Question

In: Accounting

A company began work in 2020 on a contract for $7,800. Other data are as follows:...

A company began work in 2020 on a contract for $7,800. Other data are as follows:

   

                                                   2020                         2021

Costs incurred to date                 $3,000 $5,600

Estimated costs to complete         2,000       —

Billings to date    4,400                   7,800

Collections to date                       2,000                      4,800

If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?

Solutions

Expert Solution

Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
A Company
Particulars 2020 2021 Note
Contract Price    7,800      7,800 A
Cost Incurred during the year    3,000      2,600 C
Cost Incurred to date    3,000      5,600
Estimated cost to complete    2,800 D
Estimated total cost    5,800      5,600 E=C+B
(Cost Incurred to date+ Estimated cost to complete )
Percentage complete 51.72% 100.00% F=B/E
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized    4,034      3,766 G
Gross Profit/(Loss)    1,034      1,166 H=G-C
Calculation of revenue to be recognized
(Contract Price*Percentage complete)- revenue previously recognized
Year 2020: 51.72% completed. Revenue recognized = 51.72% x $ 7,800 = $ 4,034.
So Construction in Process recorded will be revenue to be recognized i.e. $ 4,034.

Related Solutions

A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows: 2020 2021 costs incurred to due $3,000 5,600 estimated costs to complete 2,000 ---------- Billings to date 3,100 7,800 collections to date 1,000 4,400 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:         ...
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:          2020                           2021          Costs incurred to date......................................................................      $ 540,000                 $ 875,000          Estimated costs to complete as of December 31.................         360,000 100,000          Billings to date.....................................................................................         420,000 950,000          Collections to date.............................................................................         300,000 700,000 Classical uses the percentage-of-completion method. Gross profit recognized in 2020 was $210,000 (Revenue $750,000; expense $540,000). The 2020 opening balance on LT Contract Asset/Liab is...
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:         ...
Classical Ltd. Began work in 2020 on a contract for $ 1,250,000. Other data are:          2020                           2021          Costs incurred to date......................................................................      $ 540,000                 $ 875,000          Estimated costs to complete as of December 31.................         360,000 100,000          Billings to date.....................................................................................         420,000 950,000          Collections to date.............................................................................         300,000 700,000 Classical uses the percentage-of-completion method. Gross profit recognized in 2020 was $210,000 (Revenue $750,000; expense $540,000). The 2020 opening balance on LT Contract Asset/Liab is $330,000...
Oriole, Inc. began work in 2018 on a contract for $21420000. Other data are as follows:...
Oriole, Inc. began work in 2018 on a contract for $21420000. Other data are as follows:    2018    2019 Costs incurred to date $9180000 $14150000 Estimated costs to complete    $6120000    0 Billings to date    $7060000 $21300000 Collections to date $5060000 $18150000 If Oriole uses the percentage-of-completion method, the gross profit to be recognized in 2018 is
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred costs of $292,500, billed its customer for $213,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $161,340. Prepare Tamarisk’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred costs of $250,000, billed its customer for $200,000, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $178,890. Prepare Cullumber’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060. Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During 2020, Crane, Inc. incurred costs of $1,798,560, billed its customers for $1,125,000, and collected $910,000. At December 31, 2020, the estimated additional costs to complete the project total $3,197,440. Prepare Crane’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT