In: Finance
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million):
Project |
Year 0 |
Year 1 |
Year 2 |
Year 3 |
Year 4 |
A |
−$52 |
$27 |
$19 |
$18 |
$17 |
B |
−$101 |
$19 |
$40 |
$51 |
$58 |
a. What are the IRRs of the two projects?
b. If your discount rate is 5.4%, what are the NPVs of the two projects?
c. Why do IRR and NPV rank the two projects differently?
a. What are the IRRs of the two projects?
(Round to one decimal place.)
a) Calculation of IRR
IRR for the project is calculated as follows,
IRR=L+((NPVL/(NPVL-NPVH)*(H-L))
Where,
L means Lower discount rate taken
H means Higher discount rate taken
NPVLmeans NPV at Lower discount rate taken
NPVH means NPV at Higher discount rate taken
PROJECT A | |||||
Year | Cash Flow | Discounting Factor @ 10% | Present Value @10% | Discounting Factor @20% | Present Value @ 20% |
0 | -52 | 1.00 | -52.00 | 1.00 | -52.00 |
1 | 27 | 0.91 | 24.55 | 0.83 | 22.50 |
2 | 19 | 0.83 | 15.70 | 0.69 | 13.19 |
3 | 18 | 0.75 | 13.52 | 0.58 | 10.42 |
4 | 17 | 0.68 | 11.61 | 0.48 | 8.20 |
NPV | 13.38 | NPV | 2.31 |
IRR=L+((NPVL/(NPVL-NPVH)*(H-L))
IRR = 10 + ((13.38/(13.38-2.31)) x (20-10))
IRR =10 + ((13.38/11.07) x 10)
IRR =10+12.087
IRR of Project A = 22.08%
PROJECT B | |||||
Year | Cash Flow | Discounting Factor @ 10% | Present Value @10% | Discounting Factor @20% | Present Value @ 20% |
0 | -101 | 1.00 | -101.00 | 1.00 | -101.00 |
1 | 19 | 0.91 | 17.27 | 0.83 | 15.83 |
2 | 40 | 0.83 | 33.06 | 0.69 | 27.78 |
3 | 51 | 0.75 | 38.32 | 0.58 | 29.51 |
4 | 58 | 0.68 | 39.61 | 0.48 | 27.97 |
NPV | 27.26 | NPV | 0.10 |
IRR=L+((NPVL/(NPVL-NPVH)*(H-L))
IRR = 10 + ((27.26/(27.26-0.1)) x (20-10))
IRR =10 +10.0368
IRR =20.04%
IRR of Project B = 20.04%
b)
NPV of PROJECT A | |||
Year | Cash Flow | Discounting Factor @ 5.4 | Present Value |
0 | -52 | 1.00 | -52.00 |
1 | 27 | 0.95 | 25.62 |
2 | 19 | 0.90 | 17.10 |
3 | 18 | 0.85 | 15.37 |
4 | 17 | 0.81 | 13.77 |
NPV | 19.87 |
NPV of PROJECT B | |||
Year | Cash Flow | Discounting Factor @ 5.4 | Present Value |
0 | -101 | 1.00 | -101.00 |
1 | 19 | 0.95 | 18.03 |
2 | 40 | 0.90 | 36.01 |
3 | 51 | 0.85 | 43.56 |
4 | 58 | 0.81 | 47.00 |
NPV | 43.59 |
c) As per IRR rule of project selection a project with higher IRR rate of return over the required rate of return is selected over lower IRR projects so in this case Project A is selected
Were as on the other hand as per NPV rule a project with possitive NPV is slecected .for comparing between 2 projects , project with higher NPV is selcted over Lower NPV projects. so in this case Project B will be prefered.
So, its clear that IRR and NPV rank the two projects differently in this case, this is becuase both NPV and IRR measures different things. IRR computes the return rate , were as NPV calculates the value added by choosing the project,returns donot increaases with diffrent initial investments , both NPV and IRR rate projects diffrents for diffrent initial investment projects.