Question

In: Accounting

what is the cost performance index ? what is the Schedule at completion ?

what is the cost performance index ?

what is the Schedule at completion ?

and what is the Estimate at completion ?
123 Based on your project scenario which has been suggested by you or by your instructor and approved by your instructor, ans

Project Title: Date of Authorization Project Start Date Project Finish Date: Daycare Mobile Application May 3 March 1 May 2 f

B. Create the project baseline Gantt chart Task Nam Task Mode Duration Start Finish Predecessors, Baseline Dura <<<< - Daycar

( зма Question 3 Use Eamed Value Management for your Project to find out: a) Cost performance index (CPI) b) Schedule perform

Based on your project scenario which has been suggested by you or by your instructor and approved by your instructor, answer the following questions? Project Title : Daycare Mobile Application. Scenario Overview: Our project is a mobile application that called "Daycare" which helps parents and workers to do a lot of things such as: they can find children daycares easily, they can see all the daycares that locate around him/her, they can view pictures of the daycares, they can Contact with any daycare by mobile number, they can find the locations of the daycares, they can rate the daycare. Also, they can make an account, they can sign in as a quest, they can edit profile, they can add comments to any daycare, they can contact with Daycare via direct messages, they can add daycare to favorite list, and they can contact manager to add their Daycare to the application. Therefore, in this Application we will have two different parties: User, and Managers.

Solutions

Expert Solution

a.) CPI=EV/AC

  • CPI = Cost Performance Index
  • EV = Earned Value (dollars, euros, etc.)
  • AC = Actual Cost (dollars, euros, etc.)

The Cost Performance Index represents the relative amount that the task is over or under budget. As a ratio it is calculated by dividing the budgeted cost of work completed, or earned value, by the actual cost of the work performed.The cost performance index (CPI) is a measure of the financial effectiveness and efficiency of a project. It represents the amount of completed work for every unit of cost spent.

b.)

The Schedule Performance Index (SPI) is a measure of schedule efficiency, expressed as the ratio of earned value to planned value.The schedule performance index (SPI) is a measure of how close the project is to being completed compared to the schedule.As a ratio it is calculated by dividing the budgeted cost of work performed, or earned value, by the planned value.

Schedule Performance Index = (Earned Value) / (Planned Value)

SPI= EV / PV

c.)

Estimate at Completion is the total cost of the project at the end, while the Estimate to Complete is the cost required to complete the remaining work.The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

Estimate at Completion = (Budget at Completion) / (Cost Performance Index)

Or,

EAC = BAC / CPI


Related Solutions

Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Question - Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?  The answer is...
Prepare a Schedule of Cost of Goods Manufactured and a Schedule of Cost of Goods Sold...
Prepare a Schedule of Cost of Goods Manufactured and a Schedule of Cost of Goods Sold and Income Statement; this ie the jouranl entries Pre-determined manufacturing overhead rate = Total estimated manufacturing overheads / Estimated direct labor hours = = $3600/12 hours = $300 per direct labor hour Step 2: Cost Sheet Job # 1 Direct materials $ Table top 2000 Legs ($650 x 4) 2600 Drawer 0 4600 Direct labor cost @ $20 per hour (3x2x$30) 180 Manufacturing overheads...
When using Solar energy, explain the system engineering tradeoffs based on estimated performance, cost, schedule, or...
When using Solar energy, explain the system engineering tradeoffs based on estimated performance, cost, schedule, or other relevant factors and the decision process and analysis tools used in making the decision.
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Preparing a Schedule of Cost of Finished Goods Manufactured, Cost of Goods Sold Schedule, and an...
Preparing a Schedule of Cost of Finished Goods Manufactured, Cost of Goods Sold Schedule, and an Income Statement. Listed below is information related to RRR Co’s manufacturing activities for the month of October 2020. Ending Balance                       Beginning Balance Materials Inventory                                                                 $197,000                                    $ 211,000 Work in Process Inventory                                                       59,000                                         78,000                     Finished Goods Inventory                                                        91,000                                           82,000 During October 2020, RRR Company purchased $105,000 of raw materials and incurred direct labor costs of $77,100. The...
Preparing a Schedule of Cost of Finished Goods Manufactured, Cost of Goods Sold Schedule, and an...
Preparing a Schedule of Cost of Finished Goods Manufactured, Cost of Goods Sold Schedule, and an Income Statement. Listed below is information related to Danbury Co’s manufacturing activities for the month of July 2016. Ending Balance Beginning Balance Materials Inventory $7,500 $ 6,000 Goods in Process Inventory 11,000 2,000 Finished Goods Inventory 10,000 9,000 During July 2016, Danbury Company purchased $20,000 of raw materials and incurred direct labor costs of $14,160. The company applies overhead at a rate of 50%...
What is a fixed cost in a firm’s production schedule? Cost from an input that does...
What is a fixed cost in a firm’s production schedule? Cost from an input that does not change with quantity produced. Cost from an input that does not change with time. Cost from an input that does not change with its quality. Cost from an input that has no substitutes in the firm’s production. In a perfectly competitive market, firms are price takers because: There are many sellers, all offering the same product All the sellers have agreed to not...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT