In: Economics
Using the Chapter 7 - User Guide to the PMBOK 4th edition - Project Cost Management course material as a guide and the Earned Value (EV) formulas described in the example problem, answer the questions below by showing your calculations and solutions for each project parameter. Our 6-month project example is described as follows:
Total Hours of Work: 1,100 Hours
Cost per Hour: $185 per hour
Project cost at end of month three: $110,000
Estimated work complete at end of month three: 60%
Actual work complete at end month three: 50%
Month |
Planned Complete % |
Actual Complete % |
Actual Cost ($) |
Planned Value ($) |
Earned Value ($) |
CPI |
1 |
20% |
25% |
$40,000 |
|||
2 |
40% |
40% |
$70,000 |
|||
3 |
60% |
50% |
$110,000 |
|||
4 |
||||||
5 |
||||||
6 |
||||||
Complete the Table above (at Month 3) to answer the following questions:
1. Calculate BAC -
What will the total budgeted cost of the project be at
completion?
2. Calculate EV - How
much earned work has actually been completed by the end of Month
3?
3. Calculate CPI -
How much of the actual cost incurred by the end of Month 3 was
actually earned to this same point in time?
4. Calculate EAC
– Based on your review at 3 months, what will the total cost of the
project be at completion?
5. Calculate ETC -
How much more money will it take to finish the project?
6. Calculate VAR
- How much over or under budget will the total project cost
be?
7. Calculate PV - How
much work in dollars was expected to be finished at the end of
Month 3?
8. Calculate CV
- How much more (or less) did the work completed at this point
actually cost compared to what was originally planned?
9. Calculate SV - How
much more (or less) earned work, in dollars, has been accomplished
at this point compared to what was originally planned?
10. Calculate SPI - How does the
work completed (%) compare to that planned for the end of Month
3?
11. Calculate TCPI based on
BAC- What level of performance must future project work meet
in order to meet the original budget?
12. Calculate TCPI based on
EAC - What level of performance must future project meet in
order to meet the project’s revised budget based on this current
performance review?
Month | Planned completion | Actual completion | Actual cost (AC) | Planned value (P V) | Earned value (EV) | CV | SV (Earned value - Planned value) | CPI (EV/AC) | SPI (EV/PV) |
(Earned value - Actual cost) | |||||||||
1 | 20% | 24% | 40000 | 22000 | 26400 | -13600 | 4400 | 0.66 | 1.2 |
2 | 40% | 40% | 70000 | 44000 | 44000 | -26000 | 0 | 0.63 | 1 |
3 | 60% | 50% | 110000 | 66000 | 55000 | -55000 | -11000 | 0.5 | 0.83 |
Project Total cost = 1,10,000
5.Planned value for each month is noted in Column "Planned value"
6.Earned value is noted in column "Earned VAlue"
7. CV is calculated in CV Column
8 - SV is calculated in SV column
9,10 = CPI and SPI calculated in column
2.