In: Finance
Project |
C0 |
C1 |
C2 |
C3 |
C4 |
A |
-5000 |
+1000 |
+1000 |
+3000 |
0 |
B |
-1000 |
0 |
+1000 |
+2000 |
+3000 |
C |
-5000 |
+1000 |
+1000 |
+3000 |
+5000 |
A) Using financial calculator to calculate the NPV at 11%
Project A
Inputs: C0= -5,000
C1= 1,000. Frequency= 2
C2= 3,000. Frequency= 1
I= 11%
Npv= compute
We get, NPV of the project A as -$1,093.90
Project B
Using financial calculator to calculate the Npv at 11%
Inputs: C0= -1,000
C1= 0 frequency=1
C2= 1,000. Frequency= 1
C3= 2,000. Frequency= 1
C4= 3,000. Frequency=1
I= 11%
Npv= compute
We get, Npv of the project B as $3,250.20
Project C
Using financial calculator to calculate the NPV at 11%
Inputs: C0= -5,000
C1= 1,000. Frequency= 2
C2= 3,000. Frequency= 1
C3= 5,000 Frequency= 1
I= 11%
Npv= compute
We get, NPV of the project C as $2,199.75
On the basis of the NPV calculated above, we should choose Project B and C , because they have a positive NPV.
B)
Using financial calculator to calculate the NPV at 16%
Project A
Inputs: C0= -5,000
C1= 1,000. Frequency= 2
C2= 3,000. Frequency= 1
I= 16%
Npv= compute
We get, NPV of the project A as -$1,472.80
Project B
Using financial calculator to calculate the Npv at 16%
Inputs: C0= -1,000
C1= 0 frequency=1
C2= 1,000. Frequency= 1
C3= 2,000. Frequency= 1
C4= 3,000. Frequency=1
I= 16%
Npv= compute
We get, Npv of the project B as $2,681.35
Project C
Using financial calculator to calculate the NPV at 16%
Inputs: C0= -5,000
C1= 1,000. Frequency= 2
C2= 3,000. Frequency= 1
C3= 5,000. Frequency= 1
I= 16%
Npv= compute
We get, NPV of the project C as $1,288.66
On the basis of the NPV calculated above, we should choose Project B and C , because they have a positive NPV.
C) We should choose Project B because it has the highest NPV .
D) Payback period refers to the time period required to recover initial investment.
Project A = Payback period is 3 years
Project B= payback period is 2 years
Project C= payback period is 3 years.
In this case, the payback period is consistent with the Npv decision. But, in general the payback period doesn't take into consideration the time value of money. So, the decision might differ.
E) IRR of Project A
Using financial calculator to calculate the IRR
Inputs: C0= -5,000
C1= 1,000. Frequency= 2
C2= 3,000. Frequency= 1
IRR= compute
We get, IRR of the project A as 0%
IRR of project B
Using financial calculator to calculate the IRR
Inputs: C0= -1,000
C1= 0 Frequency= 1
C2= 1,000. Frequency= 1
C3= 2,000. Frequency= 1
C4= 3,000. Frequency= 1
IRR= compute
We get, IRR of the project B as 76.138%
IRR of project C
Using financial calculator to calculate the IRR
Inputs: C0= -5,000
C1= 1,000. Frequency= 2
C2= 3,000. Frequency= 1
C3= 5,000. Frequency= 1
IRR= compute
We get, IRR of the project C as 25.20%
Yes, the IRR decision is aligned with the NPV decision.
F) Profitability Index of Project A = Initial investment + NPV / Initial Investment
= 5,000 - 1,093.90 / 5,000
= 3,906.10 / 5,000
= 0.78
Profitability Index of Project B = Initial investment + NPV / Initial Investment
= 1,000 + 3,250.20 / 1,000
= 4,250.20 / 1,000
= 4.25
Profitability Index of Project C = Initial investment + NPV / Initial Investment
= 5,000 + 2,199.75 / 5,000
= 7,199.75 / 5,000
= 1.44
Yes, the decisions are aligned with the Npv. This is because a project based on Profitability index can only be selected if the index is more than 1, and it is only possible if Npv is positive.
G) The most general way to choose is by calculating the Net present value, because it take into consideration the time value of money and overcomes the problem of all other neasures.