Question

In: Accounting

During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job...

During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$393,900 $760,380 $1,059,000

Estimated costs to complete

616,100 341,620 –0–

Billings to date

299,000 905,000 1,610,000

Collections to date

268,000 818,000 1,421,000

(a)

Your answer is correct.
Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2020

$enter a dollar amountenter a dollar amount

Gross profit recognized in 2021

$enter a dollar amountenter a dollar amount

Gross profit recognized in 2022

$enter a dollar amountenter a dollar amount

SHOW LIST OF ACCOUNTS

SHOW SOLUTION

LINK TO TEXT

Attempts: 2 of 3 used

(b)

Prepare all necessary journal entries for 2021. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. For costs incurred use account Materials, Cash, Payables.)

Account Titles and Explanation

Debit

Credit

enter an account title to record cost of constructionenter an account title to record cost of construction enter a debit amountenter a debit amount enter a credit amountenter a credit amount
enter an account title to record cost of constructionenter an account title to record cost of construction enter a debit amountenter a debit amount enter a credit amountenter a credit amount

(To record cost of construction.)

enter an account title to record progress billingsenter an account title to record progress billings enter a debit amountenter a debit amount enter a credit amountenter a credit amount
enter an account title to record progress billingsenter an account title to record progress billings enter a debit amountenter a debit amount enter a credit amountenter a credit amount

(To record progress billings.)

enter an account title to record collectionsenter an account title to record collections enter a debit amountenter a debit amount enter a credit amountenter a credit amount
enter an account title to record collectionsenter an account title to record collections enter a debit amountenter a debit amount enter a credit amountenter a credit amount

(To record collections.)

enter an account title to recognize revenueenter an account title to recognize revenue enter a debit amountenter a debit amount enter a credit amountenter a credit amount
enter an account title to recognize revenueenter an account title to recognize revenue enter a debit amountenter a debit amount enter a credit amountenter a credit amount
enter an account title to recognize revenueenter an account title to recognize revenue enter a debit amountenter a debit amount enter a credit amountenter a credit amount

(To recognize revenue.)

Solutions

Expert Solution

Amount of Gross profit to be recognised each year

2020 2021 2020
Contract price $        1,610,000 $    1,610,000 $             1,610,000
Less: Estimated cost
Cost incurred to date $            393,900 $        760,380 $             1,059,000
Estimated cost to complete $616,100 $341,620
Estimated total cost $1,010,000 $1,102,000 $1,059,000
Estimated gross profit $600,000 $508,000 $551,000
Percent complete 39% 69% 100%
Revenue recognised in prior years 0 $234,000 $116,520
Total revenue recognized $234,000 $350,520 $551,000
Gross profit recognized $234,000 $116,520 $200,480

Journal entry

PARTICULERS DEBIT CREDI
Construction in process ($760,380-$393,900) $366,480
Materials, cash, payable etc $366,480
(To record cost of construction)
Accounts receivable ($905,000-$299,000) $606,000
Billings on construction in process $606,000
(To record process Billings)
Cash ($818,000-$268,000) $550,000
Accounts receivable $550,000
(To record Collections)
Construction in process $366,480
Construction expense $116,520
Revenue from long-term construction $483,000
($1,610,000*(69%-39%) = $483,000

Related Solutions

During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Prepare all necessary journal entries for 2021. (Credit account...
During 2020, Flint Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Flint Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Larkspur Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job...
During 2017, Culver Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date       $393,900       $760,380       $1,059,000 Estimated costs to complete       616,100       341,620       –0– Billings to date       299,000       905,000       1,610,000 Collections to date       268,000       818,000       1,421,000    Compute the amount of gross profit to be recognized each year, assuming the...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT