Question

In: Computer Science

The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...

The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.  

a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register?

b)   Which is PMBOK Knowledge area using a tool of Project Charter?

c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling?

d)      Which are two PMBOK Knowledge areas that use the tool of WBS?

e)      Which is PMBOK Knowledge area using the tool of risk register?

Answer a) through e) in one text box below:

Solutions

Expert Solution

There are 10 PMBOK knowledge areas that cover 47 process related to the 5 described phases of a process life cycle. The tools associated with the following one are:

(a) Project Stakeholder management is using a tool of Stakeholder register. It has the objective to raise the necessity of stakeholder engagement management. It works in 4 stages:

  • Identify Stakeholder.
  • Plan Stakeholder management.
  • Manage Stakeholder management.
  • Control Stakeholder management.

(b) Project Integration Management area of PMBOK using a tool of project charter. Under this knowledge area, processes such as

  • Develop Project Charter
  • Develop project management plan
  • Direct and manage project work

are done.

(c) Project Resource Management and Project Cost Management uses the tool of resource levelling. It talks about :

  • Planning HR management
  • Acquire project team
  • Develop project team
  • Manage project team

whereas Project cost management involves managing the costs of the project. It includes the following points:

  • Plan Cost Management
  • Estimate Costs
  • Determine Budget
  • Control Costs

(d) Project Scope management and Project Schedule Management are the two tools using WBS(Work Breakdown Structure). Both of them involve the idea of defining activities and creating WBS to work towards a goal.

The steps of Project Scope Management involves:

  • Define Scope
  • Creating WBS
  • Validate Scope
  • Control Scope

whereas, the Project Schedule management involves the following steps:

  • Define activities
  • Sequence activities
  • Estimate activity duration
  • Develop schedule
  • Control schedule

(e) PMBOK knowledge are using the tool of Risk register is Project Risk Management. It is used to identify and analyze the risk and develop reliable responses to deal with it. The steps involved in risk management are as follows:

  • Plan Risk Management
  • Identify Risk
  • Perform Qualitative risk Analysis
  • Perform Quantitative risk Analysis
  • Plan responses
  • Implement risk responses
  • Monitor risks

Related Solutions

The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them. a) Which is PMBOK Knowledge area using a tool of Stakeholder Register? b) Which is PMBOK Knowledge area using a tool of Project Charter? c) Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d) Which are two PMBOK Knowledge...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
Describe what happens in each of the five project management process groups (initiating, planning, executing, monitoring and controlling, and closing).
Technology in Enterprise MngmtDescribe what happens in each of the five project management process groups (initiating, planning, executing, monitoring and controlling, and closing). What typesof activities occur before initiating a project? (Do not be brief, explain each process group fully)
Identify the five project management process groups, and briefly describe what happens in each. What types of activities occur before initiating a project?
Identify the five project management process groups, and briefly describe what happens in each. What types of activities occur before initiating a project? What are some of the typical challenges project teams face during each of the five process groups?
Project management process involves many phases. Construction is one of the phases. Which of the following...
Project management process involves many phases. Construction is one of the phases. Which of the following aspects of the construction phase do you consider as most important as well as most challenging/demanding? Why do you think so? Third party coordination Quality Management Safety management? Please select only one option and justify your response.
Discuss the five process groups of project management as followed throughout the case project. The goal...
Discuss the five process groups of project management as followed throughout the case project. The goal of this essay is to demonstrate your understanding of the covered systems analysis and design course topics and highlight your overall learning experience. For each phase demonstrate your understanding by incorporating the ten knowledge areas with the case assignments into your analysis. Indicate any areas of successes, challenges, failures you experienced. Be specific. Your essay should highlight the importance of each process group and...
Projects have very distinct process phases that they go through according to PMI: initiating, planning, performing...
Projects have very distinct process phases that they go through according to PMI: initiating, planning, performing (monitoring and control) and closing. Describe what you think the Project Manager's role is in each of the process phases in each of the four process group steps a project is going through. Then rank the relative degree of difficulty and challenge each step in the process presents to the project manager beginning with the most challenging and difficult. Give a reasoning for each...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT