Question

In: Operations Management

The PMBOK Guide (2013) defines Project Cost Management includes the processes involved in planning, estimating, budgeting,...

The PMBOK Guide (2013) defines Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget. What actions should you as a project manager take to control costs?

Solutions

Expert Solution

The following actions should be taken to control cost as a project manager:

1. Forecast on the future budget so that the needed fund can be allocated, which minimize on the risk of the project and control cost on spending extra amount.

2. The expenses needs to be updated and make sure that is properly utilized so that will not create on any problem towards extra fund and that control on the cost.

3. The project tasks and works needs to be planned properly, so that it helps to control on the costs as where the allocated budget can be utilized to complete the project work.

4. The details on the project needs to be taken and updates as where it helps to estimate on the resources cost which needs to be used for the project and with proper budget allocation the cost can be controlled according to that.

5. The early completion time needs to be estimated so that the cost of the project can be controlled with short period of completion on the projects.


Related Solutions

Using the Chapter 7 - User Guide to the PMBOK 4th edition - Project Cost Management...
Using the Chapter 7 - User Guide to the PMBOK 4th edition - Project Cost Management course material as a guide and the Earned Value (EV) formulas described in the example problem, answer the questions below by showing your calculations and solutions for each project parameter. Our 6-month project example is described as follows: Total Hours of Work:  1,100 Hours Cost per Hour:  $185 per hour Project cost at end of month three: $110,000 Estimated work complete at end of month three:...
According to the PMBOK® Guide, what are project baselines? The project’s baseline is used to measure...
According to the PMBOK® Guide, what are project baselines? The project’s baseline is used to measure how performance deviates from the plan and is defined as the original scope, cost and schedule. The project’s baseline must be completely defined and documented before the project execution and control activities can begin. Once the project’s baseline is put under change control to help you evaluate any further change and its impact on the project. No meaningful measurements can be made if the...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them. a) Which is PMBOK Knowledge area using a tool of Stakeholder Register? b) Which is PMBOK Knowledge area using a tool of Project Charter? c) Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d) Which are two PMBOK Knowledge...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
​​​​​​Discuss how to perform cost control based on the processes involved in cost management. In details...
​​​​​​Discuss how to perform cost control based on the processes involved in cost management. In details and what is the best ways possible.
Discuss which project management methodology is better, PMBOK or Agile
Discuss which project management methodology is better, PMBOK or Agile
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT