In: Finance
Hangers Corp. is in the process of choosing the better of two
equal-risk, mutually exclusive
capital expenditure projects—X and Y. The relevant cash flows for
each project are shown in the
following table. The firm’s weighted average cost of capital is
11%.
Year Expected Net Cash Flows
project X project Y
0 -$625,000 -$600,000
1 156,250 250,000
2 156,250 100,000
3 156,250 200,000
4 156,250 100,000
a) Calculate the Payback Period for both the projects.
b) Calculate the NPV and the Profitability Index for each of the
projects. Please explain which
project should be selected and why?
Pay Back Period = Last year with negative cumulative cash flow + (Absolute value of cumulative cash flow in the last year in which Cumulative CF is negative / Cash Flow during the year in which cumulative F turns positive)
Profitability Index = Sum of PV of all cash flows / Initial Investment
NPV = Sum of Present value of all years - Initial Investment
Present Value = CF/ (1+k)^t or CF x Discount Factor
where, K = Cost of Capital & t is the time period
Discount Factor = 1/ (1+k)^t
a) Pay Back Period
For Project X, Cumulative cash flow turn positive (or zero) at the end of year 4.
i) Pay Back period for X project = 4 years
ii) Pay Back period for project Y = 3 = 50000/ 100000 = 3.5 years
The following table shows the cumulative cash flows of X & Y project
Year |
Project X cash Flows |
Project X Cumulative Cash Flows |
Project Y cash Flows |
Project Y Cumulative Cash Flows |
0 |
(625,000) |
(625,000) |
(600,000) |
(600,000) |
1 |
156,250 |
(468,750) |
250,000 |
(350,000) |
2 |
156,250 |
(312,500) |
100,000 |
(250,000) |
3 |
156,250 |
(156,250) |
200,000 |
(50,000) |
4 |
156,250 |
- |
100,000 |
50,000 |
b) For calculating NPV & PI,
NPV for project X
= 156250/(1+11%)^1 + 156250 x 1/(1+11%)^2 + 156250/ (1+11%)^3 + 156250/(1+11%)^4 - 625000
= 156250 x 0.901 + 156250 x 0.812 + 156250 x 0.731 + 156250 x 0.659 - 625000
= 140766 + 126816 + 114249 + 102927 - 625000
= 484,757 - 625000
= - $140243
NPV for Project Y
= 250000/(1+11%)^1 + 100000 x 1/(1+11%)^2 + 200000/ (1+11%)^3 + 100000/(1+11%)^4 - 600000
= 250000 x 0.901 + 100000 x 0.812 + 200000 x 0.731 + 100000 x 0.659 - 600000
= 225225 + 81162 + 146238 + 65873 - 600000
= 518499 - 600000
= - $81501
Profitability Index for X
= PV of all cash inflows / Investment
= 484757 / 625000
= 0.776
Profitability Index for Y
= 518499 / 600000
= 0.864
Since none of the projects have NPV > 0, it would be wise not to go for any of the project.
However , if one were to chose on the basis og PBP, project Y with lesser PBP is better.
Table for calculating NPV & PI
Year |
Project X cash Flows (CFx) |
Project Y cash Flows (CFy) |
Discount Factor (D) |
Discounted Cash flows of Project X |
Discounted Cash flows of Project Y D x CFy |
0 |
-625000 |
-600000 |
1.000 |
-625000 |
-600000 |
1 |
156250 |
250000 |
0.901 |
140766 |
225225 |
2 |
156250 |
100000 |
0.812 |
126816 |
81162 |
3 |
156250 |
200000 |
0.731 |
114249 |
146238 |
4 |
156250 |
100000 |
0.659 |
102927 |
65873 |
Total |
-140243 |
-81501 |