Question

In: Computer Science

53. What are the three primary constraints in project management? -A Schedule, cost, and deadline -...

53. What are the three primary constraints in project management?

-A Schedule, cost, and deadline -

B Outsourcing, sponsors, and budget -

C Time, scope, and resources -

D Testing, accptance, and operation -

-54. Which document outlines participation by various roles in a project?

-A Communication plan

B- PERT chart -

C Responsibility matrix

D Gantt chart

55. The relationship among the variables of the triple constraints is such that if any one variable changes, at least one other is likely to be affected. What is considered the sciense of making trade-offs between these variables?

- Project assumption

- Moore's law

- Risk management

- Project management --

56. What allows a project manager to close a project before it has been completed?

- Budget overrun

- Kill switch

- Stop date

- Project constraint

Solutions

Expert Solution

53. Three primary constraints in project management :

The three primary constraints in project management, also referred to as 'Project management triangle' or the 'Iron Triangle' consists of Time, Scope and Cost.

Time is simply the amount of time required to complete the project. It is also referred to as Schedule.

Scope is the extend or the dimension or the reach of the project.

Cost is the resources and other needs that are required to complete the project.

Answer : C) Time, Scope and Resources

54. Document outlining participation by various roles in a project

Where Gantt chart and PERT chart are used to describe about the flow of tasks and works in a project, Responsibility assignment matrix(RAM) outlines the participation by various roles, people in a project.

Answer: C) Responsibility Matrix

55. Triple constrain relationship

Triple constraints in project management must be balanced in a way they are achieved well. They are always fluctuating. The project must be managed in such a way.

Answer: Project Management

56. Closing a project before it has been completed

Kill switch is the trigger for a project manager to close a project before it is completed. Kill switch is defined before the starting of the project to choose parameters to when to stop the project.

Answer : Kill switch


Related Solutions

Identify three constraints imposed on an IT project schedule. Explain the impact that each of these...
Identify three constraints imposed on an IT project schedule. Explain the impact that each of these can have on project management.
Create a project schedule based on task dependencies and resource constraints
Create a project schedule based on task dependencies and resource constraints
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
First, review the "triple constraints" of IT Project Management as covered in this week's reading "What...
First, review the "triple constraints" of IT Project Management as covered in this week's reading "What is Project Management?" Note that there are more than 3 constraints discussed in the article. The illustration above from the article shows the author's interpretation of the "triple constraints." Group C: Please address the following 3 questions: Which of the triple constraints do you think is the most important for the project of implementing an enterprise hiring system for CIC? You should address from...
with the aid of a diagram, discuss the triple constraints of project management?
with the aid of a diagram, discuss the triple constraints of project management?
Consider the following project and prepare an activity schedule which satisfies the resources constraints. If the...
Consider the following project and prepare an activity schedule which satisfies the resources constraints. If the maximum labour available on any day is only 6, Find the EF for activity G Activity Duration No. of men req. per day A 1 to 2 4 6 B 1 to 3 2 3 C 1 to 4 8 4 D 2 to 6 6 3 E 3 to 5 4 2 F 5 to 6 1 1 G 4 to 6 1...
what are the typical constraints of a project with examples
what are the typical constraints of a project with examples
1-Explain project management and the role the triple constraints play when managing a project.
1-Explain project management and the role the triple constraints play when managing a project.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT