53. What are the three primary constraints in project management?
-A Schedule, cost, and deadline -
B Outsourcing, sponsors, and budget -
C Time, scope, and resources -
D Testing, accptance, and operation -
-54. Which document outlines participation by various roles in a project?
-A Communication plan
B- PERT chart -
C Responsibility matrix
D Gantt chart
55. The relationship among the variables of the triple constraints is such that if any one variable changes, at least one other is likely to be affected. What is considered the sciense of making trade-offs between these variables?
- Project assumption
- Moore's law
- Risk management
- Project management --
56. What allows a project manager to close a project before it has been completed?
- Budget overrun
- Kill switch
- Stop date
- Project constraint
53. Three primary constraints in project management :
The three primary constraints in project management, also referred to as 'Project management triangle' or the 'Iron Triangle' consists of Time, Scope and Cost.
Time is simply the amount of time required to complete the project. It is also referred to as Schedule.
Scope is the extend or the dimension or the reach of the project.
Cost is the resources and other needs that are required to complete the project.
Answer : C) Time, Scope and Resources
54. Document outlining participation by various roles in a project
Where Gantt chart and PERT chart are used to describe about the flow of tasks and works in a project, Responsibility assignment matrix(RAM) outlines the participation by various roles, people in a project.
Answer: C) Responsibility Matrix
55. Triple constrain relationship
Triple constraints in project management must be balanced in a way they are achieved well. They are always fluctuating. The project must be managed in such a way.
Answer: Project Management
56. Closing a project before it has been completed
Kill switch is the trigger for a project manager to close a project before it is completed. Kill switch is defined before the starting of the project to choose parameters to when to stop the project.
Answer : Kill switch