Draw the PERT and Gantt (calendar) charts for the following list of activities and expected durations. Identify the critical path and list the slack times (if any) for the activities. Activity Immediate Predecessor Duration A - 3 B - 3 C - 4 D A, B 5 E B, C 4 F D, E 2 G E 3 H F, G 5