Question

In: Statistics and Probability

Industrial Designs has been awarded a contract to design a label for a new wine produced...

Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 150 hours will be required to complete the project. The firm’s three graphic designers available for assignment to this project are Lisa, a senior designer and team leader; David, a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management specified that Lisa must be assigned at least 40% of the total number of hours assigned to the two senior designers. To provide label designing experience for Sarah, the junior designer must be assigned at least 15% of the total project time. However, the number of hours assigned to Sarah must not exceed 25% of the total number of hours assigned to the two senior designers. Due to other project commitments, Lisa has a maximum of 50 hours available to work on this project. Hourly wage rates are $30 for Lisa, $15 for David, and $18 for Sarah.

(a) Formulate a linear program that can be used to determine the number of hours each graphic designer should be assigned to the project to minimize total cost. If an amount is zero, enter “0”. If the constant is "1" it must be entered in the box.
Let L = number of hours assigned to Lisa
D = number of hours assigned to David
S = amount allocated to Sarah
Min L + D + S
s.t.
L + D + S Minimum Lisa
L + D + S Minimum Sarah
L + D + S Maximum Lisa
L + D + S Maximum Sarah
L + D + S = Total Time
L, D, S 0
(b) How many hours should be assigned to each graphic designer?
Hours Assigned
Lisa
David
Sarah
What is the total cost? If required, round your answer to a whole dollar amount.
$
(c) Suppose Lisa could be assigned more than 50 hours. What effect would this have on the optimal solution? Explain. If an amount is zero, enter “0”.
We know that the shadow price for this constraint is ____ , since the constraint is - Select your answer (Binding / Not Binding) -bindingnot bindingItem 29 . Therefore, additional hours for Lisa will - Select your answer (Change / Not change) -changenot changeItem 30 the solution.
(d) If Sarah were not required to work a minimum number of hours on this project, would the optimal solution change?
- Select your answer -YesNoItem 31
Explain.

Solutions

Expert Solution


Related Solutions

Industrial design has been awarded a contract to design a label for a new wine produced...
Industrial design has been awarded a contract to design a label for a new wine produced by Lake View Winery.The company estimates that150 hours will be required to complete the project.The firm's three graphic designers available for to this project are Lisa,a senior designer and team leader; David , a senior designer; and Sarah, a junior designer. Because Lisa has worked on several projects for Lake View Winery, management has specified that Lisa must be assigned at least 40%of the...
CAT Construction has been awarded a contract with the City of Newberg to replace and repair...
CAT Construction has been awarded a contract with the City of Newberg to replace and repair all of the sidewalks in the older residential areas. Based on experience with previous​ projects, CAT feels the project completion time follows a normal distribution with a mean of 60 days and a standard deviation of 10 days. CAT anticipates the net profit for completing the project is​ $100,000. If the company completes the project is less than 40​ days, it will receive an...
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska....
The Scenario: A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are...
A building company has been awarded the contract to undertake the construction works for a multi-storey...
A building company has been awarded the contract to undertake the construction works for a multi-storey office project in a city centre location. A deep basement is to be installed under one half of the building, within a layer of dense gravel. The site is surrounded by public roads and buildings on all sides and it is expected that the water table is extremely close to the ground surface on a year-round basis. You have been asked by the contractor...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a bridge replacement, including 2km approach resurfacing on each side and has placed you and your team in charge. Produce a environmental management plan. Thanks!!
Your company has been awarded a contract for 5-story addition on top of an existing 10-story...
Your company has been awarded a contract for 5-story addition on top of an existing 10-story hospital tower at a Cancer Center located in one of the most populated areas of Dallas, Texas. The existing hospital building is beyond 100% occupancy. The company was hired under a design-build contract to complete the $220 million project. Wind-load testing will be conducted. The wind-resisting system will be modified to redistribute loads on the mat foundation. High-strength concrete will be utilized for the...
case study: A leading maintenance management company has been awarded the contract for sole long- term...
case study: A leading maintenance management company has been awarded the contract for sole long- term maintenance of an airport including its hangars, control tower, parking and hotel facilities. Being a maintenance manager working for the company, suggest the most suitable ideas for the following situations. questions: 1. List five resources in this project which can have an MTBF or MTTF associated with them. Explain one benefit for each resource. 2. Explain any six benefits this project will experience by...
Mr. Phiri has been awarded a contract of supplying coarse aggregates to Junxi Engineering company who...
Mr. Phiri has been awarded a contract of supplying coarse aggregates to Junxi Engineering company who are working on Lusaka-Ndola dual carriage way. One of the condition for Mr. Phiri to supply the coarse aggregates is having his own quarry site and to employ a material’s Engineer for quality control purpose and technical advice. The material’s Engineer will give guidance on site selection for coarse aggregates which will be presented to the main contractor Junxi Engineering Company. You have been...
Fed Ex has been experimenting with a new logistical service. With this new contract, there is...
Fed Ex has been experimenting with a new logistical service. With this new contract, there is a 30% chance that freight in shipping containers will be damaged by the contractor, resulting in a $10,000 loss of total value, on average. Otherwise, the full value of the cargo is realized, $100,000. If Fed Ex is offered an insurance policy to protect them from loss at $4,000 per container, would should they buy the insurance? None of these yes, because the firm...
A new highway is to be constructed with two alternative designs. Design A calls for a...
A new highway is to be constructed with two alternative designs. Design A calls for a concrete pavement costing $90 per foot with a 20-year life; two paved ditches costing $3 per foot each; and three box culverts every mile, each costing $9,000 and having a 20-year life. Annual maintenance will cost $1,800 per mile; the culverts must be cleaned every five years at a cost of $450 each per mile. Design B calls for a bituminous pavement costing $45...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT