In: Finance
  | 
||||||||
| 
 Year  | 
 Project A  | 
 Project B  | 
||||||
| 
 0  | 
 -$2,500,000  | 
 -$2,500,000  | 
||||||
| 
 1  | 
 $500,000  | 
 $1,200,000  | 
||||||
| 
 2  | 
 $1,100,000  | 
 $1,300,000  | 
||||||
| 
 3  | 
 $1,400,000  | 
 $800,000  | 
||||||
| 
 a. What is each project's IRR?  | 
||||||||
| 
 b. What is each project's NPV if the cost of capital is 10 percent? c. Which one would you buy?  | 
||||||||
Please include the input used in a financial calculator if it is needed.
a) IRR is the rate at which NPV = 0
IRR can be calculated using either a financial calculator or excel
or through hit and trial:
Project A:
Calculator inputs are CF0 = -2500000, CF1 = 500000, CF2 = 1100000, CF3 = 1400000
Using Excel we get the IRR = 8.33% rounded to two decimal places:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $ -25,00,000.00 | 1/(1+0.0833245898465279)^0= | 1 | 1*-2500000= | $ -25,00,000.00 | 
| 1 | $ 5,00,000.00 | 1/(1+0.0833245898465279)^1= | 0.923084373 | 0.92308437320865*500000= | $ 4,61,542.19 | 
| 2 | $ 11,00,000.00 | 1/(1+0.0833245898465279)^2= | 0.85208476 | 0.852084760062006*1100000= | $ 9,37,293.24 | 
| 3 | $ 14,00,000.00 | 1/(1+0.0833245898465279)^3= | 0.786546127 | 0.78654612666248*1400000= | $ 11,01,164.58 | 
| NPV = Sum of all Discounted CF | $ 0.00 | 
Project B:
Calculator inputs are CF0 = -2500000, CF1 = 1200000, CF2 = 1300000, CF3 = 800000
Using Excel we get the IRR = 16.34% rounded to two decimal places:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $ -25,00,000.00 | 1/(1+0.1633943888366)^0= | 1 | 1*-2500000= | -25,00,000.00 | 
| 1 | $ 12,00,000.00 | 1/(1+0.1633943888366)^1= | 0.859553742 | 0.859553741702334*1200000= | 10,31,464.49 | 
| 2 | $ 13,00,000.00 | 1/(1+0.1633943888366)^2= | 0.738832635 | 0.738832634874483*1300000= | 9,60,482.43 | 
| 3 | $ 8,00,000.00 | 1/(1+0.1633943888366)^3= | 0.635066356 | 0.635066355798156*800000= | 5,08,053.08 | 
| NPV = Sum of all Discounted CF | $ 0.00 | 
b) NPV is calculated as follows:
Project A:
Calculator inputs are CF0 = -2500000, CF1 = 500000, CF2 = 1100000, CF3 = 1400000
Using Excel we get the I = 10% rounded to two decimal places:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $ -25,00,000.00 | 1/(1+0.1)^0= | 1 | 1*-2500000= | $ -25,00,000.00 | 
| 1 | $ 5,00,000.00 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*500000= | $ 4,54,545.45 | 
| 2 | $ 11,00,000.00 | 1/(1+0.1)^2= | 0.826446281 | 0.826446280991735*1100000= | $ 9,09,090.91 | 
| 3 | $ 14,00,000.00 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*1400000= | $ 10,51,840.72 | 
| NPV = Sum of all Discounted CF | $ -84,522.92 | 
Project B:
Calculator inputs are CF0 = -2500000, CF1 = 1200000, CF2 = 1300000, CF3 = 800000
Using Excel we get the I = 10% rounded to two decimal places:
| Year | CF | Discount Factor | Discounted CF | ||
| 0 | $ -25,00,000.00 | 1/(1+0.1)^0= | 1 | 1*-2500000= | $ -25,00,000.00 | 
| 1 | $ 12,00,000.00 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*1200000= | $ 10,90,909.09 | 
| 2 | $ 13,00,000.00 | 1/(1+0.1)^2= | 0.826446281 | 0.826446280991735*1300000= | $ 10,74,380.17 | 
| 3 | $ 8,00,000.00 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*800000= | $ 6,01,051.84 | 
| NPV = Sum of all Discounted CF | $ 2,66,341.10 | 
c) Project B should be selected as it has a higher NPV and even using the IRR rule, project B is correct as it has a higher IRR.