Question

In: Accounting

Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred...



Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred costs of $292,500, billed its customer for $213,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $161,340.

Prepare Tamarisk’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No entry" for the account titles and enter 0 for the amounts. Round answers to 0 decimal places, e.g. 5,275.)

No.

Account Titles and Explanation

Debit

Credit

(a)

enter an account title to record the transaction using the percentage-of-completion method

enter a debit amount

enter a credit amount

enter an account title to record the transaction using the percentage-of-completion method

enter a debit amount

enter a credit amount

enter an account title to record the transaction using the percentage-of-completion method

enter a debit amount

enter a credit amount

(b)

enter an account title to record the transaction using the completed-contract method

enter a debit amount

enter a credit amount

enter an account title to record the transaction using the completed-contract method

enter a debit amount

enter a credit amount

Solutions

Expert Solution

Requirement:

No Account Titles and Explanation Debit Credit
a Construction expenses $      309,329
Construction in process $        47,340
Revenue from long term contract $      261,989
b Loss from long term contract $        47,340
Construction in process $        47,340

Working:

Contract price (a) $      406,500
Actual cost to date (b) $      292,500
Estimated cost to complete ( c) $      161,340
Total estimated costs (b) +( c) $      453,840
Estimated gross profit [406500-453840] $       (47,340)
Percentage of completion [292500/453840] 64.45%
Revenue from long term contract [406500*64.45%] $      261,989

Related Solutions

Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred costs of $250,000, billed its customer for $200,000, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $178,890. Prepare Cullumber’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred costs of $280,300, billed its customer for $216,200, and collected $176,500. At December 31, 2017, the estimated additional costs to complete the project total $162,000. Prepare Waterway’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred...
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred costs of $277,100, billed its customer for $215,200, and collected $173,900. At December 31, 2017, the estimated additional costs to complete the project total $161,000. Prepare Swifty’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
During 2020, Tamarisk Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Tamarisk Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $749,360 $1,070,000 Estimated costs to complete 636,300 352,640 –0– Billings to date 302,000 907,000 1,620,000 Collections to date 268,000 815,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 225,700 Gross profit recognized...
A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows: 2020 2021 costs incurred to due $3,000 5,600 estimated costs to complete 2,000 ---------- Billings to date 3,100 7,800 collections to date 1,000 4,400 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows:                                                        2020                         2021 Costs incurred to date                 $3,000 $5,600 Estimated costs to complete         2,000       — Billings to date    4,400                   7,800 Collections to date                       2,000                      4,800 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT