Question

In: Mechanical Engineering

Your company has been awarded a contract for 5-story addition on top of an existing 10-story...

Your company has been awarded a contract for 5-story addition on top of an existing 10-story hospital tower at a Cancer Center located in one of the most populated areas of Dallas, Texas. The existing hospital building is beyond 100% occupancy. The company was hired under a design-build contract to complete the $220 million project. Wind-load testing will be conducted. The wind-resisting system will be modified to redistribute loads on the mat foundation. High-strength concrete will be utilized for the addition's floors and columns (to reduce the load). The new mechanical level will be relocated from an upper floor to the floor just above the hospital's existing roof level. Glass fiber reinforced concrete cladding matching the original building's precast concrete façade (but at about one-quarter the weight) is specified in the design. The duration of the project is three-year.

Can you guys help me find the mechanical and electrical system hazards in this problem?!

And what would be the control strategies for them.

Solutions

Expert Solution

LESSONS FROM THE BUILDING TEAM

1. Get the heck out of the way.“Plan out exactly when and where you're going to be performing work and make sure the hospital knows all those details,” says SSOE's Seibenaller. The team planned the four-phase program with precision so as to minimize disruptions to hospital functions. “It's like a game of checkers,” adds Eric Murrell, CCS, CSA, senior associate with SSOE Group. The strategy has the Building Team in and out of the hospital, and staff always knows their next 10 moves.

2. Assume there will be emergencies and plan for them.“Establish protocols and points of contact upfront so hospital staff know whom they can call,” says Murrell. “With everything working as it should, stoppage should be within minutes.” On this project, demolition and construction work near the hospital's MRI interfered with its use, so the team had to interrupt its work a few times as a result of emergencies.

3. Be prepared for the unknown inside the building. As is often the case in older buildings, the Building Team is finding that the existing hospital's mechanicals and utilities simply are not located where they're supposed to be. “We're playing cat and mouse with the utilities,” says Murrell. Pipes and wires were reworked during previous additions and renovations. “Not everything is the way we expected it to be, but that's to be expected,” he says.

4. Use BIM, but don't assume it's a cure-all. “Revit was critical to the success of this project and allowed us to compress the schedule,” says Siebenaller. But BIM is not a panacea. Siebenaller says Revit's MEP tools were not up to the level of its architectural tools at the time. Moreover, he acknowledges that not enough people on the team were trained in the MEP tools. The Building Team restricted the use of BIM to the additions, not to any work on the existing hospital, whose construction predated BIM.

UNIVERSITY OF TEXAS M.D. ANDERSON CANCER CENTER, HOUSTON

The M.D. Anderson Cancer Center is one of the nation's highest-rated hospitals for cancer care, which is the main reason why this world-class facility was in desperate need of more patient beds. “We're beyond 100% occupancy,” says Susan Lipka, the hospital's associate VP for capital planning and management services.

Fortunately, the existing 12-story Alkek Hospital Tower, completed in 1998, had been designed by Dallas A/E firm HKS to accommodate a 10-story vertical expansion. In 2007 the hospital opted to put a massive 500,000-sf addition atop the tower, thereby adding 208 new patient rooms (each 40 sf larger than those in the existing hospital) and providing shell space for another 200 or so patient rooms.

A Building Team consisting of HKS, structural engineer Walter P Moore, and contractor McCarthy Building Companies was hired under a design-build contract to complete the $220 million project. There was just one hitch. The hospital decided that if a 10-story addition was good, a 12-story one would be even better. That meant adding two extra floors, at 45,000 sf each, while the existing facility was not only occupied, but operating at more than 100% capacity.

The plans were turned into a BIM model, starting in AutoCAD and finishing in Revit. Extensive wind-load testing was conducted at CPP Wind in Fort Collins, Colo. Walter P Moore modified the wind-resisting system to redistribute loads on the mat foundation, eliminated shear walls from the upper floors to reinforce existing shear walls, utilized high-strength concrete for the addition's floors and columns (to reduce the load), and relocated the new mechanical level from an upper floor to the floor just above the hospital's existing roof level. Glass fiber reinforced concrete cladding matching the original building's precast concrete façade (but at about one-quarter the weight) was specified. The three-year project is expected to open this June.

LESSONS FROM THE BUILDING TEAM

5. Know how much noise you're going to make well before you make it. “We didn't want to start the process and find out there's too much noise, vibration, and interference, so we conducted a pre-investigation before we even decided to go ahead with any of the work,” says Lipka. Jackhammer tests showed that noise penetrated down as far as the ninth floor, and vibrations went down even farther. Lipka says the hospital officials were shocked. “We assumed that closing the top floor (the 12th) would be required but we didn't anticipate that noise levels on the 11th and 10th floors would be just as loud.”

To avoid closing three floors during construction, Lipka and her team put strict requirements into the RFQ: drilling, jackhammering, and other intrusive work would be limited to 15-minute increments in any one area to minimize patient and staff disruption. The lesson, says Lipka, is that it's better to know what to expect than be in for a nasty surprise.

6. Communicate, communicate, communicate. It may sound trite, but letting the hospital staff, patients, and patients' families know what's going on in the project is crucial, says Lipka. The nursing staff was involved in the logistics plan and were alerted—pretty much on a daily basis—as to what work to expect. The hospital reworked wayfinding. They printed weekly news bulletins and placed them on patients' food trays. “We spelled everything out,” says Lipka. “Because nurses and patients were kept in the loop to such a significant degree, their tolerance levels were higher.”

7. Negotiate for any parking spaces and staging areas you can get. Because the existing tower was surrounded on all sides by buildings and a busy road, staging on site was impossible. That meant the team had to use just-in-time delivery of materials. (Subcontractors stored their materials at their own facilities.) Nor was there parking near the site. McCarthy's jobsite office was a half mile from the site. Soon after the project started, however, McCarthy was able to find parking for subcontractors in a garage not far from the site; as a result, they were able to negotiate lower bids from subcontractors.

8. Minimize exposure to harmful elements. “Something I've never encountered before was working on the roof with 25 fans releasing harmful, or possibly harmful, exhaust because they were connected to fume hoods inside the hospital,” says Ben Johanneman, project director for McCarthy. Since the fans had to be removed to accommodate the 12-story addition, the Building Team installed temporary fans with vertical ductwork; they kept adding on to this ductwork as work progressed, so that the exhaust was always expelled at least 20 feet above where any crews were working.

UNIVERSITY OF VIRGINIA MEDICAL CENTER, CHARLOTTESVILLE, VA.

The University of Virginia Medical Center is adding 50,000 sf and 72 universal patient beds to its 500-bed, 20-year-old hospital. Another 50,000 sf of space will be renovated during the $54 million project. The overall $150 million expansion of the medical center campus also includes construction of a new cancer center and a parking garage. The Building Team consists of a Mid-Atlantic-based group from Gilbane Building (CM, not at risk) and a design team from SmithGroup's Washington, D.C., office.

To say the site was tight would be an understatement; there was no available land adjacent to the hospital on which an addition could be built, so the team devised a skinny, eight-story, 34-foot-deep addition that's being more or less “laminated” onto the front elevation of the hospital, over the existing lobby and main entrance, with a two-foot-eight-inch gap between the new construction and the old exterior wall. This will remain intact until the addition is closed up and the gap built out. Once that façade comes off, the area where old hospital meets new (mostly corridors and staff support spaces) is slated for renovation.

Construction started in October 2008 and is expected to wrap up in August 2011.

LESSONS FROM THE BUILDING TEAM

9. Understand that no phasing plan is perfect. “Our vision was to build the new structure first and then when we got to the top, capture the renovation piece and work our way down, completing two floors at a time,” says Michael Holdren, project executive at Gilbane. “It hasn't worked out that way.” That's because the hospital hasn't been able to vacate the floors for the Building Team—a pitfall of working on an occupied hospital—so the team has had to rework its plan and avoid occupied spaces. “We accomplish what we can where we can,” says Holdren.

10. Expect your work to bother someone, and adjust accordingly. “When we were working on the seventh floor, it wasn't unexpected to have an impact on sensitive medical equipment on the third floor,” says Holdren. “We just had to adjust our schedule and sometimes work an hour, stop for an hour, and then start up again for an hour.”

11. Minimize inconveniences.With the new addition being built above the lobby, the Building Team wanted to close the main entrance, an impossible request with as many as 2,000 people a day using that entry. A compromise was reached whereby the lobby was closed from 9 p.m. to 5 a.m., and all steel erection had to be done during these hours. (Fortunately, most patient rooms are located at the rear of the hospital, away from the construction.) To minimize inconvenience for nighttime visitors or patients, Gilbane trained its crew to direct people around the closure. In fact, Holdren says the hospital stated that patient satisfaction scores actually increased during construction, a fact he attributes at least in part to beefed-up wayfinding.

BAPTIST MEDICAL CENTER SOUTH, JACKSONVILLE, FLA.

When Baptist Medical Center opened in 2005, it was a state-of-the-art, 92-bed, 257,000-sf hospital that served southern Duval and northern St. Johns Counties. A scant five years later the hospital is a nine-story, 479,000-sf, 159-bed facility as the result of a $70.7 million expansion designed by Gresham, Smith and Partners.

“Almost from the time the [existing] hospital opened, it was filled,” says Rick McManus, director of construction at the Haskell Commercial Group and the senior project manager on this project. The campus had been master planned for future expansion, but the expansion came much sooner than anticipated. “They thought this tower would be built as part of a 10-year-plan, but it turned out to be a three-year plan,” says McManus.

The patient tower addition started in spring 2007 and the first parts of the tower were occupied in February 2009, in time to help the hospital mop up the flu season.

