Question

In: Accounting

Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:         ...

Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:

         2020                           2021

         Costs incurred to date......................................................................      $ 540,000                 $ 875,000

         Estimated costs to complete as of December 31.................         360,000 100,000

         Billings to date.....................................................................................         420,000 950,000

         Collections to date.............................................................................         300,000 700,000

Classical uses the percentage-of-completion method. Gross profit recognized in 2020 was $210,000 (Revenue $750,000; expense $540,000). The 2020 opening balance on LT Contract Asset/Liab is $330,000 DR.

Required:

(a) Calculate gross profit to be recognized in 2021.

(b) What amounts will be reported on the Statement of Financial Position in 2021?

(c) If the estimated costs to complete were $300,000 at the end of 2021, how would your response to part (a) change?

Solutions

Expert Solution

Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:


Related Solutions

Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:         ...
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:          2020                           2021          Costs incurred to date......................................................................      $ 540,000                 $ 875,000          Estimated costs to complete as of December 31.................         360,000 100,000          Billings to date.....................................................................................         420,000 950,000          Collections to date.............................................................................         300,000 700,000 Classical uses the percentage-of-completion method. Gross profit recognized in 2020 was $210,000 (Revenue $750,000; expense $540,000). The 2020 opening balance on LT Contract Asset/Liab is...
A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows: 2020 2021 costs incurred to due $3,000 5,600 estimated costs to complete 2,000 ---------- Billings to date 3,100 7,800 collections to date 1,000 4,400 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows:                                                        2020                         2021 Costs incurred to date                 $3,000 $5,600 Estimated costs to complete         2,000       — Billings to date    4,400                   7,800 Collections to date                       2,000                      4,800 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
Oriole, Inc. began work in 2018 on a contract for $21420000. Other data are as follows:...
Oriole, Inc. began work in 2018 on a contract for $21420000. Other data are as follows:    2018    2019 Costs incurred to date $9180000 $14150000 Estimated costs to complete    $6120000    0 Billings to date    $7060000 $21300000 Collections to date $5060000 $18150000 If Oriole uses the percentage-of-completion method, the gross profit to be recognized in 2018 is
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated...
Deen Construction began a construction project in 2018. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows: 2018 2019 2020 Costs incurred during the year $250,000 $600,000 $190,000 Partial billings $375,000 $500,000 $375,000 Estimated costs to complete $750,000 $212,500 $0 Collections $187,500 $469,000 $593,500 Instructions: 1. Assuming Deen the percentage of completion method: (a) Prepare a schedule that computes the gross profit for 2018 - 2020 (b) Determine...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred costs of $292,500, billed its customer for $213,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $161,340. Prepare Tamarisk’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred costs of $250,000, billed its customer for $200,000, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $178,890. Prepare Cullumber’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060. Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT