Question

In: Economics

Using the Chapter 7 - User Guide to the PMBOK 4th edition - Project Cost Management...

Using the Chapter 7 - User Guide to the PMBOK 4th edition - Project Cost Management course material as a guide and the Earned Value (EV) formulas described in the example problem, answer the questions below by showing your calculations and solutions for each project parameter. Our 6-month project example is described as follows:

Total Hours of Work:  1,100 Hours

Cost per Hour:  $185 per hour

Project cost at end of month three: $110,000

Estimated work complete at end of month three: 60%

Actual work complete at end month three: 50%

Month

Planned Complete %

Actual Complete %

Actual Cost ($)

Planned Value ($)

Earned Value ($)

CPI

1

20%

25%

$40,000

2

40%

40%

$70,000

3

60%

50%

$110,000

4

5

6

Complete the Table above (at Month 3) to answer the following questions:

1.   Calculate BAC - What will the total budgeted cost of the project be at completion?

2.   Calculate EV - How much earned work has actually been completed by the end of Month 3?

3.   Calculate CPI - How much of the actual cost incurred by the end of Month 3 was actually earned to this same point in time?

4.   Calculate EAC – Based on your review at 3 months, what will the total cost of the project be at completion?

5.   Calculate ETC - How much more money will it take to finish the project?

6.   Calculate VAR - How much over or under budget will the total project cost be?

7.   Calculate PV - How much work in dollars was expected to be finished at the end of Month 3?

8.   Calculate CV - How much more (or less) did the work completed at this point actually cost compared to what was originally planned?

9.   Calculate SV - How much more (or less) earned work, in dollars, has been accomplished at this point compared to what was originally planned?

10. Calculate SPI - How does the work completed (%) compare to that planned for the end of Month 3?

11. Calculate TCPI based on BAC- What level of performance must future project work meet in order to meet the original budget?

12. Calculate TCPI based on EAC - What level of performance must future project meet in order to meet the project’s revised budget based on this current performance review?

Solutions

Expert Solution

Month Planned completion Actual completion Actual cost (AC) Planned value (P V) Earned value (EV) CV SV (Earned value - Planned value) CPI (EV/AC) SPI (EV/PV)
(Earned value - Actual cost)
1 20% 24% 40000 22000 26400 -13600 4400 0.66 1.2
2 40% 40% 70000 44000 44000 -26000 0 0.63 1
3 60% 50% 110000 66000 55000 -55000 -11000 0.5 0.83

Project Total cost = 1,10,000

5.Planned value for each month is noted in Column "Planned value"

6.Earned value is noted in column "Earned VAlue"

7. CV is calculated in CV Column

8 - SV is calculated in SV column

9,10 = CPI and SPI calculated in column

2.


Related Solutions

guide to unix using linux / 4th edition / chapter 2 / p10 2.10 Assume that...
guide to unix using linux / 4th edition / chapter 2 / p10 2.10 Assume that you work for a company that is developing a telephone database and you are creating directories for the Mail and Receiving Departments, which are referenced in the company’s budget and accounting systems as departments 4540 and 4550. After you create the directories, you begin creating files of department phone numbers to store in those directories. You must use the mkdir (make directory) command to...
In An Introduciton to Programmig Using Visual Basic tenth edition chapter 6 the 4th project program...
In An Introduciton to Programmig Using Visual Basic tenth edition chapter 6 the 4th project program has me using loops. I am having a hard time trying to figure out what the double declining balance methods depreciation value is. It is 2 divided by the items life, but multiplied by the previous years balance. I do not know how to find the previous years balance to use in the depreciation value. Thank you
The PMBOK Guide (2013) defines Project Cost Management includes the processes involved in planning, estimating, budgeting,...
The PMBOK Guide (2013) defines Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget. What actions should you as a project manager take to control costs?
Guide to UNIX Using Linux (4th Edition) 1.What is sed? A Stream editor is used to...
Guide to UNIX Using Linux (4th Edition) 1.What is sed? A Stream editor is used to perform basic transformations on text read from a file or a pipe. The result is sent to standard output. The syntax for the sed command has no output file specification, but results can be saved to a file using output redirection. The editor does not modify the original input. What distinguishes sed from other editors, such as vi and ed, is its ability to...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and add pictures of the machine.) Project 2-6 In this hands-on project, you properly shut down your Linux system. 1. Press CtrlþAltþF2 to switch to a command-line terminal (tty2), and then log in to the terminal using the user name of root and the password of LNXrocks!. 2. At the command prompt, type poweroff to shut down your Linux system immediately. Which commands from Table...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and add pictures of the machine.) Project 2-3 In this hands-on project, you log in to a graphical terminal in Fedora Linux and interact with the GNOME and KDE desktops. 1. Switch to the graphical terminal (tty1) by pressing CtrlþAltþF1, click user1, supply the password of LNXrocks!, and click Sign In. Which desktop is started and why? 2. The first time you log into the...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and add pictures of the machine.) Project 2-5 In this hands-on project, you find information about commands using help utilities. 1. Press CtrlþAltþF2 to switch to a command-line terminal (tty2), and then log in to the terminal using the user name of root and the password of LNXrocks!. 2. At the command prompt, type man –k cron and press Enter to view a list of...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and add pictures of the machine.) Project 2-4 In this hands-on project, you use and protect shell metacharacters. 1. Switch to a command-line terminal (tty2) by pressing CtrlþAltþF2 and log in to the terminal using the user name of root and the password of LNXrocks!. 2. At the command prompt, type date;who and press Enter to run the date command immediately followed by the who...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and add pictures of the machine.) Project 2-2 In this hands-on project, you explore some command-line terminals on a Linux system and enter some basic commands into the BASH shell. 1. After your Linux system has been loaded, you are placed at a graphical terminal (tty1). Instead of logging in to this graphical terminal, press CtrlþAltþF2 to switch to a command-line terminal (tty2) and then...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and...
CompTIA Linux+ Guide to Linux Certification (4th Edition)(Please do not do it in a mac and add pictures of the machine.) Project 4-6 In this hands-on project, you delete files and directories using the rmdir and rm commands. 1. Switch to a command-line terminal (tty2) by pressing Ctrl+Alt+F2 and log in to the terminal using the user name of root and the password of LNXrocks!. 2. At the command prompt, type cd samples and press Enter. At the command prompt,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT