In: Computer Science
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.
a) Which is PMBOK Knowledge area using a tool of Stakeholder Register?
b) Which is PMBOK Knowledge area using a tool of Project Charter?
c) Which are two PMBOK Knowledge areas that use the tool of Resource Levelling?
d) Which are two PMBOK Knowledge areas that use the tool of WBS?
e) Which is PMBOK Knowledge area using the tool of risk register?