LESSONS FROM THE BUILDING TEAM

12. Make infection control training a top priority. With ICRA (infection control risk assessment) requirements a part of the package, Building Teams are faced with difficult standards that aren't part of a typical construction project. “There's lots of liability because any and all work you do can affect patients,” says Paul Tyler, president of Haskell Commercial Group. Working on an occupied healthcare facility requires more than just erecting and maintaining sanitary enclosures between the existing space and the new work. Everyone on the job has to understand what infection control means. “Everyone on our construction staff who went into the existing hospital had to have infection control training,” says Tyler. “If they didn't understand what it took to work within the sanitary enclosure, they didn't work on that part of the project.”

13. Utilities can't be shut off, so have a backup plan. Have backup equipment ready to go because utilities can't be shut down. When new equipment is being connected to existing equipment, you need to have a backup system at the ready to handle the loads in the interim. In the event of accidental power cutoff at a hospital, warns McManus, “It's not an inconvenience, it's life and death.”

14. Anticipate surprises. “It's inevitable something unexpected will happen,” says Tyler. The hospital could ask for construction to be halted immediately despite weeks of planning. You might not be able to find oxygen lines, med-gas lines, or water lines where they should be. You might have to redesign the foundation four times to minimize disruption to hospital operations (as was the case with the Baptist Medical project). “Plan everything in detail and then create a detailed Plan B, Plan C, and Plan D,” says McManus


Related Solutions

Your company has just been awarded a project to renovate part of an existing occupied building....
Your company has just been awarded a project to renovate part of an existing occupied building. Your customer has stated that prior to starting work, all existing conditions are to be reviewed and a plan is to be developed off what you discover for how the work will be conducted so as to not interrupt/disrupt any of the existing occupants and their on-going activities. You decide to look to technology to help accomplish and expedite this task. Identify a technological...
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska....
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are...
A building company has been awarded the contract to undertake the construction works for a multi-storey...
A building company has been awarded the contract to undertake the construction works for a multi-storey office project in a city centre location. A deep basement is to be installed under one half of the building, within a layer of dense gravel. The site is surrounded by public roads and buildings on all sides and it is expected that the water table is extremely close to the ground surface on a year-round basis. You have been asked by the contractor...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a bridge replacement, including 2km approach resurfacing on each side and has placed you and your team in charge. Produce a environmental management plan. Thanks!!
case study: A leading maintenance management company has been awarded the contract for sole long- term...
case study: A leading maintenance management company has been awarded the contract for sole long- term maintenance of an airport including its hangars, control tower, parking and hotel facilities. Being a maintenance manager working for the company, suggest the most suitable ideas for the following situations. questions: 1. List five resources in this project which can have an MTBF or MTTF associated with them. Explain one benefit for each resource. 2. Explain any six benefits this project will experience by...
Mr. Phiri has been awarded a contract of supplying coarse aggregates to Junxi Engineering company who...
Mr. Phiri has been awarded a contract of supplying coarse aggregates to Junxi Engineering company who are working on Lusaka-Ndola dual carriage way. One of the condition for Mr. Phiri to supply the coarse aggregates is having his own quarry site and to employ a material’s Engineer for quality control purpose and technical advice. The material’s Engineer will give guidance on site selection for coarse aggregates which will be presented to the main contractor Junxi Engineering Company. You have been...
CAT Construction has been awarded a contract with the City of Newberg to replace and repair...
CAT Construction has been awarded a contract with the City of Newberg to replace and repair all of the sidewalks in the older residential areas. Based on experience with previous​ projects, CAT feels the project completion time follows a normal distribution with a mean of 60 days and a standard deviation of 10 days. CAT anticipates the net profit for completing the project is​ $100,000. If the company completes the project is less than 40​ days, it will receive an...
Industrial Designs has been awarded a contract to design a label for a new wine produced...
Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 150 hours will be required to complete the project. The firm’s three graphic designers available for assignment to this project are Lisa, a senior designer and team leader; David, a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management specified that Lisa must be assigned at...
Industrial design has been awarded a contract to design a label for a new wine produced...
Industrial design has been awarded a contract to design a label for a new wine produced by Lake View Winery.The company estimates that150 hours will be required to complete the project.The firm's three graphic designers available for to this project are Lisa,a senior designer and team leader; David , a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management has specified that Lisa must be assigned at least 40%of the...
Question 4: Your company has been approached to bid on a contract to sell 10 phone...
Question 4: Your company has been approached to bid on a contract to sell 10 phone booths each year for the next 5 years. Your initial equipment cost will be $5,000. You’ll depreciate this cost straight-line to zero over the next 5 years. You believe the equipment can be repurposed and salvaged for $2,000. You expect fixed costs each year to amount to $500 with variable costs equal to $1,000/booth. Initial NWC needs are $750 and are fully recovered at...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT