Question

In: Finance

Etisalat is in the process of choosing the better of two equal-risk, independed capital expenditure projects-A...

Etisalat is in the process of choosing the better of two equal-risk, independed capital expenditure projects-A and B. The relevant cash flows for each project are shown in the following table. The firm's cost of capital is 14%.
   
Project A
Project B
Initial investment
$27000
$25,000
1
$10,000
$11,000
2
$10,000
$10,000
3
$10,000
$9,000
4
$10,000
$8,000
Required:
a. Calculate each project's payback period. what are the disadvantages of the payback period?

b. Calculate the net present value (NPV) for each project.
c. Calculate Profitability Index (PI) for each project.
d. If you are given the internal rate of return (IRR) for project A is 18% and IRR for Project B is 20 %, which one you select and why?
e. Summarize the preferences dictated by each measure (Payback period, NPV, PI, IRR), and indicate which project you would recommend. Explain why?

Solutions

Expert Solution

Year Project A Project B Discount factor @ 14% NPV of A NPV of B
0 -27000 -25000 1        (27,000)        (25,000)
1 10000 11000 0.877192982            8,772            9,649
2 10000 10000 0.769467528            7,695            7,695
3 10000 9000 0.674971516            6,750            6,075
4 10000 8000 0.592080277            5,921            4,737
13000 13000            2,137            3,155
a Payback period A B
2.84 2.53
When NPV is zero - All cash investments are earned back
A (7k in year 3 earned in 0.84 years as 1 year earns 10k 7000/10000*12 months)
B (4k in year 3 earned in 0.53 years as 1 year earns 9k 4000/9000*12 months)
Discount factor 1/1+r^t
b NPV is discouned cash flows. A B
2137 3155
c Profitability index PV of cash inflow/PV of cash outflows
A B
Cash inflows     29,137     28,155
Cash outflows     27,000     25,000
         1.08          1.13
d IRR is the rate where NPV is 0. It is the rate of return earned by the project. The greater the IRR, better is the profiatbility of the project
So choose Project B has IRR of 20% compared to 18% from A
A B Which project to choose Reason
e Payback period 2.84 2.53 B Cash earned back quicker
NPV 2137 3155 B More cash flows at discounted terms
Profitability index          1.08          1.13 B Better profitablility
IRR 18% 20% B Better rate of return

Related Solutions

Hangers Corp. is in the process of choosing the better of two equal-risk, mutually exclusive capital...
Hangers Corp. is in the process of choosing the better of two equal-risk, mutually exclusive capital expenditure projects—X and Y. The relevant cash flows for each project are shown in the following table. The firm’s weighted average cost of capital is 11%. Year Expected Net Cash Flows project X project Y 0 -$625,000 -$600,000 1 156,250 250,000 2 156,250 100,000 3 156,250 200,000 4 156,250 100,000 a) Calculate the Payback Period for both the projects. b) Calculate the NPV and...
What is forecasting risk and why is it important to the analysis of capital expenditure projects?...
What is forecasting risk and why is it important to the analysis of capital expenditure projects? Explain how can the firm get the net present value technique to live up to its potential and before actual funding, how one can check out the project’s underlying assumptions about revenues and costs?
Better Health, Inc. is evaluating two investment projects, each of which requires an up-front expenditure of...
Better Health, Inc. is evaluating two investment projects, each of which requires an up-front expenditure of $2.5 million. The projects are expected to produce the following net cash inflows: Year Project A Project B 0 -$2,500,000 -$2,500,000 1 $500,000 $1,200,000 2 $1,100,000 $1,300,000 3 $1,400,000 $800,000 a. What is each project's IRR? b. What is each project's NPV if the cost of capital is 10 percent? c. Which one would you buy? Please include the input used in a financial...
Better Health, Inc. is evaluating two investment projects, each of which requires an up-front expenditure of...
Better Health, Inc. is evaluating two investment projects, each of which requires an up-front expenditure of $2.5 million. The projects are expected to produce the following net cash inflows: Year Project A Project B 1 750,000 2,000,000 2 1,250,000 1,250,000 3 2,000,000 750,000 a. What is each project's IRR? Project A = IRR(C11: b. What is each project's NPV if the cost of capital is 10%? Attention Chegg Tutor: There is a similar answer online in Chegg, but the excel...
Home Ltd. has the option of investing in the following two projects of equal risk; they...
Home Ltd. has the option of investing in the following two projects of equal risk; they are mutually exclusive alternatives for expanding the firm’s capacity. The firm’s cost of capital is 12%. The cash flows for each project are given in the following table. PROJECT A PROJECT B Initial investment 545,000 300,000 Year Net cash inflows Net cash inflows 1 135,000 200,000 2 185,000 120,000 3 220,000 92,000 4 280,000 Home Ltd. has incurred a research and development expenditure of...
Home Ltd. has the option of investing in the following two projects of equal risk; they...
Home Ltd. has the option of investing in the following two projects of equal risk; they are mutually exclusive alternatives for expanding the firm’s capacity.  The firm’s cost of capital is 12%.  The cash flows for each project are given in the following table. PROJECT A PROJECT B Initial investment 545,000 300,000 Year Net cash inflows Net cash inflows 1 135,000 200,000 2 185,000 120,000 3 220,000 92,000 4 280,000 Home Ltd. has incurred a research and development expenditure of $35,000 initially...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$52 $27 $19 $22 $17 B −$100 $22 $41 $48 $61 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.4%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$52 $27 $19 $18 $17 B −$101 $19 $40 $51 $58 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.4%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A -$ 49 $ 24 $ 19 $ 20 $ 13 B -$ 100 $ 18 $ 39 $ 48 $ 59 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.5 % what are the NPVs of the two​ projects? c. Why...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A -$48 $27 $ 21 $ 19 $ 12 B −$98 $20 $ 41 $ 51 $ 59 a. What are the IRRs of the two​ projects? (Round to one decimal​ place.) b. If your discount rate is 4.7%​ what are the NPVs of the two​ projects? c. Why...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT