In: Computer Science
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.
a) Which is PMBOK Knowledge area using a tool of Stakeholder Register?
b) Which is PMBOK Knowledge area using a tool of Project Charter?
c) Which are two PMBOK Knowledge areas that use the tool of Resource Levelling?
d) Which are two PMBOK Knowledge areas that use the tool of WBS?
e) Which is PMBOK Knowledge area using the tool of risk register?
Answer a) through e) in one text box below:
There are 10 PMBOK knowledge areas that cover 47 process related to the 5 described phases of a process life cycle. The tools associated with the following one are:
(a) Project Stakeholder management is using a tool of Stakeholder register. It has the objective to raise the necessity of stakeholder engagement management. It works in 4 stages:
(b) Project Integration Management area of PMBOK using a tool of project charter. Under this knowledge area, processes such as
are done.
(c) Project Resource Management and Project Cost Management uses the tool of resource levelling. It talks about :
whereas Project cost management involves managing the costs of the project. It includes the following points:
(d) Project Scope management and Project Schedule Management are the two tools using WBS(Work Breakdown Structure). Both of them involve the idea of defining activities and creating WBS to work towards a goal.
The steps of Project Scope Management involves:
whereas, the Project Schedule management involves the following steps:
(e) PMBOK knowledge are using the tool of Risk register is Project Risk Management. It is used to identify and analyze the risk and develop reliable responses to deal with it. The steps involved in risk management are as follows: