert Solution

a) Cost Performance Index (CPI)=Earned value of work performed (EV) / Actual Cost of work performed (CV)

Earned value of work performed (EV) = $50,000

Actual Cost of work performed (CV)=$75,000

Cost Performance Index (CPI)=50000/75000

=0.66 (over budget)

b) Schedule Performance Index (SPI)=Earned Value of work performed (EV) / Planned Value of work (PV)

Earned Value of work performed (EV)=$50,000

   Planned Value of work (PV)=$70,000

  Schedule Performance Index (SPI)=50000/70000

=0.71 (behind schedule)

c) Expected cost At Completion (EAC)=Budgeted cost At Completion (BAC) / Cost Performance Index (CPI)

Budgeted cost At Completion (BAC)=$110,000

  Cost Performance Index (CPI)=0.66

Expected cost At Completion (EAC)=110000/0.66

=$166,666.66

d) Estimate To Complete (ETC)=Expected cost At Completion (EAC) - Actual Cost of work performed (AC)

Expected cost At Completion (EAC)=$166,666.66

Actual Cost of work performed (AC) = $75,000

  Estimate To Complete (ETC)=$166,666.66 - $75,000

= $91666.66

e) The Schedule Variance (SV)=Earned Value of work performed (EV) - Planned Value of work (PV)

Earned value of work performed (EV) = $50,000

Planned Value of work (PV) = $70,000

The Schedule Variance (SV)=50000 - 70000

= -20,000 (behind schedule)

f) The project is over budget since Cost performance Index (CPI) is 0.66 which is less than 1 and the project is behind schedule since The Schedule Variance (SV) and Schedule Performance Index (SPI) are both less than 1


Related Solutions

Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Build an Earned Value Management (EVM) model using these variables: Planned Value: $45,000 i.Note for understanding,...
Build an Earned Value Management (EVM) model using these variables: Planned Value: $45,000 i.Note for understanding, this based on time, and what we expected to use based on time.  Your schedule variance is based on earned and planned. Actual Cost: $39,500 Earned Value (how much has been spent based on planned costs) : $43,500 i.Note for understanding, this usually based on expected costs at the task level.  In other words, for the tasks complete the project was expected to use this much...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Question - Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?  The answer is...
Prepare an earned value schedule for a public construction project improving the drainage system of a...
Prepare an earned value schedule for a public construction project improving the drainage system of a neighborhood street.
What are some examples of strategies for analyzing and measuring performance in project management? What are...
What are some examples of strategies for analyzing and measuring performance in project management? What are the strengths and drawbacks for these strategies?
How does project scope, project budget and earned value management conpare and contrast?
How does project scope, project budget and earned value management conpare and contrast?
Actual Cost, planned value and earned value of the activities of an ongoing project after 5...
Actual Cost, planned value and earned value of the activities of an ongoing project after 5 months and after 8 months are given below. All values and costs are in Rs lakhs. Comment on status of the a) Activities (Activity delayed/early, activity cost overrun/underrun) b) status of project and estimated total cost at completion at 5 months and at 8 months. After 5 months    Activity. EV PV AC Comment    A 10 10 8    B 18 15 12...
53. What are the three primary constraints in project management? -A Schedule, cost, and deadline -...
53. What are the three primary constraints in project management? -A Schedule, cost, and deadline - B Outsourcing, sponsors, and budget - C Time, scope, and resources - D Testing, accptance, and operation - -54. Which document outlines participation by various roles in a project? -A Communication plan B- PERT chart - C Responsibility matrix D Gantt chart 55. The relationship among the variables of the triple constraints is such that if any one variable changes, at least one other...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT